PDM / CPM / AON
Exercise Activity Preceding Activity Duration
A. N/A 5
B. N/A 8
C. A, B 6
D. C 7
E. D 3
F. D 4
G. F 9
H. E, G 4
• Draw the Network Diagram using the Critical Path Method
• Determine Critical Path
• Which task is not on the CP?
1. B
2. D
3. F
4. A