| Project: | Schlumberger - Montney Onshore Project |
| Name: |
| Date: | 7-Nov-20 |
| ID | LEVEL 1 TASK | LEVEL 2 TASK | LEVEL 3 TASK | DURATION | BASELINE | ACTUAL WORK | RESOURCE | ACTIVITY NOTES |
| 1 | Geological Investigation |
| 1.1 | | GeoReam (www.slb.com, n.d.) |
| 1.1.1 | | | Drilling Site Excavation | 3 WEEKS | | | Ole Usted | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.2 | | | Flooring Bed Set-up | 2 WEEKS | | | Ole Usted | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.3 | | | Resolve Geological Issues | 2 WEEKS | | | Emmanuel Pena | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 1.1.4 | | | Inspection and documentation | 2 WEEKS | | | Emmanuel Pena |
| 1.2 | | Pressurization |
| 1.2.1 | | | Regulating Temperature | 1 WEEK | | | Alvaro Pardo |
| 1.2.2 | | | Regulating Pressure | 1 WEEK | | | Alvaro Pardo |
| 1.2.3 | | | Regulating Depth | 1 WEEK | | | Alvaro Pardo |
| 1.2.4 | | | Inspection and documentation | 1 WEEK | | | Alvaro Pardo |
| 2 | Well Foundation |
| 2.1 | | Wall |
| 2.1.1 | | | Floor Setting | 2 WEEKS | | | Rune Landro | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.2 | | | Concrete Pouring | 1 WEEK | | | Rune Landro | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.3 | | | Rebar Placement | 1 WEEK | | | Rune Landro | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.1.4 | | | Inspection and documentation | 1 WEEK | | | Rune Landro |
| 2.2 | | Slab |
| 2.2.1 | | | Rebar Placement | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.2 | | | Concrete Pouring | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.3 | | | Concrete Float Joint (www.slb.com, n.d.) | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 2.2.4 | | | Inspection and documentation | 1 WEEK | | | James Sheffield |
| 3 | Framing |
| 3.1 | | Wall |
| 3.1.1 | | | Support Wall (1) | 2 WEEKS | | | Luis Espinosa | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.2 | | | Support Wall (2) | 2 WEEKS | | | Luis Espinosa | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.3 | | | Support Wall (Firming) | 2 WEEKS | | | Luis Espinosa | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.1.4 | | | Inspection and documentation | 1 WEEK | | | Luis Espinosa |
| 3.2 | | Slab |
| 3.2.1 | | | Rebar Placement | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.2 | | | Concrete Pouring | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.3 | | | Concrete Float Joint (www.slb.com, n.d.) | 1 WEEK | | | James Sheffield | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 3.2.4 | | | Inspection and documentation | 1 WEEK | | | James Sheffield |
| 4 | Well Drilling |
| 4.1 | | Rigs |
| 4.1.1 | | | Rig set up (15) | 5 WEEKS | | | Jeni Hyland | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.1.2 | | | Rig computerization | 5 WEEKS | | | Jeni Hyland | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.3 | | | Begin rig run | 5 WEEKS | | | Jeni Hyland | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.4 | | | Inspection and documentation | 5 WEEKS | | | Jeni Hyland |
| 4.2 | | Drilling |
| 4.2.1 | | | Site set up (15) | 5 WEEKS | | | Todd Smith | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.2 | | | Rig installation | 5 WEEKS | | | Todd Smith | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.3 | | | Begin drilling run | 5 WEEKS | | | Todd Smith | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 4.2.4 | | | Inspection and documentation | 5 WEEKS | | | Todd Smith |
| 5 | Turnkey Deliverable |
| 5.1 | | Interrelationship of rigs |
| 5.1.1 | | | Connect rigs 1 to 5 | 2 WEEKS | | | Graham Butte | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.2 | | | Connect rigs 5 to 10 | 2 WEEKS | | | Graham Butte | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.3 | | | Connect rigs 10 to 15 | 2 WEEKS | | | Graham Butte | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.1.4 | | | Inspection and documentation | 2 WEEKS | | | Graham Butte |
| 5.2 | | Technology |
| 5.2.1 | | | Develop software solution | 12 WEEKS | | | Vinay Narayana | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.2 | | | Software testing in lab environment | 3 WEEKS | | | Vinay Narayana | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.3 | | | Software installation | 1 WEEK | | | Vinay Narayana | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.4 | | | Test and run software | 3 WEEKS | | | Vinay Narayana | Comparative Estimate/Previous Experience/Duration may vary due to environmental or regulatory changes, logistical or project resource issues. |
| 5.2.5 | | | Training and documentation | 3 WEEKS | | | Vinay Narayana |
| | References |
| | Explore the new Oilfield Glossary. (n.d.). Retrieved November 7, 2020, from https://www.glossary.oilfield.slb.com/en/Terms/f/float_joint.aspx |
| | GeoReam. (n.d.). Retrieved November 7, 2020, from https://www.slb.com/drilling/bottomhole-assemblies/reamers-and-stabilizers/geoream-dual-diameter-near-bit-reamer |