Need Urgent Help - Project Management Performance Report

profilepurplebed
PerformanceReportingLS.xlsx

Performance Reporting - Montney

Performance Report:
Project: Schlumberger - Montney Onshore Project
Name:
Date: 29-Nov-20
ID LEVEL 1 TASK LEVEL 2 TASK LEVEL 3 TASK DURATION BASELINE ACTUAL WORK ACTIVITY NOTES
1 Geological Investigation
1.1 GeoReam (www.slb.com, n.d.)
1.1.1 Drilling Site Excavation 21 Days 84 Hours 98 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
1.1.2 Flooring Bed Set-up 14 Days 36 Hours 60 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
1.1.3 Resolve Geological Issues 14 Days 24 Hours 36 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
1.1.4 Inspection and documentation 14 Days 12 Hours 6 Hours
1.2 Pressurization
1.2.1 Regulating Temperature 7 Days 24 Hours 16 Hours
1.2.2 Regulating Pressure 7 Days 24 Hours 16 Hours
1.2.3 Regulating Depth 7 Days 24 Hours 16 Hours
1.2.4 Inspection and documentation 7 Days 24 Hours 8 Hours
2 Well Foundation
2.1 Wall
2.1.1 Floor Setting 14 Days 60 Hours 72 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.1.2 Concrete Pouring 7 Days 36 Hours 48 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.1.3 Rebar Placement 7 Days 36 Hours 48 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.1.4 Inspection and documentation 7 Days 24 Hours 10 Hours
2.2 Slab
2.2.1 Rebar Placement 7 Days 36 Hours 42 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.2.2 Concrete Pouring 7 Days 36 Hours 40 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.2.3 Concrete Float Joint (www.slb.com, n.d.) 7 Days 36 Hours 48 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
2.2.4 Inspection and documentation 7 Days 24 Hours 8 Hours
3 Framing
3.1 Wall
3.1.1 Support Wall (1) 14 Days 48 Hours 54 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.1.2 Support Wall (2) 14 Days 48 Hours 54 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.1.3 Support Wall (Firming) 14 Days 60 Hours 66 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.1.4 Inspection and documentation 7 Days 24 Hours 6 Hours
3.2 Slab
3.2.1 Rebar Placement 7 Days 36 Hours 44 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.2.2 Concrete Pouring 7 Days 36 Hours 42 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.2.3 Concrete Float Joint (www.slb.com, n.d.) 7 Days 36 Hours 52 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
3.2.4 Inspection and documentation 7 Days 24 Hours 8 Hours
4 Well Drilling
4.1 Rigs
4.1.1 Rig set up (15) 35 Days 120 Hours 140 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.1.2 Rig computerization 35 Days 80 Hours 72 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.2.3 Begin rig run 35 Days 120 Hours 130 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.2.4 Inspection and documentation 20 Days 24 Hours 12 Hours
4.2 Drilling
4.2.1 Site set up (15) 35 Days 120 Hours 148 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.2.2 Rig installation 35 Days 120 Hours 156 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.2.3 Begin drilling run 35 Days 120 Hours 132 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
4.2.4 Inspection and documentation 35 Days 24 Hours 12 Hours
5 Turnkey Deliverable
5.1 Interrelationship of rigs
5.1.1 Connect rigs 1 to 5 14 Days 48 Hours 52 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.1.2 Connect rigs 5 to 10 14 Days 48 Hours 60 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.1.3 Connect rigs 10 to 15 14 Days 48 Hours 58 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.1.4 Inspection and documentation 14 Days 24 Hours 8 Hours
5.2 Technology
5.2.1 Develop software solution 84 Days 160 Hours 120 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.2.2 Software testing in lab environment 21 Days 80 Hours 80 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.2.3 Software installation 7 Days 16 Hours 21 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.2.4 Test and run software 21 Days 80 Hours 80 Hours Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues.
5.2.5 Training and documentation 21 Days 40 Hours 40 Hours