MS Project Exercise
Earned Value Analysis Report
Earned Value Management Template
Prepared By: Mary Krenisky © 2012-2017 Vertex42 LLC
Date: 27-Aug-18
[42]
For Period: Week 8
Summary:
According to the results of the graph that is prepared on the basis of various computations, shows the Planned value and earned value exceed the actual cost.
Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS)
WBS
Vertex42: Work Breakdown Structure (WBS)
Task Name TBC
Vertex42: Total Budgeted Cost (TBC)
Jan Feb Mar April May June July August Sep Oct Nov Dec ← You can change the labels for the periods (e.g. Week 1/2/3, Jan/Feb/Mar, etc.)
1.1 Retirement&social security benefits 176 46 20 25 30 55 ← Enter or edit values in the light-blue cells.
1.2 Audit&risk evaluation 143 25 43 25 30 50
1.3 Equipment&maintenance 151 20 23 10 15 20 20 20
1.4 Training&Development 134 20 20 45 20 30 30 24
1.5 Logistics,Appraisals&Rewards 148 20 35 25 25 38 45
0
0
0
0
0
0
Insert new rows above this one ← To add more tasks, insert rows above this one. You can or delete this row after you are done adding tasks.
Total Budgeted Cost 752 46 45 88 98 135 145 65 75 88 69 0 0
Cumulative Planned Value (PV) 46 91 179 277 412 557 622 697 785 854 854 854
Actual Cost and Earned Value
Cumulative Actual Cost (AC) 48 126 229 325 439 531 607 ← Enter the Actual Costs as calculated from the AC worksheet.
Cumulative Earned Value (EV) 26.4 101.15 232.24 311.45 460.4 553.7 627.35 ← Enter the Earned Value as calculated from the EV worksheet.
Project Performance Metrics
Cost Variance (CV = EV - AC) -21.6 -24.85 3.24 -13.55 21.4 22.7 20.35 - - - - -
Schedule Variance (SV = EV - PV) -19.6 10.15 53.24 34.45 48.4 -3.3 5.35 - - - - -
Cost Performance Index (CPI = EV/AC) 0.55 0.80 1.01 0.96 1.05 1.04 1.03 - - - - -
Schedule Performance Index (SPI = EV/PV) 0.57 1.11 1.30 1.12 1.12 0.99 1.01 - - - - -
Estimated Cost at Completion (EAC) 1367 937 742 785 717 721 728 - - - - -

&8&K01+049https://www.vertex42.com/ExcelTemplates/earned-value-management.html &8&K01+049EVM Template © 2012 Vertex42 LLC

Planned Value (PV) Jan Feb Mar April May June July August Sep Oct Nov Dec 46 91 179 277 412 557 622 697 785 854 854 854 Earned Value (EV) Jan Feb Mar April May June July August Sep Oct Nov Dec 26.4 101.15 232.24 311.45000000000005 460.4 553.69999999 999993 627.35 Actual Cost (AC) Jan Feb Mar April May June July August Sep Oct Nov Dec 48 126 229 325 439 531 607

Period

https://www.vertex42.com/ExcelTemplates/earned-value-management.html

EV

Earned Value Worksheet
This worksheet is used to help calculate the Earned Value (EV) or Budgeted Cost of Work Performed (BCWP). Earned Value Management Template
Make sure that the WBS, Task Name, and TBC are identical to the table in the Report worksheet. © 2012-2017 Vertex42 LLC
Enter the % Complete for each task to calculate the cumulative earned value.
Cumulative Earned Value (EV)
WBS Task Name TBC Jan Feb March Apr May June July Aug Sep Oct Nov Dec
1.1 Retirement&social security benefits 176 15% 20% 45% 100% 85% 80% 100% 100% 100% 100%
1.2 Audit&risk evaluation 143 25% 50% 15% 55% 70% 65% 45% 75% 100%
1.3 Equipment&maintenance 151 20% 54% 40% 65% 100% 80% 35% 65% 100%
1.4 Training&Development 134 40% 100% 60% 100% 55% 80% 100%
1.5 Logistics,Appraisals&Rewards 148 55% 70% 40% 70% 90%
- - 0
- - 0
- - 0
- - 0
- - 0
- - 0
- - 0
Insert new rows above this one
Cumulative EV 26.4 101.15 232.24 311.45 460.4 553.7 627.35 426.1 592.2 737.2 0 0
https://www.vertex42.com/ExcelTemplates/earned-value-management.html

AC

Actual Cost Worksheet
Use this worksheet to help calculate the Actual Cost (AC) of Work Performed (ACWP) by entering the costs incurred each period. Earned Value Management Template
Make sure that the WBS, Task Name, and TBC are identical to the table in the Report worksheet. © 2012-2017 Vertex42 LLC
Transfer the Cumulative Actual Cost to the Report worksheet.
Actual Cost (AC) of Work Performed
WBS Task Name Jan Feb March April May June July Aug Sep Oct Nov Dec
1.1 Retirement&social security benefits 48 25 52 21 30
1.2 Audit&risk evaluation 30 31 35 24 23
1.3 Equipment&maintenance 23 20 20 20 24 10 24 10
1.4 Training&Development 20 20 25 26 30 48 20
1.5 Logistics, Appraisals&Rewards 20 20 40 26 20 22
- -
- -
- -
- -
- -
- -
Insert new rows above this one
Total Actual Cost 48 78 103 96 114 92 76 80 78 42 0 0
Cumulative Actual Cost (AC) 48 126 229 325 439 531 607 687 765 807 807 807
https://www.vertex42.com/ExcelTemplates/earned-value-management.html

©

Earned Value Management (EVM) Template
By Vertex42.com
https://www.vertex42.com/ExcelTemplates/critical-path-method.html
© 2012-2017 Vertex42 LLC
This spreadsheet, including all worksheets and associated content is a copyrighted work under the United States and other copyright laws.
Do not submit copies or modifications of this template to any website or online template gallery.
Please review the following license agreement to learn how you may or may not use this template. Thank you.
https://www.vertex42.com/licensing/EULA_privateuse.html
Do not delete this worksheet.
https://www.vertex42.com/ExcelTemplates/critical-path-method.html https://www.vertex42.com/licensing/EULA_privateuse.html