| Performance Report: |
| Project: | Schlumberger - Montney Onshore Project |
| Name: |
| Date: | 29-Nov-20 |
| ID | LEVEL 1 TASK | LEVEL 2 TASK | LEVEL 3 TASK | DURATION | BASELINE | ACTUAL WORK | ACTIVITY NOTES |
| 1 | Geological Investigation |
| 1.1 | | GeoReam (www.slb.com, n.d.) |
| 1.1.1 | | | Drilling Site Excavation | 21 Days | 84 Hours | 98 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.2 | | | Flooring Bed Set-up | 14 Days | 36 Hours | 60 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.3 | | | Resolve Geological Issues | 14 Days | 24 Hours | 36 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.4 | | | Inspection and documentation | 14 Days | 12 Hours | 6 Hours |
| 1.2 | | Pressurization |
| 1.2.1 | | | Regulating Temperature | 7 Days | 24 Hours | 16 Hours |
| 1.2.2 | | | Regulating Pressure | 7 Days | 24 Hours | 16 Hours |
| 1.2.3 | | | Regulating Depth | 7 Days | 24 Hours | 16 Hours |
| 1.2.4 | | | Inspection and documentation | 7 Days | 24 Hours | 8 Hours |
| 2 | Well Foundation |
| 2.1 | | Wall |
| 2.1.1 | | | Floor Setting | 14 Days | 60 Hours | 72 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.2 | | | Concrete Pouring | 7 Days | 36 Hours | 48 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.3 | | | Rebar Placement | 7 Days | 36 Hours | 48 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.4 | | | Inspection and documentation | 7 Days | 24 Hours | 10 Hours |
| 2.2 | | Slab |
| 2.2.1 | | | Rebar Placement | 7 Days | 36 Hours | 42 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.2 | | | Concrete Pouring | 7 Days | 36 Hours | 40 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.3 | | | Concrete Float Joint (www.slb.com, n.d.) | 7 Days | 36 Hours | 48 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.4 | | | Inspection and documentation | 7 Days | 24 Hours | 8 Hours |
| 3 | Framing |
| 3.1 | | Wall |
| 3.1.1 | | | Support Wall (1) | 14 Days | 48 Hours | 54 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.2 | | | Support Wall (2) | 14 Days | 48 Hours | 54 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.3 | | | Support Wall (Firming) | 14 Days | 60 Hours | 66 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.4 | | | Inspection and documentation | 7 Days | 24 Hours | 6 Hours |
| 3.2 | | Slab |
| 3.2.1 | | | Rebar Placement | 7 Days | 36 Hours | 44 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.2 | | | Concrete Pouring | 7 Days | 36 Hours | 42 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.3 | | | Concrete Float Joint (www.slb.com, n.d.) | 7 Days | 36 Hours | 52 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.4 | | | Inspection and documentation | 7 Days | 24 Hours | 8 Hours |
| 4 | Well Drilling |
| 4.1 | | Rigs |
| 4.1.1 | | | Rig set up (15) | 35 Days | 120 Hours | 140 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.1.2 | | | Rig computerization | 35 Days | 80 Hours | 72 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.3 | | | Begin rig run | 35 Days | 120 Hours | 130 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.4 | | | Inspection and documentation | 20 Days | 24 Hours | 12 Hours |
| 4.2 | | Drilling |
| 4.2.1 | | | Site set up (15) | 35 Days | 120 Hours | 148 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.2 | | | Rig installation | 35 Days | 120 Hours | 156 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.3 | | | Begin drilling run | 35 Days | 120 Hours | 132 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.4 | | | Inspection and documentation | 35 Days | 24 Hours | 12 Hours |
| 5 | Turnkey Deliverable |
| 5.1 | | Interrelationship of rigs |
| 5.1.1 | | | Connect rigs 1 to 5 | 14 Days | 48 Hours | 52 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.2 | | | Connect rigs 5 to 10 | 14 Days | 48 Hours | 60 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.3 | | | Connect rigs 10 to 15 | 14 Days | 48 Hours | 58 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.4 | | | Inspection and documentation | 14 Days | 24 Hours | 8 Hours |
| 5.2 | | Technology |
| 5.2.1 | | | Develop software solution | 84 Days | 160 Hours | 120 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.2 | | | Software testing in lab environment | 21 Days | 80 Hours | 80 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.3 | | | Software installation | 7 Days | 16 Hours | 21 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.4 | | | Test and run software | 21 Days | 80 Hours | 80 Hours | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.5 | | | Training and documentation | 21 Days | 40 Hours | 40 Hours |