Plan Program Performance Management 3
· 1. In earned value measurement, earned value is represented by:
· A. BCWS
· B. BCWP
· C. ACWP
· D. None of the above
· 2. If BCWS 5 1000, BCWP 5 1200, and ACWP 5 1300, the project is:
· A. Ahead of schedule and under budget
· B. Ahead of schedule and over budget
· C. Behind schedule and over budget
· D. Behind schedule and under budget
· 3. If BAC 5 $20,000 and the project is 40 percent complete, then the earned value is:
· A. $5000
· B. $8000
· C. $20,000
· D. Cannot be determined
· 4. If BAC 5 $12,000 and CPI 5 1.2, then the variance at completion is:
· A. 2$2000
· B. 1$2000
· C. 2$3000
· D. 1$3000
· 5. If BAC 5 $12,000 and CPI 5 0.8, then the variance at completion is:
· A. 2$2000
· B. 1$2000
· C. 2$3000
· D. 1$3000
· 6. If BAC for a work package is $10,000 and BCWP 5 $4,000, then the work package is:
· A. 40 percent complete
· B. 80 percent complete
· C. 100 percent complete
· D. 120 percent complete
· 7. If CPI 5 1.1 and SPI 5 0.95, then the trend for the project is:
· A. Running over budget but ahead of schedule
· B. Running over budget but behind schedule
· C. Running under budget but ahead of schedule
· D. Running under budget but behind schedule
· 8. The document that describes a work package, identifies the cost centers allowed to charge against this work package, and establishes the charge number for this work package is the:
· A. Code of accounts
· B. Work breakdown structure
· C. Work authorization form
· D. None of the above
· 9. Unknown problems such as escalation factors are often budgeted for using the:
· A. Project manager's charge number
· B. Project sponsor's charge number
· C. Management reserve
· D. Configuration management cost account
· 10. EAC, ETC, SPI, and CPI most often appear in which type of report?
· A. Performance
· B. Status
· C. Forecast
· D. Exception
· 11. If BAC 5 $24,000, BCWP 5 12,000, ACWP 5 $10,000, and CPI 5 1.2, then the cost that remains to finish the project is:
· A. $10,000
· B. $12,000
· C. $14,000
· D. Cannot be determined
· 12. There are several purposes for the 50–50 rule, but the primary purpose of the 50–50 rule is to calculate:
· A. BCWS
· B. BCWP
· C. ACWP
· D. BAC
· 13. When a project is completed, which of the following must be true?
· A. BAC 5 ACWP
· B. ACWP 5 BCWP
· C. SV 5 0
· D. BAC 5 ETC
· 14. In March CV 5 2$20,000, and in April CV 5 2$30,000. In order to determine whether or not the situation has really deteriorated because of a larger unfavorable cost variance, we would need to calculate:
· A. CV in percent
· B. SV in dollars
· C. SV in percent
· D. All of the above
· 15. If a project manager is looking for revenue for a value-added scope change, the project manager's first choice would be:
· A. Management reserve
· B. Customer-funded scope change
· C. Undistributed budget
· D. Retained profits
· 16. A project was originally scheduled for 20 months. If CPI is 1.25, then the new schedule date is:
· A. 16 months
· B. 20 months
· C. 25 months
· D. Cannot be determined
· 17. The cost or financial baseline of a project is composed of:
· A. Distributed budget only
· B. Distributed and undistributed budgets only
· C. Distributed budget, undistributed budget, and the management reserve only
· D. Distributed budget, undistributed budget, management reserve, and profit only
ANSWERS
· 1. B
· 2. B
· 3. B
· 4. B
· 5. C
· 6. A
· 7. D
· 8. C
· 9. C
· 10. C
· 11. A
· 12. B
· 13. C
· 14. A
· 15. B
· 16. D
· 17. B