Acoustics and Architecture

profileHayzel
PH2DrainageTutorial.pptx

Building Services Applications

Drainage Review

Presentation by

Chris

Puttick

Senior Lecturer Building Services

January 2020

Worked Example

In this example we will focus on working through the design using Part H of the building regulations. Considerably more detail is provided within the BS however at this level the regulations are adequate.

Worked Example

Break out group 1

Draw the pipework layout

Draw the schematic

Work out your demand units through the pipe

Convert to flow rates

Hints:

Consider the impact of ventilated and unventilated branches.

Consider where you are going to locate your vertical stacks

Assumptions:

You are dropping directly into the ground

Worked Example

Layouts

Worked Example

10 WCs

Layouts

8 WHBs

1 WC +

1 WHB

Worked Example

From Building Regulations Part H:

Considering WCs

Layouts

Worked Example

10 WCs in total.

If unvented then max of 8 allowed

Also a door in the way of the two groups of WCs, which would get in the way of the pipe!

=>

Split into 2 groups of 5

Each group drops into a vertical soil pipe

This can go anywhere behind the WCs, final location most likely dependant on what’s going on above and below. Note the hidden wall behind, this is typical

Layouts

Worked Example

From Building Regulations Part F:

Considering WHB

Layouts

Worked Example

8 WHBs in total

4 max on each run

=>

Again split into 2 groups of 5

Each group drops into a vertical soil pipe

This can go anywhere behind the WHBs, final location most likely dependant on what’s going on above and below.

Layouts

Worked Example

Another option is to take both sides into the centre

This is down to you as a designer!

Layouts

Worked Example

In both cases there is a ‘hidden wall’ behind an IPS system (where the toilet cistern can be hidden).

This also acts as a space to hide this low level waste pipework and is a normal solution for WCs.

Layouts

Worked Example

Finally the little WC.

Firstly where should the vertical waste pipe go?

Layouts

Worked Example

In the IPS on the other side of the wall would work well

Layouts

Worked Example

Which could also be used for the WHBs, so remove the extra one

Layouts

Worked Example

What if we add two more WHBs?

Too many to take into the stacks at either end….so what do we do?

Layouts

Worked Example

What if we add two more WHBs?

Too many to take into the stacks at either end (limited to 4)

….so what do we do?

Layouts

Worked Example

OPTION 1

Put in an additional stack

Layouts

Worked Example

OPTION 2

Referring back to Part H…..page 10

Layouts

Worked Example

OPTION 2

Ventilated pipework to serve 5 No WHBs

Layouts

Worked Example

Label your vertical stacks to help with referencing your schematics

Layouts

2

1

4

3

Worked Example

Break out group 2

Draw the pipework layout

Draw the schematics

Work out your demand units through the pipe

Convert to flow rates

Hints:

Consider the impact of ventilated and unventilated branches.

Consider where you are going to locate your vertical stacks

Assumptions:

You are dropping directly into the ground

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

Start with your WCs and the vertical stack pipe

Show the levels the pipe goes through the building

(from the roof to the ground)

1

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

Connect up the WCs

1

Worked Example

Off to the main below ground drainage system

Level 1

Level 2

Roof

Ground

Possible other connections on level 2 (not shown on this example

Schematics

Finish off the schematic

Roof Cowl, allow air in to vent but stop rain coming in

1

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

It needs to be ventilated!

In this case I’m going to use an AAV

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

The height of the AAV should be above the level of the WHB. This means if there is a blockage in the pipe you will see it come out of the WHBs not leaking out the AAVs (which may well be hidden….you’ll never know it’s blocked...until you can smell it….)

Worked Example

So we need an AAV at the end of both the runs of the WHBs, which will need access

Should show this on your layout!

Worked Example

Remember that also has the accessible WC connected to it

Schematics

3

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

These are run on separate horizontal pipes with their own connections to the SVP to reduce any back pressure impact.

Worked Example

Break out group 3

Draw the pipework layout

Draw the schematics

Work out your demand units through the pipe

Convert to flow rates

Hints:

Remember to add DUs not flow rates

Work out the overall demand unit per soil stack

Assumptions:

Assume you have the same setup on the floor above

Worked Example

Off to the main below ground drainage system

Level 1

Level 2

Roof

Ground

Schematics

Roof Cowl, allow air in to vent but stop rain coming in

1

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

AAV

Worked Example

Demand Units and flow rate

Worked Example

Level 1

Level 2

Roof

Ground

Schematics

3

AAV

AAV

0.3

0.3

0.3

0.3

0.3

0.3

0.3

0.3

0.3

0.3

0.3

0.3

1.5

1.5

= 0.7 x 6.6 = 4.62 l/s

Do this for all stacks