5 page project

profileDayessi100
NR631W6WBSExamplesPPT.pptx

Work Breakdown Structure (WBS) Outline Format Example

Work Breakdown Structure (WBS) Graphical Format Example

(Level 0) (Name of Project)

(Level 1) (Major Task)

(Level 2) (Subtasks)

1 Baseball Stadium Project (Level 0 ) (Name of Project)

1.1 Prepare Site (Level 1) (Major Tasks)

1.1.1 Clear stadium site (Level 2) (Subtasks)

1.1.2 Demolish building

1.1.3 Set up construction site

1.1.4 Drive support piling

1.1.5 Pour lower concrete bowl

1.1.6 Pour main concourse

1.2 Installation

1.2.1 Install playing field

1.2.2 Construct upper steel bowl

1.2.5 Install Jumbotron

1.2.4 Build luxury boxes

1.2.6 Stadium infrastructure

1.2.3 Install seats

1.2.7 Construct steel canopy

1.2.8 Light installation

1.3 Construction

1.3.1 Build roof supports

1.3.3 Install roof tracks

1.3.2 Construct roof

1.3.4 Install roof

1.3.5 Inspection

1 Baseball Stadium Project (Level 0 ) (Name of Project)

1.1 Prepare Site (Level 1) (Major Tasks)

1.1.1 Clear stadium site (Level 2) (Subtasks)

1.1.2 Demolish building

1.1.3 Set up construction site

1.1.4 Drive support piling

1.1.5 Pour lower concrete bowl

1.1.6 Pour main concourse

1.2 Installation

1.2.1 Install playing field

1.2.2 Construct upper steel bowl

1.2.5 Install Jumbotron

1.2.4 Build luxury boxes

1.2.6 Stadium infrastructure

1.2.3 Install seats

1.2.7 Construct steel canopy

1.2.8 Light installation

1.3 Construction

1.3.1 Build roof supports

1.3.3 Install roof tracks

1.3.2 Construct roof

1.3.4 Install roof

1.3.5 Inspection