Project Management 10

profileP1363
PowerPoint1.pptx

Chapter Eight

Scheduling Resources and Costs

© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.

No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.

Because learning changes everything.®

Where We Are Now

2

© McGraw-Hill Education

Learning Objectives

08-01 Understand the differences between time-constrained and resource-

constrained schedules.

08-02 Identify different types of resource constraints.

08-03 Describe how the smoothing approach is used on time-constrained projects.

08-04 Describe how the leveling approach is used for resource-constrained

projects.

08-05 Understand how project management software creates resource-constrained

schedules.

08-06 Understand when and why splitting tasks should be avoided.

08-07 Identify general guidelines for assigning people to specific tasks.

08-08 Identify common problems with multiproject resource scheduling.

08-09 Explain why a time-phased budget baseline is needed.

08-10 Create a time-phased project budget baseline.

3

© McGraw-Hill Education

Chapter Outline

8.1 Overview of the Resource Scheduling Problem

8.2 Types of Resource Constraints

8.3 Classification of a Scheduling Problem

8.4 Resource Allocation Methods

8.5 Computer Demonstration of Resource-Constrained Scheduling

8.6 Splitting Activities

8.7 Benefits of Scheduling Resources

8.8 Assigning Project Work

8.9 Multiproject Resource Schedules

8.10 Using the Resource Schedule to Develop a Project Cost Baseline

4

© McGraw-Hill Education

Project Planning Process

5

FIGURE 8.1

© McGraw-Hill Education

8.1 Overview of the Resource Scheduling Problem

Resources and Priorities

Project network times are not a schedule until resources have been assigned.

There are always more project proposals than there are available resources.

The project priority team will add a new project only if resources are available.

Cost estimates are not a budget until they have been time-phased.

Once resource assignments have been finalized, you are able to develop a baseline budget schedule for the project.

6

© McGraw-Hill Education

The Resource Scheduling Problem

Resource Smoothing

Involves attempting to even out varying demands on resources by delaying non-critical activities (using slack) to lower peak resource demand and, thus, increase resource utilization when resources are adequate over the life of the project.

Resource-Constrained Scheduling

Occurs when resources are not adequate to meet peak demands. The late start of some activities must be delayed, and the duration of the project may be increased.

7

© McGraw-Hill Education

Types of Project Constraints

Technical or Logical Constraints

Are related to the networked sequence in which project activities must occur.

Resource Constraints

Occur when the absence, shortage, or unique interrelationship and interaction characteristics of resources require a particular sequencing of project activities.

Note that the resource dependency takes priority over the technological dependency but does not violate the technological dependency.

Types of Resources Constraints

People

Materials

Equipment

8

© McGraw-Hill Education

Constraint Examples

9

FIGURE 8.2

© McGraw-Hill Education

8.3 Classification of a Scheduling Problem

Time-Constrained Project

Must be completed by an imposed date.

Time (project duration) is fixed and resources are flexible. If required, resources can be added to ensure the project is completed by a specific date.

Resource-Constrained Project

Assumes the level of resources available cannot be exceeded.

Resources are fixed and time is flexible. If the resources are inadequate, it will be acceptable to delay the project.

Consult a project priority matrix to determine if the project is time- or resource- constrained.

10

© McGraw-Hill Education

8.4 Resource Allocation Methods

Limiting Assumptions

Splitting activities will not be allowed.

Splitting refers to interrupting work on one task and assigning the resources to work on a different task for a period of time, then reassigning them to work on the original task.

Level of resources used for an activity cannot be changed.

Risk Assumptions

Activities with the most slack pose the least risk.

Reduction of flexibility does not increase risk.

The nature of an activity (easy, complex) doesn’t increase risk.

11

© McGraw-Hill Education

Time-Constrained Projects

Must be completed by an imposed date.

Focus on resource utilization.

Require use of resource smoothing techniques that balance demand for a resource.

Leveling (Smoothing) Techniques

Delay noncritical activities by using positive slack to reduce peak demand and fill in the valleys for the resources without delaying the entire project.

Goals of Smoothing Resource Demand

Reduce the peak of demand for the resource

Reduce the number of resources over the life of the project

Minimize the fluctuation in resource demand

Downside of Smoothing Resource Demand

Loss of flexibility that occurs from reducing slack

Creates more critical activities and/or near-critical activities because of slack reduction

12

© McGraw-Hill Education

Botanical Garden

13

FIGURE 8.3

© McGraw-Hill Education

Resource-Constrained Projects

Resources are limited in quantity or availability.

Activities are scheduled using heuristics (rules of thumb) by following the priority rules:

Minimum slack

Smallest (least) duration

Lowest activity identification number

The parallel method is used to apply heuristics.

The parallel method is an iterative process that starts from the beginning of project time and, when the resources needed exceed the resources available, retains activities first by the priority rules.

14

© McGraw-Hill Education

Resource-Constrained Schedule through Period 2-3

15

FIGURE 8.4

© McGraw-Hill Education

Resource-Constrained Schedule through Period 5-6

16

FIGURE 8.5

© McGraw-Hill Education

8.5 Computer Demonstration of Resource-Constrained Scheduling

EMR Project

The development of a hand-held electronic medical reference guide to be used by emergency medical technicians and paramedics

Resource Problem

Only eight design engineers can be assigned to the project due to the shortage of design engineers and commitments to other projects.

The peak demand is 21 design engineers.

17

© McGraw-Hill Education

EMR Project Network View Schedule before Resources Leveled

18

FIGURE 8.6

© McGraw-Hill Education

EMR Project before Resources Added

19

FIGURE 8.7

© McGraw-Hill Education

EMR Project—Time-Constrained Resource Usage View, January 15-23

20

FIGURE 8.8A

© McGraw-Hill Education

Resource Loading Chart for EMR Project, January 15-23

21

FIGURE 8.8B

© McGraw-Hill Education

EMR Project Network View Schedule after Resources Leveled

22

FIGURE 8.9

© McGraw-Hill Education

EMR Project Resources Leveled

23

FIGURE 8.10

© McGraw-Hill Education

The Impacts of Resource-Constrained Scheduling

Reduces slack; reduce flexibility

Increases the number of critical and near-critical activities

Increases scheduling complexity because resource constraints are added to technical constraints

May make the traditional critical path no longer meaningful

Can break the sequence and leave the network with a set of disjointed critical activities

May cause parallel activities to become sequential

Can change activities from critical to noncritical

24

© McGraw-Hill Education

8.6 Splitting Activities

Splitting Tasks

Is a scheduling technique used to get a better project schedule and/or to increase resource utilization.

Involves interrupting the work and sending the resource to another activity for a period of time and then having the resource resume work on the original activity.

Can be useful if the work involved does not include large start-up or shut-down costs.

Is considered a major reason why projects fail to meet schedule.

25

© McGraw-Hill Education

Splitting Activities

26

FIGURE 8.11

© McGraw-Hill Education

8.7 Benefits of Scheduling Resources

Leaves time for considering reasonable alternatives

Cost-time tradeoffs

Changes in priorities

Provides the information needed to prepare time-phased work package budgets with dates

To gauge the impact of unforeseen events

To assess how much flexibility over certain resources

27

© McGraw-Hill Education

8.8 Assigning Project Work

Reasons why we should not always assign the best people the most difficult tasks

Best people: resent to the fact that they are always given the toughest assignments

Less experienced participants: resent to the fact that they are never given the opportunity to expand their skill/knowledge base

Factors to be considered in deciding who should work together

Minimize unnecessary tension; complement each other

Experience: veterans team up with new hires

Future needs: have people work together early on so that they can become familiar with each other

28

© McGraw-Hill Education

8.9 Multiproject Resource Schedules

Problems in a multiproject environment

Overall schedule slippage

Shared resources causes a ripple effect—delays in one project create delays for other projects.

Inefficient resource utilization

Different schedules and requirements by multiple projects create the peaks and valleys in overall resource demands.

Resource bottlenecks

Shortages of critical resources required by multiple projects cause delays and schedule extensions.

29

© McGraw-Hill Education

Managing Multiproject Scheduling

Create project offices or departments to oversee the scheduling of resources across multiple projects

Use a project priority queuing system—first come, first served for resources

Treat individual projects as part of one big project and adapt the scheduling heuristics to this “mega project”

Utilize project management software to prioritize resource allocation

Outsource projects to reduce the number of projects managing internally

Hire temporary workers to expedite certain activities that are falling behind schedule

Contract project work during peak periods when there are insufficient internal resources to meet the demands of all project

30

© McGraw-Hill Education

8.10 Using the Resource Schedule to Develop a Project Cost Baseline

Why a Time-Phased Budget Baseline Is Needed

To determine if the project is on, ahead, or behind schedule and over or under its budgeted costs

To assess how much work has been accomplished for the allocated money spent—the project cost baseline (planned value, PV)

Creating a Time-Phased Budget

Assign each work package to one responsible person or department and deliverable

Compare planned schedule and costs using an integrative system called earned value

Generate cash flow statements and resource usage schedules

31

© McGraw-Hill Education

Direct Labor Budget Rollup ($000)

32

FIGURE 8.12

© McGraw-Hill Education

Time-Phased Work Package Budget (labor cost only)

33

FIGURE 8.13

© McGraw-Hill Education

Two Time-Phased Work Packages (labor cost only)

34

FIGURE 8.14

© McGraw-Hill Education

Patient Entry Project Network

35

FIGURE 8.15

© McGraw-Hill Education

Patient Entry Time-Phased Work Packages Assigned

36

FIGURE 8.16

© McGraw-Hill Education

Project Monthly Cash Flow Statement

37

FIGURE 8.17

© McGraw-Hill Education

Project Weekly Resource Usage Schedule

38

FIGURE 8.18

© McGraw-Hill Education

Key Terms

Heuristics

Leveling

Planned value (PV)

Resource-constrained project

Resource-constrained scheduling

Resource smoothing

Splitting

Time-constrained project

Time-phased budget baseline

39

© McGraw-Hill Education

© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.

No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.

Because learning changes everything.®

www.mheducation.com