PMT 3.3 Case Study: Nightingale Project Crashes and Lags

profilemford
PMT472L3-3CaseStudy-NightingaleProject-PartBTemplate.xlsx

Gantt Chart Schedule

PMT472L 3.3 CASE STUDY: NIGHTINGALE PROJECT - PART B
Crashed Gantt Chart Schedule
What does the crashed schedule look like? Adjust the Part A Gantt chart that you already created to include all duration reductions and lags listed in the Part B assignment instructions.
Activity Duration (days) Start Date Finish Date Predecessor(s) 1/3/17 1/4/17 1/5/17 1/6/17 1/9/17 1/10/17 1/11/17 1/12/17 1/13/17 1/16/17 1/17/17 1/18/17 1/19/17 1/20/17 1/23/17 1/24/17 1/25/17 1/26/17 1/27/17 1/30/17 1/31/17 2/1/17 2/2/17 2/3/17 2/6/17 2/7/17 2/8/17 2/9/17 2/10/17 2/13/17 2/14/17 2/15/17 2/16/17 2/17/17 2/20/17 2/21/17 2/22/17 2/23/17 2/24/17 2/27/17 2/28/17 3/1/17 3/2/17 3/3/17 3/6/17 3/7/17 3/8/17 3/9/17 3/10/17 3/13/17 3/14/17 3/15/17 3/16/17 3/17/17 3/20/17 3/21/17 3/22/17 3/23/17 3/24/17 3/27/17 3/28/17 3/29/17 3/30/17 3/31/17 4/3/17 4/4/17 4/5/17 4/6/17 4/7/17 4/10/17 4/11/17 4/12/17 4/13/17 4/14/17 4/17/17 4/18/17 4/19/17 4/20/17 4/21/17 4/24/17 4/25/17 4/26/17 4/27/17 4/28/17 5/1/17 5/2/17 5/3/17 5/4/17 5/5/17 5/8/17 5/9/17 5/10/17 5/11/17 5/12/17 5/15/17 5/16/17 5/17/17 5/18/17 5/19/17 5/22/17 5/23/17 5/24/17 5/25/17 5/26/17 5/30/17 5/31/17 6/1/17 6/2/17 6/5/17 6/6/17 6/7/17 6/8/17 6/9/17 6/12/17 6/13/17 6/14/17 6/15/17 6/16/17 6/19/17 6/20/17 6/21/17 6/22/17 6/23/17 6/26/17 6/27/17 6/28/17 6/29/17 6/30/17 7/3/17 7/5/17 7/6/17 7/7/17 7/10/17 7/11/17 7/12/17 7/13/17 7/14/17 7/17/17 7/18/17 7/19/17 7/20/17 7/21/17 7/24/17 7/25/17 7/26/17 7/27/17 7/28/17 7/31/17 8/1/17 8/2/17 8/3/17 8/4/17 8/7/17 8/8/17 8/9/17 8/10/17 8/11/17 8/14/17 8/15/17 8/16/17 8/17/17 8/18/17 8/21/17 8/22/17 8/23/17 8/24/17 8/25/17 8/28/17 8/29/17 8/30/17 8/31/17 9/1/17 9/5/17 9/6/17 9/7/17 9/8/17 9/11/17 9/12/17 9/13/17 9/14/17 9/15/17 9/18/17 9/19/17 9/20/17 9/21/17 9/22/17 9/25/17 9/26/17 9/27/17 9/28/17 9/29/17 10/2/17 10/3/17 10/4/17 10/5/17 10/6/17 10/9/17 10/10/17 10/11/17 10/12/17 10/13/17 10/16/17 10/17/17 10/18/17 10/19/17 10/20/17 10/23/17 10/24/17 10/25/17 10/26/17 10/27/17 10/30/17 10/31/17 11/1/17 11/2/17 11/3/17 11/6/17 11/7/17 11/8/17 11/9/17 11/10/17 11/13/17 11/14/17 11/15/17 11/16/17 11/17/17 11/20/17 11/21/17 11/22/17 11/24/17 11/27/17 11/28/17 11/29/17 11/30/17 12/1/17 12/4/17 12/5/17 12/6/17 12/7/17 12/8/17 12/11/17 12/12/17 12/13/17 12/14/17 12/15/17 12/18/17 12/19/17 12/20/17 12/21/17 12/22/17 12/27/17 12/28/17 12/29/17
Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Wed Thu Fri
1 - Architectural decisions 10 1/3/17 1/16/17 None

Report

PMT472L 3.3 CASE STUDY: NIGHTINGALE PROJECT - PART B
Is it possible to meet the October 25, 2017 deadline with all of the duration reductions and lags included?
(Enter response)
What other factors should be considered before finalizing the schedule?
(Enter response)