Quality Management Plan Assignment

profilekvillamarin
order_148891_399842.docx

Logo  Description automatically generated

M3 Assignment: Build a WBS

Create a WBS for “Interior Construction” for the Smith Family Home that we are building in the Recorded Lectures. The WBS needs to be between 20 and 30 lines long and at least 3 levels deep. It should describe the work – all the work but only the work – to build the interior of the Smith Family home.

The outline below is setup to add the correct WBS code to each element. Replace “First Deliverable” and “Sub Deliverable” with your own material, then continue building the WBS.

1. Internal construction of Smith Family House

1.1 Drywall texture

1.1.1 Install drywall in 1st floor walls

1.1.2 Install drywall in 2nd floor walls

1.1.3 Mud and tape joints of drywall in 1st floor

1.1.4 Mud and tape joints of drywall in 2nd floor

1.2 Painting

1.2.1 Apply primer undercoat paint – 1st floor

1.2.2 Apply wall putty first and second coat – 1st floor

1.2.3 Apply chosen paint – 1st floor

1.2.4 Apply primer undercoat paint – 2nd floor

1.2.5 Apply wall putty first and second coat – 2nd floor

1.2.6 Apply chosen paint – 2nd floor

1.3 Install cabinets

1.3.1 Install kitchen cabinets – 1st floor

1.3.2 Install guest bath cabinets – 1st floor

1.3.3 Install master bath cabinets – 2nd floor

1.3.4 Install other rooms bath cabinets – 2nd floor

1.4 Plumbing

1.4.1 Kitchen plumbing – 1st floor

1.4.2 Guest bath plumbing – 1st floor

1.4.3 Master bath plumbing – 2nd floor

1.4.4 Other rooms plumbing – 2nd floor

1.5 Electrical wiring

1.5.1 Complete electrical wiring to service panel – 1st floor

1.5.2 Complete electrical wiring to service panel – 2nd floor

1.5.3 Inspection of the electrical wiring

1.5.4 Complete installation of communication appliances; alarm, phone, internet – 1st and 2nd floor

Internal Construction of Smith Family House

1

Drywall Texture

1.1

painting

1.2

Installing Cabinets

1.3

Plumbing

1.4

Apply primer undercoat paint-1st floor

1.2.1

Electrical wiring

1.5

Install drywall-1st floor

1.1.1

Install drywall-2nd floor

1.1.2

Mud and tape joint of drywall-1st floor

1.1.3

Mud and tape joint of drywall-2nd floor

1.1.4

Apply wall putty first and second coat-1st floor

1.2.2

Apply chosen paint-1st floor

1.2.3

Apply primer undercoat paint-2nd floor

1.2.4

Apply wall putty first and second coat-2nd floor

1.2.5

Apply chosen paint-2nd floor

1.2.6

Install Kitchen cabinets-1st floor

1.3.1

Install guest bath cabinets-1st floor

1.3.2

Install master bath cabinets-2nd floor

1.3.3

Install other rooms bath cabinets-2nd floor

1.3.4

Kitchen plumbing-1st floor

1.4.1

Guest bath plumbing-1st floor

1.4.2

Master bath plumbing-2nd floor

1.4.3

Other rooms plumbing-2nd floor

1.4.4

Complete electrical wiring to service panel-1st floor

1.5.1

Complete electrical wiring to service panel-2nd floor

1.5.2

Inspection of electrical wiring

1.5.3

Complete installation of communication appliances-alarm, phone, internet

1.5.4

References

Li, Y., Zhang, X., Ding, G., & Feng, Z. (2016). Developing a quantitative construction waste estimation model for building construction projects. Resources, Conservation and Recycling106, 9-20. https://www.sciencedirect.com/science/article/pii/S0921344915301282