project manager
PM/310 v2
Status Report 1
PM/310 v2
Page 2 of 2
Status Report 1
Project name: Web Application Project
Company: Next Day Solutions
Project manager: Flavia Howard
Date: 4/12/20XX
Project week: Week 4
Project Status Overview
The project is progressing well, with initial milestones completed on schedule. The mobile app design has been successfully wrapped up, and technical architecture setup is finalized. However, there are minor delays in the user interface (UI) design of the login/signup pages, which have caused minor backlogs in development.
Completed
· Requirement gathering and design validation
· UI for landing page, privacy policy, and terms of use
· AWS and GitHub environment setup
Challenges
· UI of login/signup pages delayed due to design dependencies.
· Google Analytics integration blocked due to UI issues.
Overall Health
Yellow (minor issues) – Delays in UI design impact development but are manageable with adjustments.
Open Issues
· Login/signup UI delays
· Impact: Blocking development of authentication modules
· Resolution: Prioritizing this in the next sprint with additional designer support
· Integration with Google Analytics blocked
· Impact: Affects tracking of visitor statistics
· Resolution: Technical leader working on resolving UI-related blockers
Open Risks
Resource Allocation Constraints
· Probability: Medium
· Impact: If UI delays persist, developers may need to be reassigned to other modules, slowing down progress.
Budget Overrun Due to Extra Design Hours
· Impact: Minor additional costs incurred for extra design support
· Mitigation: Monitoring closely and reallocating hours where needed
Deliverables and Milestones
· Completed: Requirement gathering, UI designs for landing page and legal pages
· Pending: Login/signup UI, AWS integration, admin dashboard UI
Key Performance Indicators (KPIs)
· Sprint velocity: 85% completion rate for Sprint 2
· Budget adherence: 5% over budget due to additional design work
· Issue resolution time: Average resolution time 3–4 days (slower than target 2 days)
· Feature completion rate: 80% for Sprint 2
Conclusion: Early UI design dependencies should be resolved before backend development begins.
Adapted with Permission from MyEducator. Copyright 2025 by University of Phoenix. All rights reserved.
Adapted with Permission from MyEducator. Copyright 2025 by University of Phoenix. All rights reserved.