Create Construction company
Part 11
Scenario 1
The agreement between the Prime Contractor and Sub-Contractor was to follow the contract documents. Although the plans originally called for Grade 60 steel for the reinforcement of the building footings, the Special Provision says to use Grade 40. Since the Special Provision is an amendment to the original contract documents, regardless of what the plans say, the Sub-Contractor should abide by the contract documents, assuming the plans were not part of them. Assuming the Grade 40 steel was available, if the Sub-Contractor still chose to use Grade 60, they would either need to pay for the price difference in materials themselves or correct their mistake by replacing the Grade 60 steel with Grade 40 as the Special Provision called for. If the Grade 40 steel was not available, then the Sub-Contractor should have confirmed with the Prime Contractor that it was acceptable to use Grade 60 before doing so.