Executive Summary

Airbus is an important airlines company in the world and its product Airbus A380 is

the largest passenger aircraft in recent years. The Airbus A380 project is designed to

against American Boeing aircraft. However, there are several issues happened during

the implementation of the Airbus A380 project. This report starts with the problem

definition of technology, communication, culture, and management. Moreover, after

the problem definition is the analysis of issues. The following part after the root cause

analysis is the possibility of solutions and makes a project proposal, and project plan

with SWOT and stakeholders analysis. At the end of this report for a conclusion is

going to combine with all analysis and will make recommends for this project.

The various obstacles like cultural barriers, negative management, and lack of

communication have been addressed in this report. The report has also provided

solutions and intends to tackle these obstacles.

! 3

1.Introduction

Airbus A380, which is the most complex aircraft in recent years with two full desks

and the space for carrying 850 passengers. A380 is the largest passenger aircraft and

plays a major role in the aerospace industry. There were 4 countries such as Germany,

Span, England, and France joined Airbus 380 projects. Throughout the cooperation

between these countries, this project was delivered profitable in the end. However,

there were several issues and failure decisions during the implementation and

production route. The main issues which we will address in this report are the gap of

technology problem, the difficulties of communication, the differences of culture

between countries, and management problem. These problems caused the Airbus

A380 program delayed and over budget.

2.Problem Definition

Besides the negative influences of the projects themselves, the project unfinished

time occasioned serious social problems. Here, we will identify the problems and

explain them.

2.1!Delay!the!schedule!of!the!project! !

Airbus A380 construction will ease the traffic pressure, and Airbus A380 is the most

aircraft flying today. However, delivery of Airbus A380 delayed leads to not improve

the traffic problems. For example, originally schedule for delivery of this project in

2006. However, entry service of the aircraft was delayed by almost two years. Airbus

announced the first delay in 2005 and noticed other aircraft companies that deliveries

would be delayed for six months because of the difficulties of production speed. And

in June 2006, Airbus announced the additional delay that deliveries would be delayed

by six to seven months. In October 2006, new Airbus CEO Christian Streiff

announced a third delay. The delay increased the earnings shortfall projected by

Airbus through 2010 to 4.8 billion.

! 4

!

2.2!Snowballing!costs!and!over!budget!

Airbus A380 construction delay causes a significant economic loss. Such as the

previous example, the project was finished after four years of delays. The project

manager focuses on the atmosphere in different parts of the organization rather than

how to build the aircraft in the best way. Overly aggressive schedule caused the time

pressure of the schedule. Moreover, at the end of this project was several billion over

budget. Moreover, Airbus A380 construction generally belongs to the government

investment. The government finance deficit could affect social welfare programs.

2.3!HighAlevel!Resignation!and!employee!turnover!

The deliveries delay several times and the incorrect decision making during the

project caused a 26 percent drops in the share price of Airbus’ parent. EADS. The

huge financial burden leads to the employees turnover and the high-level managers

punished. For instant, these issues caused the departure of EADS CEO Noël Forgeard,

Airbus CEO Gustav Humbert, and A380 programmer manager Charles Champion.

2.4!Several!companies!had!to!cancel!order!forms!and!be!implicated.!

Related companies were directly or indirectly involved in this project delayed. For

example, Air Transport Word states Malaysia Airlines and International Lease

Finance Corporation (ILFC) canceled the order forms because of the deliveries delay.

Moreover, in November 2006, FedEx canceled 10 A380-800F aircraft order forms

and steering Boeing ordered 15 Boeing 777-200 Freighters. UPS announced they

were considered to cancel 10 A380 aircrafts in March 2007.

3. Root Cause Analysis

Although this project was successful in the end, Airbus A380 project was delayed and

over budget. It had several issues during the implementation and production phase to ! 5

result in the plan unfinished on time. There are 4 main reasons for this project:

communication, technology, culture, and individual. The fish-bone diagram will

show the possible roots, and each reason will be explained deeply as follows:

! ! ! ! ! ! ! ! ! Lack!of!communication!

! ! ! ! ! ! ! ! Language! ! ! ! ! ! ! ! Ineffective! ! ! ! communication! !

The! ! different! ! requirements! !

of!product!

! ! ! ! ! ! ! Lack! ! of! ! technology! ! ! ! ! ! ! ! ! ! verification! !

! ! ! ! ! Mode!of!fixed!thinking!

! ! ! Bias! ! Time!difference!

!

!Wrong!decision! ! !Lack!of!management!capacity! ! ! ! ! ! Overconfident! !

3.1!Communication! !

Ineffective communication and lack of communication are the first primary problem to lead the project delay.! All! departments! in! Organizational! structure! are! too!

independent.! It! led! to! reducing! communication! opportunity.! A380! manufacturing!

for! the! global! tender! parts! production! including! over! 40!

countries!and!hundreds!of!manufacturers.!Each!aspect!of!Airbus!is!independent! and!

different! work,! but! if! one! part! existed! a! little! error,! it! will! affect! the! entire!

project!chain!and!delivery!time.!The!four!main!countries!were!allocated!different! task,!

and! they! have! their! own! independent! supplier! of! technical! personnel,! accounting,!

legal! adviser,! which! led! to! difficult! to! carry! out! effective! communication! between!

members! of! different! work! even! if! under! the! same! project.! Firstly,! it! led! to!

inefficient! communication! and! the! project! extension! of!

! 6

the!development! cycle.! Secondly,! it! also! restricts! technological! communication,!

so!that!engineers!in!different!countries!even!use!incompatible!software.!

3.2!Individual!

As for the individual aspect, wrong decision and overconfident were all the frequent

weaknesses of the leaders, which result in the project facing many difficulties in the

implementation stage of the Airbus A380 project. In fact, for the cultural side, a

project manager should more effectively opt team members that match both the team

culture, the project, roles and responsibilities when he or she better to understand the

human nature and personalities of these individuals. However, there is a real story:

the project manager of Airbus A380 attempted to move the German designers on to

the same CAD system as the French, however, the manager did not consider the

cross-culture problem. It led the manager met a wall of resistance and the designers

had a conflict when they designed the aircraft. Besides, this issue led to losing his job

at a later time. In addition, for the technology field, the project manager believed that

electrical system designed in Germany would be compatible with the air-frame

components designed in France. However, he did not consider that CATIA version 4

which Germany used was not matched with version 5 which France used. This issue

caused the project delay and engineers needed to design the electrical system again.

Failure management from project managers will cause project delay, over budget, or

a fail the project. Project managers have to manage project team members effectively.

3.3!Culture!

The third main problem comes from the different culture. At first, Airbus A380

project was implemented by four countries. Different cultural background brings the

conflict of communication and lack of interactivity. Multiple languages and time

difference will produce risks when they transform some important information to

other countries. In addition, narrow-mind thinking of different units set up a culture

within the organization, which led to isolation among groups. Therefore, there was no

! 7

effective communication between project teams and numerous processes and

exercises were unchallenged.

According to the reading from the course, culture is a fuzzy set of attitudes, beliefs,

behavioral norms, and basic assumption and values that are shared by group of

people, and that influence each members' behavior and his/her interpretations of the

meaning of other people's behavior. In Airbus A380 project case, in the early period,

European governments cooperated all aerospace industries in every country in

Europe to compete with the US based Boeing Commercial Aircraft Company.

Because of their different backgrounds, different parts of the organization inherit

different corporate cultures, management styles and systems. The cultural differences

could be caused serious irreversible consequences for Airbus A380, even if only a

little difference could be still deeply entrenched. The personal rivalries and national

pride from project team members caused the project implementation difficulties and

delay the project schedule.

3.4!Technology!

The fourth main reason is about the technology field. To operate the aircraft with the

mental airframe. Engineers need to integrate the complex wiring system which

threading through the aircraft. Airbus A380 is the most complex electrical system

with 530 kilometers wires, cables and wiring harnesses weave throughout the

airframe. And more than 100,000 wires and 40,300 connectors operating 1,150

separate functions. After the first prototype completed in France, engineers found a

problem and it is not an isolated problem. After the installation of the wires, they

found out that the wires were too short even though they had been manufactured to

specification the wires and harnesses. It is hard to pull cables to make them suitable

even though cables are only a few centimeters short. Engineers realized that the

problem of short wires will influence the whole design of the airplane. In addition,

the Computer Aided Design (CAD) software which design group working on the

project was different in every country. The designers of German and Spanish had

! 8

used CATIA version 4, however, British and French design teams had used CATIA

version 5. The difference between CATIA Vision4 and vision5 was not a simply

evolution. Vision 5 was a complete rewrite software. Unfortunately, drawings of

electrical system that Germany designed did not suitable with the air-frame

components designed in France.

4. Possible Solution

Based on the root causes analyzed before, there were some corresponding measures

to solve the problems. Each problem is provided several solutions, which are related

to communication, culture, technology and individual separately. Then sum up these

one-sided solutions to contribute to a finial systematic solution.

4.1!Solutions for communication problems

For the large multinational project, using second languages or hiring translators is

inevitable. However, in this case, it is likely misunderstanding in communication

because there are at least four languages. To reduce the probability of

misunderstanding, using a unified language like English could be a solution.

However, it does not need everyone speaking English. As long as there are no less

than two staffs that are good in English in each department, the language obstacle is

not a problem. In this way, the staffs could understand the stakeholders from other

countries and explain to their internal members. Moreover, they know more

professional knowledge than translators, so they can convey information more easily.

Language is neither the only problem of communication nor the significant problem.

Ineffective communication or lack of communication is more serious. Because the

purpose of communication is sharing information and understanding each other, how

to achieve the purpose is the key point of solving the communication problem.

Expressing ideas clearly are the basis of sharing information. Some programmers are

good at programming but do not know how to express their thoughts. This kind of ! 9

employee could improve communication skills by practicing or joining training. In

addition to the efforts of their own, organizations could hire a supervisor to discover

and listen to their problems. Supervisors could not only provide help to the

employees that initiatively seek help, but also discover the ignored problems then

solve them. Moreover, supervisors could collect all problems, analyze the common

features and find solutions. Then they could be publicly a help manual including the

common problems and solutions to all internal members. Another responsibility of

supervisors is supervising and reminding all employees pay attention on

communication issues. If an employee makes a mistake, the supervisor could correct

it in time.

4.2!Solutions for individual problems

Individual problems also cannot be ignored, which includes both personal ability and

personal attitude. For personal ability, before start a project, it is necessary to

measure the ability of all employees. Then the managers will know their levels and

put them at the accurate positions. Another solution is training them to raise their

ability to meet the work requirement. Personal attitude is difficult to change; no

matter it is positive or negative. However, it can be controlled or limited to ensure the

attitude will not cause bad effects on the project. For example, training employees

how to relieve stress, how to work with team members, how to negotiate with

stakeholders and so on. In addition, rules and regulations are required to quantitative

all tasks. If employees cannot finish their work in time, they will be punished.

4.3!Solutions for cultural problems

Culture is another kind of language, so understanding the culture from other countries

or organizations is required. Because culture and belief are difficult to change, the

only way of avoiding cultural conflict is understanding the culture from each other.

All managers and staffs have to know the culture difference among four countries.

Therefore, it is necessary to implement a cultural training for everyone. In the ! 10

training, all members will know the different cultures firstly, then they have to accept

the difference and know how to avoid conflict. Because the members from different

countries have to work together, if someone ignores the difference of culture or do

not know how to handle it, there will be contradictory in a team or organization. To

solve this problem, there have to make policies to avoid culture resistance and

prejudice, which include norms of behavior and punishment. If all members are asked

to follow the policies, then cultural conflicts will be reduced.

4.4!Solutions for technology problems

Technology is the core of the project, so the unmatched technology has to be solved.

To a certain extent, using unmatched technology is also a problem of lacking

communication. But if there is no communication problem, some issues may still

occur related to technology, for example, outdated technology or low production

efficiency. The solutions are not complete without communication skills and

management methods. The outdated technology from one country could be replaced

by other country’s advanced technology and low efficiency country could learn the

efficient methods from other countries. As long as they can effectively communicate

and correctly manage technology transfer and technical training, it will increase the

effectiveness of the project. Moreover, in a project, everything is important even an

electric wire or screw. Therefore all information required to be shared with each other.

Although it looks too much trouble, it will avoid mismatching technology.

4.5!The systematic solution

Summarizing all solutions above, there are two main solutions to address all issues.

One is set up a department of supervisor, which could make policies to avoid cultural

conflict, estimate ability of each organization and employee, ensure employees’ work

efficiency, support help for employees and understand stakeholder dynamics

condition. The other one is training for all level internal members. The training

includes technology coaching, communication skills, culture knowledge and so on. ! 11

The two solutions are both benefits to the project. Only choosing one of them could

increase project efficiency. Certainly, they can be applied together, which is more

effective to optimize the project.

5 Proposal and project plan

5.1 Vision and Purpose

Airbus a380 is a large and complex project that is related to many countries,

including four countries in project planning and implementation and some other

countries in products purchasing. Meanwhile, it is also a high-tech project that

requires employees having high level technology skills in producing a product.

Therefore, it is a big challenge for the project manager to effectively and efficiently

implement the project in the expectation of all stakeholders and controlling it in the

schedule, while to ensure the quality of the airplane in security and establish good

relations among the cooperators. According to the failure experience of Airbus a380

in the past, there are some problems in terms of interpersonal communication and

leadership of project management, so some strategies should be proposed in this

aspect, in order to reduce the problems being result of chaos and ineffective human

resource management and promote the project success.

Firstly, a new structure of management should be established instead of the old one.

Division of Supervisor system and Project Manager Training system are the two core

departments should be built and added in the project system, which can be looked as

a hub of four countries communication being given a lot of vital functions in project

execution process to help project manager manage the project. Secondly, some

methodologies will be used in feasibility analysis. The methods of SWOT analysis,

stakeholder analysis, motivation, negotiation, team building, communication plan are

in order to give the reasons why the two system could be in operating.

In summary, Division of Supervisor system includes five offices: Supervision Policy Office, Supervisor Examination Office, Supervisor Consultant Office and Customer ! 12

Office. The staffs of this system are from four countries, including France, Germany,

Spain and the UK, and each office has its special function. The purpose of building

this system is addressing the weakness of the old organization structure. The

functions of Supervision Policy Office are collecting and finding the difference in

policies, laws and market regulations from different countries, then the

representatives from different countries do a negotiation internal to find an outcome

that be accepted by four countries work teams, and make a regulation for all project

team members as a guidance regulating the behavior of employees. Moreover, the

project manager of this office will set up the training plan for employees based on

their results of professional skills’ testing, then the employees need to do the training

to make up for their deficiencies in skills. The functions of Supervisor Examination

Office are in the following. One is to ensure every region being observed the

common policies and rules. One is checking and evaluating the career performance of

employees and collecting the employers’ requirement and feedback, after that making

an examination report to identify the issues and provide possible solutions. The

functions of Supervisor Enforcement are three. They are guiding employees to

complete their work, providing support to employees and appraising the performance

of employees. The purpose of this office is to ensure all the employees completing

their works correctly and effectively. The function of Supervisor Consultant is

providing useful suggestions and advices for all level’s internal project managers and

staffs in the entire project cycle. Meanwhile, the office also provides marketing and

information technology (IT) consultant. The function of Customer Monitoring Office

is identifying the expectations of customers and meeting the satisfaction of them to

develop the customer experience and help improving and perfecting the performance

of products.

The Project Manager Training system exists as a subordinate department of Division

of Supervisor system, which could help giving some supplementary function in

project manager training aspect of the project. Due to the particularity of the new

aircraft project, there should be some different from other or past projects, so this

! 13

system could support the specific training for all levels’ managers, such as project

practitioner, project manager, senior project manager, project director and portfolio

executive. The project manager training is divided in 7 parts, including coaching

training, culture & political training, leadership training, conflict management training,

communication training, decision-making training and trust building training, which

are in different length of class hours. Project managers can be chosen to learn a

different class by their inspection results. This training can reduce the weaknesses of

project management in the A380 project.

Another benefit for establishing these two systems is that can reduce the expense and

the risks for outsourcing in consultation, because the outsourcing company cannot

know the project in detail. All the functions of the two systems could be beneficial

for project success in the final.

The next section also includes some professional analysis throughout some

methodologies and models of leadership. The outcomes of these analyses can be

meaningful information to guide project manager building project teams in correct

way, being corporation with stakeholders to satisfy their demands and avoiding the

potential risk to ensure achieving project success.

5.2 Methodology

In this project plan, implement two methodologies, the division of supervisor and

project manager training, to address the issues in Airbus a380 project and improve

the project rate of success. The first methodology is that provide the division of the

supervisor to address the weaknesses of organizational structure. The organization of

the division of supervisor is based on the review of Consumer Financial Protection

Bureau’s (CFPB) supervision program.

! 14

Figure 1: Division of Supervisor

According to Figure 1, the department of supervisor includes five offices and office

of supervisor examination includes 4 regional offices in France, Germany, Spain and

UK.

5. 2.1 Office of Supervision Policy

Responsibility of Office of Supervision Policy is that collects and analysis of the

different policies, regulations and laws for different countries. Make sure the whole

decision in this project considers all laws and avoids potential risks and issues. It also

considers the factors of different markets, regions and cultures. The detail principles

of Office of Supervisor Policy as follows:

•! Collect and analyze the new policies, regulation and laws in different regions

The A380 project is a multi-national program that includes major four countries such

as France, Germany, Spanish and United Kingdom. Each country is in charge of

! 15

different tasks within the project. The initial idea is that utilize the advantages of different

countries to improve the project rate of success. However, due to the different policies

and regulations, four countries utilize two versions of software and it directly leads to the

project delay the schedule and overrun budget. The program of German and Spanish

utilized the CATIA version 4 to continue to design and complete the process of the

project. Meanwhile, British and French updated the CATIA to version 5. Thus, the

supervisor should provide and update the important policy and regulation for the project

manager and ongoing monitor and consider the process of project follows the policy. The

possible policies in Airbus a380 project as follows:

1.! Effective communication with different groups and report the content of meeting

such as agenda and minutes of the meeting.

2.! Unifying the different tools and techniques in different countries, for example, the

different versions of software.

3.! Set up the performance standards of employees to evaluate the contributions of

each member.

•! Set up the training plan for employee

The supervisor should qualify and evaluate the performance of each employee

according to each job role. Analysis and judge the weakness and strengths of

personality to develop an improvement of the performance plan. Set up a suitable

objective and action strategy and schedule to improve work or management skills for

each employee. Moreover, the supervisor should ongoing evaluate the career

performance. Details of project manager plan in the figure 2.

5.2.2 Office of Supervisor Examinations

The office of supervisor examinations divides in four offices in four countries. It

should take responsibility to ensure each region follows the policy and rule. Check

and evaluate the career performance and collect the employer’s requirement and

feedback, rewards or new positions, to project manager. ! 16

Identify the issues or risks in the project and generate the exanimation reports for the

department of supervisor. The details principle of examination as follows:

1.! Set up examination guidance based on the objectives and goals of the project.

2.! Applied the approaches and methodologies of examination.

3.! Set up the content of examination and inform each member among the exam

schedule.

4.! Review the results of the examination staff and report the strengths and

weaknesses for each.

5.! Provide the training advices for the project manager.

The purpose of the examination is that review the staff performance among the

professional knowledge, technique level and professional ethics. According to the

examination report, identify the issues and provide possible solutions to improve

person’s abilities and the probability of project success.

5.2.3 Office of Supervisor Enforcement

The duty of this office is to ensure all the employees complete their works correctly

and effectively. Thus, the supervisor would provide guidance to employees before

they start working to make sure they have the same goal and direction as an

organization. In the process, employees may have specific problems related to project.

In this case, the supervisor could help them to address the problems based on

professional knowledge and experience. At the end of each project, it is necessary to

evaluate the performance to know everyone’s contribution and drawback. Details of

strategies of enforcing as follows:

1.! Guide employees to complete the work

Before starting to work, all employees need to know organizational polices, project

programs and their responsibilities. Mechanical passing on an order by documents

could not accurately transmit information, because the written documents may create ! 17

ambiguity and cannot ensure communication in time. To overcome the problem, the

supervisors in the office provide face-to-face guidance. They cannot only clearly

explain policies and programs that employees involved in, but also show them their

scope, standard and effective methods of work.

2.! Provide support to employees

No project can be completed without any problems. Problems could happen

anywhere. If nobody to collect these problems and just leave the problems to

employees themselves, then the project will exist many unsolved problems and even

hide problems. The supervisors of this office at the role of collecting problems,

solving problems, and reminding other related employees. They can apply their

knowledge and experience to solve the problems, or brainstorm a relative workable

solution. Their only purpose is to help all employees to complete works with quality

and efficiency.

3.! Appraise performance of employees

Performance appraisal aims to clarify the roles and responsibility of all employees,

which mean evaluating everyone’s contribution to the project. As long as the

contributions are determined, the issues of specific employees and other side issues

will be discovered. And once the issues are found, managers could start with analysis

problems and finding solutions. For the individual issues of employees, the

supervisors could make a plan of training to them. In this way, they will keep an eye

on these issues in future projects, and if similar issues occur, they will learn how to

address them.

5. 2.4 Office of Supervisor Consultant

Office of supervisor consultant provides useful suggestions and advices to internal

project managers or staff to support the continuing of the project. Details of strategies

as follow:

! 18

1.! Offer the strategy consultants to develop and improve the structure of organization

for senior management in the A380 project.

2.! Offer the marketing consultant to address the risks of competition between Airbus

Company and Boeing Company.

3.! Offer the management strategy of human resources to deal with the barriers of

cross-culture. The different cultural background in A380 project leads to the

problems of communication, ineffective people management and the issues of

unifying different deliverables of different project groups.

4.! Offer the information technology (IT) consultant. The most important issue is that

the A380 project uses different versions of software. If the project has IT

consultant, it would effectively avoid this risk or reduce the negative impacts.

The major duty of IT consultant is that provide useful advices of hardware,

software and network.

5.! Advice the plan of development for personal to require higher position and better

development in the company.

6.! Provide ongoing consultant, coaching and guidance for staff.

The purpose of office of supervisor consultant is that improves the quality of the

project and addresses the potential risks in the process of project. Moreover, provide

the ongoing consultant for the project manager during the process of project.

Meanwhile, the staff could require a path to improve the personal ability to acquire

the higher position.

5.2.5 Office of Customer Monitoring

The purpose of office of customer monitoring is that identify the expectations of

customer and meet the customer satisfaction to develop the customer experience. The

major methodology is that generate the survey to require the feedback of customer.

Evaluate and analyze the feedback of customer to understand the demands of

! 19

customer and develop the improvement of the project. Report the customer analysis

to project manager and present the advantages and disadvantages of reporting.

Improve the quality of each deliverable to satisfy the expectations of the customer.

The detail principles of customer survey as follows:

1.! Offer the customer satisfaction survey or customer non-satisfaction survey.

Sometimes, the customer perhaps does not clearly understand the requirements

or demands of the product. Thus, the project manager could identify what kind

of factors customer does not like. It also could help or inspire the project

manager to identify the expectations of the customer.

2.! Questions of customer survey should be quite an easy answer. Multiple choices

are a good way and it easy to quantitative analysis for project manager.

3.! Regular and ongoing customer survey. Ongoing survey may have benefits to build

well relationship between manufacturer and customer.

5.2.6'Project'Manager'Training'

In the figure 2, show the structure or organization of project manager training. The

purpose of training is that reduce the weaknesses of project management in the A380

project. Project manager training divides 7 parts, coaching training, culture &

political training, leadership training, conflict management training, communication

training, decision-making training and trust building training. Seven parts of project

manager training are based on the interpersonal skills in PMBOK. The appropriate

utilize of interpersonal skills supports the managing of the project to improve the

quality of project (PMBOK, 2013). The assumption of project manager training plan

as follows:

1.! Coaching training focus on the project practitioner and project manager who is the

low-level in the organization of management. Thus, provide the longest time to

training and the content of training pay more attention on the basic management

skills. ! 20

2.! The objective of cultural and political training is portfolio executive and project

director who is the high-level in the project. It assumed that the problem of cross-

culture and politics has high probability appear in the high-level cooperation.

Thus, provide 100 hours to address these possible problems in the project.

3.! Assumed the high-level has strong leadership skills, and training have low effects

to support them. Thus, the objective of leadership training is senior project

manager and other low-level manager.

4.! It assumed that the conflict management more effective in the high-level project

manager. Due to the strong power and authority of high-level project manager. It

easily influences the process of the project.

5.! Assumed the communication, decision-making and trust building training more

important to high-level project manager.

Figure 2: Project Manager Training ! 21

The managerial level of Figure 2 divides five different grades, project practitioner, project manager, senior project manager, project director

and portfolio executive, is based on the roles of the Australian Institute of Project Management. The time line of training major considers the

available time of different level project manager. The details of the time as follow:

Training Content Before the project start

The process of project Week1 Week2 Week3 Week4 Week5

Coaching Training

Culture & Political Training 2.5 week

Leadership Training

Conflict Management Training 40 hours

Communication Training 15 hours 5 hours

Decision-making Training 15 hours 5 hours

Trust Building Training 30 hours

Table 1: The high-level Gantt chart of project manager training

! 22

According to Table 1, the schedule plan of project manager plan divides two parts

that before the project start and the process of the project. The assumptions of high-

level Gantt chart as follows:

1.! The duration of working is 8 hours per day and having 5 working days per week.

Do not consider the public holiday in this Gantt chart.

2.! Consider the objective of training is high-level manager, the office of supervisor

choice online course to ensure staff have available schedule continuing.

3.! Conflict management training and trust building training have a high probability

to appear in the process of project. Provide more training hours during the process

of project.

4.! Training in the process of project pay more attention to address the potential risks

and provide the details of the project management plan for project manage

! 23

5.3 Stakeholder Management

5.3.1 Stakeholder Identification

According to the Figure 1, it indicates the structure of mainly stakeholders.

Figure 1: Stakeholder Identification

! 24

5.3.2 Stakeholder Analysis

The major function of stakeholder analysis is that enhance the probability of project

success dependS on the identification of stakeholders’ interest, expectation and

influence (PMBOK, 2013). Due to the analysis of different stakeholders, provide

adopted options or processes to satisfy the different demands of each stakeholder.

Figure 1: Power/Interest Gide with Stakeholder

According to the Figure 1, the users and airport authorities would not influence the

process of the project due to the low power and interest. For the government

regulatory bodies, they have high power but low interest. Thus, the project manager

should satisfy the demands of those stakeholders. However, some groups have high

interest and low power such as supplier, employee and airline companies and they are

the divers of the project. Thus, keep informing for those groups. The board of

directors and higher managers has high power and high interest and they would

change the process of the project. Satisfy the demands of those groups first. ! 25

5.3.3$Stakeholder$Engagement$Plan$

The purpose of stakeholder engagement plan is that communication and corporate with stakeholders to satisfy the demands and avoid the

potential risk to ensure the project achieves success (PMBOK, 2013).

Project manager utilizes the effective communication and negotiation with stakeholders to require the support from them and reduce the

resistance (PMBOK, 2013). Therefore, analysis and conclude the stakeholder engagement plan to provide possible strategies to address the

project issues.

No Stakeholder Roles Interest Power Strategy Engagement Plan

1 Government Regulatory Setting up the regulations and laws. Low High Keep Satisfy Keep satisfied. Provide the

Bodies Create the flight quality standards detail project plan and meet

and certificate the each test to ensure the requirement of

the deliverables of project safety. Government Regulatory

Bodies to acquire approvals.

! 26

2 Users Provide a feedback of airport to Low Low Monitor Keep informed. Satisfy the

evaluate the performance and make key requirements of users or

some recommendations. customers and create

innovations and interest

points of products to

develop users' interest.

3 Airport Authorities Authorize the licenses of Low Low Monitor Keep informed. Hold a

manufacturers according to the meeting constantly to seek

process of project. supports.

4 Board of Directors The major decision maker in this High High Manage Closely Create project charts,

project cause of high interests and deliverables, milestones and

power. Make important decisions on deadline of project.

the project, and affect the direction Delivery the tasks,

of the project. resources and funds to each

programmers and engage

! 27

the regular meetings to

promote, control and

monitor the process of

project.

5 Higher Management Level Key divers to promote the High High Manage Closely Conduct regular meeting

development of each project. with team members.

Delivery the tasks and assignments Motivate individuals to

to each membership. Monitor and ensure the quality of project

control the process of project within with a high level.

budget and in schedule.

6 Suppliers The key partners of project supplies High Low Keep Informed Provide the relevant

necessary resources to meet the information to share with

standards of project design and suppliers to require

product. feedbacks to promote the

development of project.

! 28

Conduct regular meeting.

7 Employee Execute the details of project tasks High Low Keep Informed Provide training to ensure

and the major productivities on the individual dose a competent

project. job. Impose motivation and

conduct regular meeting to

make sure the each

deliverables attain per

targets. Collect the project

update timely.

8 Airline Companies The most important clients on this High Low Keep Informed Conduct regular meetings to

project. Advance the requirements of understand the requirements

project. or change requirements of

project. Share the

information of project

situation to acquire the

! 29

feedback of Airline

Companies.

9 Shareholder Invest in this project to require the High Low Keep Informed Conduct meeting to report

profits. the financial situation, the

investment of company and

business reports.

Table 2: The Stakeholder Analysis

5.4 Communication Plan

The purpose of stakeholder communication table is that discusses with different levels of stakeholders and requires the feedback of each group.

Modify the part contents or structures of supervisor department according to the feedback to require major stakeholder support. Informed low

power or low interest stakeholder and improve the relationship with them.

Stakeholders Communication Table

Communication Target Audience Purpose Owner Communication Medium Frequency

! 30

Type Deliverable

Kick-off meeting Board of Directors, Introduce the Project manager Agenda, Meeting Face to face Once a month

Higher management purpose; duty and minutes and report.

level, Shareholder work flow of office

of supervisor to

require the supports

of stakeholder.

Require the budget

support of the board

of directors.

Regular meeting Government Informed the general Supervisor manager Agenda, Meeting Face to face Once a month

Regulatory Bodies contents of the minutes, feedback

project plan for and report.

government and

build a good

! 31

relationship between

government and

project.

Client meeting Users, Airport Informed the details Supervisor manager Agenda, Meeting Face to face Once a month

Authorities, Higher of the supervisor minutes, feedback

project manager structure and require and report.

the feedback of the

client

Procurement meeting Higher management, Informed the duty Supervisor manager Agenda, Meeting Face to face Once a month

suppliers and responsible and minutes, feedback

require the feedback. and report.

Internal Employees, Higher Informed the details Supervisor manager Agenda, Meeting Face to face Once a month

announcement project manager of supervisor minutes, feedback

! 32

meeting department for and report.

employee.

Table 3: Stakeholder Communication Table

! 33

5.5 SWOT Analysis of the Project Plan

The definition of SWOT analysis is that it is a planning and evaluation technique,

which has four factors such as strengths, weaknesses, opportunities and threats (Hill

& Westbrook, 1997). The purpose of SWOT analysis is that the decision maker could

clearly understand the whole aspects of the project and make reasonable options to

achieve the objectives of the project (Hill & Westbrook, 1997).

! 34

! 35

References

[1]Hill, T., & Westbrook, R. (1997). SWOT analysis: it's time for a product recall.

Long range planning, 30(1), 46-52.

[2]Garbade, R., &Dolezal, W. R. (2007). DMU@ Airbus—Evolution of the Digital

M ock-up (DMU) at Airbus to the Centre of Aircraft Development. In The Future of

Product Development (pp. 3-12). Springer Berlin Heidelberg.

[3]Lawrence, P., &Scanlan, J. (2007). Planning in the dark: why major engineering pr

ojects fail to achieve key goals. Technology Analysis & Strategic Management, 19(4),

509-525.

[4]Hartmann, J., Meeker,C., Weller, M., Izzard, N., Smith, A., Ferguson, A., &

Ellson ,A.(2004). Determinate assembly of tooling allows concurrent design of

Airbus wings and major assembly fixtures (No. 2004-01-2832). SAE Technical Paper.

[5]Gellman, A. J., Weber,H. J, Hamlin, G. W & Aboulafia, R. L. (2004). A shadow

cri tical project appraisal: The A380 program.