< Develop and Implement Project RoadRunner in China >

Revision: <1.0>

Project Charter

Date: 11/02/2019

<Johnson & Johnson >

<Johnson & Johnson >

<Soumitra Girish Shilotri>

<11/02/2019>

<Kim Young- Sponsor, PMO>

< Develop and Implement Project RoadRunner in China >

Project Charter

Revision <1.0>

PMGT 699 Project Charter v.1 April 2018 (Adapted from Document Code: PMBOK4.1.3.1)

List of Changes

Date

Revision

Description

Author

<11/02/2019>

<1.0>

Publication for use for J&J Project

<Soumitra Girish Shilotri>

Table of Contents 1. General Provisions 4 2. Terms, Notations, Abbreviations 4 3. Project Purpose 4 4. Measurable Project Goals and Objectives 5 5. High-level Project Description and Boundaries 6 6. High-Level Requirements 6 7. Overall Project Risk 7 8. High Level Constraints and Assumptions 7 9. Summary Milestone Schedule 8 10. Key Project Deliverables 8 11. Preapproved Financial Resources 9 12. Key Stakeholder List 9 13. Project Approval Requirements 9 Project Exit Criteria 9 Project Managers 10 Name 10 Position 10 Signature 10 Date 10 Appendixes 10

1. General Provisions

This document refers to the project "< Develop and Implement Project RoadRunner in China >", which is implemented by the organization "<Johnson & Johnson >".

The Project Charter formulates the practical requirements and documents the high-level description of the product, service or other deliverable that should meet these requirements and will be result of the project.

The Project Charter is issued and signed by the Initiator or Sponsor of the project and formally legitimized the existence of the project. It provides the Project Manager with the authority to use the organizational assets in the project operations.

The approved Project Charter formally initiates the project.

If the project consists of several phases, the Charter can be updated to verify or improve the decisions taken during the previous iteration of the Project Charter development. In such a case the Charter is re-issued and signed as amended.

Terms, Notations, Abbreviations

Term/Abbreviation

Definition

PMO

Project Management Office

CAPA

Corrective and Preventive Action

CE mark

Conformité Européene

IFU

Instructions for use

R&D

Research and Development

SME

Subject Matter Expert

PRA

Product Review Approval

RA

Regulatory Affairs

Sr.

Senior

FDA

Food and Drugs Administration

Project Purpose

The purpose of this project is to Develop and Implement Project RoadRunner in China Market. Project RoadRunner is an Implant medical device that is used extensively in bariatric surgeries. Project RoadRunner will improve the stapling and cutting quality of the device. Hence, improving the performance on the device and decrease in market complaints. 3-D staples will be used to improve the quality and performance of the device.

Following factors are equally important for the purpose of the project:

· Market demand – China is one of the biggest market for Johnson & Johnson devices. There is an constant demand in China market for such devices.

· Organizational need – From business point of view Johnson & Johnson wants to be ready to deliver quality devices, thus by stopping any other competitors to enter the business.

· Customer request – There is an unmet need for quality devices in China. Johnson & Johnson wants to meet this unmet need for their customers.

· Technological advance This new device will resolve the CAPA issue for the legacy devices and the new device will be marketed with 3-D staples technology which is currently the most technologically advance system and not available in the the legacy devices.

· Legal requirement – As the legacy devices have complaints, Johnson & Johnson had to open a CAPA to fix these designs. From legal point of view it is very important that the company fix this issue, to avoid any patient complaints that could lead to major legal financial consequences and even affecting company brand name.

Measurable Project Goals and Objectives

Project Goals:

· Successful development of the project's procedures of initiation, planning, execution, regulation and closure.

· To provide guidance to the project team's operations towards achieving all the agreed upon goals within the set scope, time, quality and budget standards.

· To finish project RoadRunner on time with minimum risk to business with respect to time and budget

· To follow regulatory guidelines to ensure it meets China’s regulatory requirement.

· Control budget, time, quality and scope of the project.

· Provide proper communication across industry to various involved departments.

· Set up weekly meetings with all the involved project teams.

· Achieve SMART (Specific, Measurable, Achievable, Relevant, Time-based) Goals.

Business Goals:

· Increase revenue income by 10% by end of year 2020 for RoadRunner Devices in China market.

· Reduce complaints and increase quality and performance of RoadRunner Devices in China market.

· Increase market share in China by 15% by end of the year 2020, thus reducing competition from other companies.

· Reach out to maximum hospitals and doctors and make them aware of the new medical device that Johnson & Johnson is planning to launch in China that will make surgeries more comfortable for surgeons.

· Build a robust quality system, validation system and post market surveillance that will catch any non-conformance in the device at the manufacturing site or before entering the market. That will reduce complaints during surgery from doctors / patients.

· Do an in-depth market study in China to understand what other companies are marketing and what are the concerns that doctors are facing in other companies device. Use them at advantage and develop robust design that will resolve those complaints and then start marketing those devices to doctors.

High-level Project Description and Boundaries

The purpose of this project is to Develop and Implement Project RoadRunner in China Market. Project RoadRunner is an Implant medical device that is used extensively in bariatric surgeries. Project RoadRunner will improve the stapling and cutting quality of the device. Hence, improving the performance on the device and decrease in market complaints. 3-D staples will be used to improve the quality and performance of the device.

Currently, the boundary for this product is non-CE mark and can’t be sold in other markets that require CE marking. Current strategy is to only develop this product for China market and develop local IFU’s for China only.

High-Level Requirements

For successful development and implementation of Project RoadRunner in China following requirements needs to be fulfilled:

· Approval from higher management to execute the project.

· Approved financial budget and timeline for this project

· Project initiation requirements -

· Successful completion of process for generating new product codes for China

· Creating manufacturing assembly for component development

· Manufacturing site vision system software validation upgrades

· Design Validation

· Performance Qualification Testing

· Labelling Requirements to be approved as per China Regulatory Body

· Regulatory Approval Process

· Project Documentation

· Design Change documentation

· Labelling documentation

· Packaging documentation

· Manufacturing documentation

· Regulatory documentation

Overall Project Risk

Risk

Description

Impact

Probability

Mitigation Plan

Availability of Human Resources for timely completion of Project

Lack of available resource because of illness and vacations

Medium

Low

Good Project Planning

Assign back up person to primary resource

Project Completion in twelve months

Non-conformities are observed leading to not having enough time for project implementation

High

Medium

Add reserve days for testing devices in project plan and also managing non-conformities

Regulatory Approval

Regulatory Approval from regulatory agencies

High

High

Face to face meeting with regulatory body reviewers to understand exact regulatory requirements for approval

High Level Constraints and Assumptions

Constraints:

· Time zone constraint to work with China team on the project.

· Manufacturing equipment constraint to work in manufacturing facility during validation.

· US government shutdown delayed US FDA approval.

Assumptions:

· China Regulatory Approval will be done in 6 months.

· US FDA Regulatory Approval will be done in 3 months.

· The device design will resolve the issue of complaints in China.

Summary Milestone Schedule

No.

Milestone

Responsible Party

Date

1.

Successful completion of process for generating new product codes for China market

Change Review Board / Project Manager

December 2021

2.

Design Change Documentation

Project Manager

December 2020

3.

Creating manufacturing assembly for component development

Manufacturing Lead

March 2021

4.

Manufacturing site vision system software validation upgrades

Manufacturing Lead

March 2021

5.

Design Validation

R&D Lead

March 2021

6.

Performance Qualification Testing

R&D / Manufacturing Lead

March 2021

7.

Labelling Approval

Labelling Lead

January 2021

8.

Packaging Approval

Packaging Lead

March 2021

9.

Regulatory Approval

Regulatory Lead

December 2021

Key Project Deliverables

Deliverables

Date Available

Acceptance Criteria

Project Charter

July 2020

Approved by PMO

Project Plan

August 2020

Approved by Sponsor

Project Change Request Draft

September 2020

Approved by Change Review Board members

Project Change Request Initial Review and SME inputs

September 2020

Approved by all SME’s

Project Review Board - Initiate

September 2020

Approved by Change Review Board members

Project Design Review Documentation

September 2021

Approved by Project Lead

Design Review

October 2021

Approved by Project Lead

Mitigate Design Review Risk

October 2021

Approved by Project Lead

Project Review Board - Approval

December 2021

Approved by Change Review Board members

Final Product Review Approval (PRA)

December 2021

Approved by Change Review Board members

Preapproved Financial Resources

Department

2020-2021

2021-2022

R&D

$30,000

$30,000

Manufacturing

$50,000

$50,000

Project Management

$10,000

$10,000

Labelling

$20,000

$20,000

Packaging

$10,000

$10,000

Regulatory

$30,000

$30,000

PMO

$50,000

$50,000

Reserve Funds for Project

$50,000

$50,000

Equipment

$10,000

$10,000

Devices

$10,000

$10,000

Total

$270,000

$270,000

Key Stakeholder List

Full Name

Position/Organization

Role in the Project

Telephone/E-mail

Kim Young

Sponsor, PMO

Project Sponsor, PMO

[email protected]

Kent Baker

Project Manager

Project Lead

[email protected]

Kimberly Schumacher

Sr. Director, RA

Regulatory Lead

kschumacher.com

Brian Ruble

Director, Quality & Compliance

Quality & Compliance Lead

[email protected]

Project Approval Requirements

Project approval requirements will be performed by Johnson & Johnson designated Subject Matter Expert’s (SME’s) employees, through the approval of the project's deliverables listed in Section 10 of this document

Final Project Approval will be performed by the Change Review Board Members that will include SME’s from Research & Development (R&D), Project Management, Manufacturing, Regulatory Affairs, Quality Assurance, and Marketing.

Project Exit Criteria

Product Review Approval form (PRA) needs to be signed and sent to PMO office for exit criteria.

Project Managers

Kent Baker and Craig Smith will be acting as the Project Manager from Johnson & Johnson for the RoadRunner Project for China. They will be responsible from initiating stage to execution stage of the RoadRunner project and also making sure all tasks are completed on time for project completion from other SME’s as well.

Signed/Project sponsor(s) or charter approving authority

Name

Position

Signature

Date

Brian Ruble

Director, Quality & Compliance

Kent Baker

Project Manager

Kimberly Schumacher

Sr. Director, RA

Kim Young

PMO

Joanne Hull

Director Marketing

Appendixes

<N/A>