Corrections on MS project as per the Rubric Instructions.
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
1 0 Online Retail Grocery Store website’s software development
190 days
Mon 10/12/09
Fri 7/2/10
2 1 Project Management 190 days?Mon 4/5/21Fri 12/31/21 3 2 Project Initiation 15 days? Mon 4/5/21Fri 4/23/21 4 2.1.1 Project Charter Review 2 days? Mon 4/5/21Tue 4/6/21 5 2.1.2 Project proposal Evaluation 3 days Wed 4/7/21Fri 4/9/21 4 6 2.1.3 Project Kick off Meeting 1 day Mon 4/12/21Mon 4/12/215 7 2.1.4 Project Vision and Mission
Statement 1 day? Tue
4/13/21 Tue 4/13/21
8 2.1.5 Defining Problem Statement 1 day? Wed 4/14/21Wed 4/14/21 9 2.1.6 Onboarding of project resources 1 day? Thu 4/15/21Thu 4/15/216
10 2.1.7 Documentation of Project Charter 3 days Fri 4/16/21Tue 4/20/219 11 2.1.8 Signatures on Project Charter Team 1 day? Wed 4/21/21Wed 4/21/2110 12 2.1.9 Defining Responsibilties and goals 1 day? Thu 4/22/21Thu 4/22/2111 13 2.1.10 Project Charter Document
completion 1 day? Fri
4/23/21 Fri 4/23/21
12
14 2.1.11 Project Charter Approved M 0 days Fri 4/23/21Fri 4/23/21 15 2.1.12 Project Initiation Phase End 0 days Fri 4/23/21Fri 4/23/21 16 3 Project Planning 45 days? Mon 4/26/21Mon 6/28/21 17 3.1 Review Project Documentation 1 day? Mon 4/26/21Mon 4/26/21 18 3.2 Create a PMP Draft Template 1 day? Tue 4/27/21Tue 4/27/2117 19 3.3 Review the draft PMP with
project team 1 day? Wed
4/28/21 Wed 4/28/21
17,18
20 3.4 Review/Approve PMP with Project Sponsor
1 day? Thu 4/29/21
Thu 4/29/21
21 3.5 PMP Approval M 0 days Thu 4/29/21Thu 4/29/2120 22 3.6 Tool and Technology Selection 2 days? Fri 4/30/21Mon 5/3/21
4/23
4/23
4/29
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 1
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
23 3.6.1 MS SQL 1 day? Fri 4/30/21Fri 4/30/21 24 3.6.2 Dot Net Technology 1 day? Mon 5/3/21Mon 5/3/2123 25 3.6.3 License Approval on Tool
and Technology M 0 days Mon
5/3/21 Mon 5/3/21
26 3.7 Development of Organizational Chart which includes who reports to whom
2 days? Tue 5/4/21
Wed 5/5/21
27 3.8 Template selection of Website 2 days? Thu 5/6/21Fri 5/7/21 28 3.8.1 Template selection for desktop 1 day? Thu 5/6/21Thu 5/6/21 29 3.8.2 Template selection for Mobile 1 day? Fri 5/7/21 Fri 5/7/21 28 30 3.9 Authorization Set up 5 days? Mon 5/10/21Fri 5/14/2127 31 3.9.1 Authorization includes email
set up and permssion to the sharepoint for accessing project relateddocuments
1 day Mon 5/10/21
Mon 5/10/21
32 3.9.2 Uploading Project Documentation
1 day? Tue 5/11/21
Tue 5/11/21
14
33 3.9.3 Creating Project Communication Process
3 days Wed 5/12/21
Fri 5/14/21
13
34 3.10 Application Environment Set-up 7 days? Mon 5/17/21Tue 5/25/21 35 3.10.1 Development Environment
Set up 2 days Mon
5/17/21 Tue 5/18/21
36 3.10.2 SIT Environment Set up 2 days Wed 5/19/21Thu 5/20/2135 37 3.10.3 Production Environment Set up 1 day? Fri 5/21/21Fri 5/21/2136 38 3.10.4 UAT Environment Set up 2 days Mon 5/24/21Tue 5/25/2115,37 39 3.11 Requirement analysis of the
customer 17 days?
Wed 5/26/21
Fri 6/18/21
5/3
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 2
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
40 3.11.1 Getting an idea or overview of the website
2 days Wed 5/26/21
Thu 5/27/21
41 3.11.3 Identification of Stakeholders 1 day? Fri 5/28/21Fri 5/28/21 42 3.11.3 Gather requirements for the
web application 2 days Tue
6/1/21 Wed 6/2/21
41
43 3.11.4 Conducting Meeting and Surveys 1 day Fri 6/4/21 Fri 6/4/21 42 44 3.11.5 Perform Stakeholder Analysis 1 day? Mon 6/7/21Mon 6/7/2143 45 3.11.6 Determing Solution Approach 2 days Tue 6/8/21 Wed 6/9/21 46 3.11.7 Finding new enhanced needs 1 day? Thu 6/10/21Thu 6/10/21 47 3.11.8 Creation requirements draft 1 day? Fri 6/11/21Fri 6/11/2146 48 3.11.9 Document those
requirements into Business Requirement Document and Funtional Requirement Document i.e. FRD & BRD
2 days Mon 6/14/21
Tue 6/15/21
47
49 3.11.10 Documented BRD and FRD M 0 days Tue 6/15/21Tue 6/15/2148 50 3.11.11 Business Analysis Establishment 1 day? Wed 6/16/21Wed 6/16/21 51 3.11.12 Preparation of Requirement
Traceability Matrix D 2 days Thu
6/17/21 Fri 6/18/21
52 3.12 Project Risk Analysis 7 days? Fri 6/18/21Mon 6/28/21 53 3.12.1 Analysis of risks involved 2 days Fri 6/18/21Mon 6/21/21 54 3.12.2 Registering the risks 1 day? Tue 6/22/21Tue 6/22/2153 55 3.12.3 Documenting the risks involved 2 days Wed 6/23/21Thu 6/24/2154 56 3.12.4 Development of WBS 2 days Fri 6/25/21Mon 6/28/2155 57 3.12.5 Work Breakdown Structure
Development M 0 days Mon
6/28/21 Mon 6/28/21
58 3.12.6 Project Planning Phase End M 0 days Mon 6/28/21Mon 6/28/21 59 4 Project Execution 81 days? Tue 6/29/21Wed 10/20/21
6/15
6/28
6/28
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 3
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
60 4.1 Web Design Architure 8 days? Tue 6/29/21Thu 7/8/21 61 4.1.1 Getting Server, memory and
communication interfaces ready
3 days Tue 6/29/21
Thu 7/1/21
62 4.1.2 Building functionality aspects 2 days Fri 7/2/21 Mon 7/5/2161 63 4.1.3 Building visual appearance
as User Interface design 3 days Tue
7/6/21 Thu 7/8/21
64 4.2 Business Analysis 20 days? Fri 7/9/21 Thu 8/5/21 65 4.2.1 Organizing, verifying and
validating the gathered requirements
3 days Fri 7/9/21 Tue 7/13/21
63
66 4.2.2 Analysis of change requirements 2 days Wed 7/14/21Thu 7/15/2165 67 4.2.3 Translation of the business
requirements into technicality for development purpose
2 days? Fri 7/16/21
Mon 7/19/21
66
68 4.2.4 Workshop sessions with vendors 2 days Tue 7/20/21Wed 7/21/21 69 4.2.5 Use Case Diagrams 1 day? Thu 7/22/21Thu 7/22/2168 70 4.2.6 Conduct Unit Testing Activites 2 days Fri 7/23/21Mon 7/26/21 71 4.2.7 Performance Reporting and
Progress tracking 4 days Tue
7/27/21 Fri 7/30/21
72 4.2.8 Working on Change Requests 2 days Mon 8/2/21Tue 8/3/21 73 4.2.9 Updating the change
documentation 2 days Wed
8/4/21 Thu 8/5/21
72
74 4.3 Web application Development & Testing
53 days?
Fri 8/6/21 Wed 10/20/21
75 4.3.1 Review of the requirements or features for development
1 day? Fri 8/6/21 Fri 8/6/21
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 4
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
76 4.3.1 Coding or developing the requirements which meets the acceptance critieria
5 days Mon 8/9/21
Fri 8/13/21
75
77 4.3.2 Performing Unit Testing 2 days Mon 8/16/21Tue 8/17/2176 78 4.3.3 Perform Integration Tesing 2 days Wed 8/18/21Thu 8/19/2177 79 4.3.3 Deploying the features into
development envrionment and system integration test environment
1 day Fri 8/20/21
Fri 8/20/21
78
80 4.3.4 Testing the features in development environment
1 day? Mon 8/23/21
Mon 8/23/21
79
81 4.3.5 Debugging the application 1 day? Tue 8/24/21Tue 8/24/2180 82 4.3.6 Deployment of features into
system integration test environment
1 day Wed 8/25/21
Wed 8/25/21
80
83 4.3.7 Integration of new features in the application
3 days Thu 8/26/21
Mon 8/30/21
82
84 4.3.8 Deployment Accomplished M 0 days Mon 8/30/21Mon 8/30/2183 85 4.3.9 Test plan Review 1 day? Tue 8/31/21Tue 8/31/21 86 4.3.10 Preparing the test plan 3 days Wed 9/1/21Fri 9/3/21 85 87 4.3.11 Preparing test scenarios 2 days Tue 9/7/21 Wed 9/8/21 88 4.3.12 Preparing the test scripts as
per organization template 5 days Thu
9/9/21 Wed 9/15/21
86
89 4.3.13 Executing the test scripts and updating the results i.e. pass or fail
2 days Thu 9/16/21
Fri 9/17/21
88
90 4.3.14 Test result documentation process
1 day? Mon 9/20/21
Mon 9/20/21
89
8/30
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 5
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
91 4.3.15 Loging defects found in the application with bug severirties & priorities
D 2 days Tue 9/21/21
Wed 9/22/21
92 4.3.16 Developers fix the issues D 2 days Thu 9/23/21Fri 9/24/2191 93 4.3.17 Retesting is done 1 day? Mon 9/27/21Mon 9/27/2192 94 4.3.18 Regression testing on newly
deployed features D 1 day Tue
9/28/21 Tue 9/28/21
95 4.3.19 Application's functionality successful in SIT environment
M 0 days Tue 9/28/21
Tue 9/28/21
96 4.3.20 Secuity Based Testing 1 day? Wed 9/29/21Wed 9/29/21 97 4.3.21 Stress Testing 1 day Thu 9/30/21Thu 9/30/2196 98 4.3.22 Performance Testing 1 day? Fri 10/1/21Fri 10/1/2197 99 4.3.23 Load Testing 1 day? Mon 10/4/21Mon 10/4/2198
100 4.3.24 Performing UAT and coording with business users
2 days Tue 10/5/21
Wed 10/6/21
97
101 4.3.25 Making changes before pre-production
1 day? Thu 10/7/21
Thu 10/7/21
102 4.3.26 Performing Pilot testing 2 days Fri 10/8/21Mon 10/11/21100 103 4.3.27 Training the users on the
application usage 3 days Tue
10/12/21 Thu 10/14/21
102
104 4.3.28 Transfer of new database structures
1 day Fri 10/15/21
Fri 10/15/21
105 4.3.29 Database testing 1 day? Mon 10/18/21Mon 10/18/21104 106 4.3.30 Readiness Review of the
application 1 day? Tue
10/19/21 Tue 10/19/21
107 4.3.31 Moving the application into production environment
1 day Wed 10/20/21
Wed 10/20/21
108 4.3.32 Project Execution Phase End M 0 days Wed 10/20/21Wed 10/20/21
9/28
10/20
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 6
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
109 5 Project Monitoring & Controlling Phase 35 days? Thu 10/21/21Fri 12/10/21 110 5.1 Solution towards Application's
issues 11 days?
Thu 10/21/21
Thu 11/4/21
111 5.1.1 Monitoring key server resources for the purpose of load and usage
2 days Thu 10/21/21
Fri 10/22/21
112 5.1.2 Monitoring the response and load time
2 days Mon 10/25/21
Tue 10/26/21
111
113 5.1.3 Monitoring version and configuration changes
2 days Wed 10/27/21
Thu 10/28/21
112
114 5.1.4 Controlling the scope of the deployed requirements
2 days Fri 10/29/21
Mon 11/1/21
115 5.1.5 Tracking the performance of the application
2 days Tue 11/2/21
Wed 11/3/21
116 5.1.6 Information and reporting on end user's issues in production
1 day? Thu 11/4/21
Thu 11/4/21
115
117 5.2 Network traffic monitoring 5 days? Fri 11/5/21Thu 11/11/21 118 5.2.1 Monitoring, tracing and
analyzing traffic data once for all
2 days Fri 11/5/21
Mon 11/8/21
119 5.2.2 Identifying the major users of the network
1 day Tue 11/9/21
Tue 11/9/21
118
120 5.2.3 Troubleshoot the issues 1 day? Wed 11/10/21Wed 11/10/21119 121 5.2.4 Transition support set up for users 1 day? Thu 11/11/21Thu 11/11/21120 122 5.2 Monitoring the response time
of servers 5 days? Fri
11/12/21 Thu 11/18/21
123 5.2.1 Checking the server response time with both physically and virtually
2 days Fri 11/12/21
Mon 11/15/21
124 5.2.2 Reporting from Network and database Administration
2 days Tue 11/16/21
Wed 11/17/21
123
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 7
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
125 5.2.3 Isolating application Issues 1 day? Thu 11/18/21Thu 11/18/21 126 5.3 Identifying user feedback 4 days? Fri 11/19/21Wed 11/24/21 127 5.3.1 Updates on the deployments 1 day? Fri 11/19/21Fri 11/19/21 128 5.3.2 Capturing and documenting
issues in production 2 days Mon
11/22/21 Tue 11/23/21
127
129 5.3.3 Ensuring issues are resolved successfully
1 day Wed 11/24/21
Wed 11/24/21
128
130 5.4 Maintaince of the application 4 days? Mon 11/29/21Thu 12/2/21 131 5.4.1 Minor Bug fixes for new versions 1 day Mon 11/29/21Mon 11/29/21 132 5.4.2 Updating new supporting
frameworks 1 day? Tue
11/30/21 Tue 11/30/21
131
133 5.4.2 Inserting or Importing new data for enhancements
1 day Wed 12/1/21
Wed 12/1/21
132
134 5.4.3 Confirmation on the service level agreements
1 day? Thu 12/2/21
Thu 12/2/21
133
135 5.5 Post production support 6 days? Fri 12/3/21Fri 12/10/21 136 5.5.1 Retesting the new version changes 1 day? Fri 12/3/21Fri 12/3/21 137 5.5.2 Approval of new version changes 1 day? Mon 12/6/21Mon 12/6/21136 138 5.5.3 Version Approval M 0 days Mon 12/6/21Mon 12/6/21137 139 5.5.4 Implementing critical changes 1 day? Tue 12/7/21Tue 12/7/21138 140 5.5.5 Regulatory maintainence
and Compliances 2 days? Wed
12/8/21 Thu 12/9/21
139
141 5.5.6 Residual Error fixes 1 day? Fri 12/10/21Fri 12/10/21 142 5.6.7 Montly Status Meeting 154 days Mon 5/3/21Wed 12/8/21 143 5.6.7.1 Montly Status Meeting 1 1 day Mon 5/10/21Mon 5/10/21 144 5.6.7.2 Montly Status Meeting 2 1 day Tue 6/8/21 Tue 6/8/21 143 145 5.6.7.3 Montly Status Meeting 3 1 day Thu 7/8/21Thu 7/8/21144
12/6
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 8
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
146 5.6.7.4 Montly Status Meeting 4 1 day Mon 8/9/21Mon 8/9/21145 147 5.6.7.5 Montly Status Meeting 5 1 day Wed 9/8/21Wed 9/8/21146 148 5.6.7.6 Montly Status Meeting 6 1 day Fri 10/8/21Fri 10/8/21147 149 5.6.7.7 Montly Status Meeting 7 1 day Mon 11/8/21Mon 11/8/21148 150 5.6.7.8 Montly Status Meeting 8 1 day Wed 12/8/21Wed 12/8/21149 151 5.5.7 Project Monitoring &
Controlling Phase End M 0 days Fri
12/10/21 Fri 12/10/21
152 6 Project Closing Phase 14 days? Mon 12/13/21Fri 12/31/21 153 6.1 Evaluation Reporting 5 days? Mon 12/13/21Fri 12/17/21 154 6.1.1 Collection and Evaluation of
performances of the application
2 days Mon 12/13/21
Tue 12/14/21
155 6.1.2 Formal Acceptability from the users
1 day? Wed 12/15/21
Wed 12/15/21
154
156 6.1.3 Lessons learnt document analysis 2 days Thu 12/16/21Fri 12/17/21 157 6.2 Benfit Analysis Reporting 2 days? Mon 12/20/21Tue 12/21/21 158 6.2.1 Highlighting of web
application features 1 day Mon
12/20/21 Mon 12/20/21
159 6.2.2 Brief summary of final product or service
1 day Tue 12/21/21
Tue 12/21/21
158
160 6.3 Project Status Reporting 7 days? Wed 12/22/21Fri 12/31/21 161 6.3.1 Operational and Support
documentation 1 day? Wed
12/22/21 Wed 12/22/21
162 6.3.2 Phase closure documentation 1 day? Thu 12/23/21Thu 12/23/21161 163 6.3.3 Scope, quality and objective
reporting 2 days Mon
12/27/21 Tue 12/28/21
162
164 6.3.4 Genrating Monthly and weekly status reports
1 day Wed 12/29/21
Wed 12/29/21
165 6.3.5 Successful Project Reporting M 0 days Wed 12/29/21Wed 12/29/21
12/10
12/29
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 9
Project: Online Retail Grocery Sto Date: Sat 4/10/21
ID Task Mode
WBS Task Name M or D Duration Start Finish Predecessors
166 6.3.6 Project Review Documentation 1 day? Thu 12/30/21Thu 12/30/21 167 6.3.7 Release the project Resoures 1 day? Fri 12/31/21Fri 12/31/21166 168 6.3.8 Project Closing Phase End M 0 days Fri 12/31/21Fri 12/31/21 12/31
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Manual Progress
Page 10
Project: Online Retail Grocery Sto Date: Sat 4/10/21