Chapter 6, Part B: Distribution and Network Models
Shortest-Route Problem
Maximal Flow Problem
A Production and Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Shortest-Route Problem
The shortest-route problem is concerned with finding the shortest path in a network from one node (or set of nodes) to another node (or set of nodes).
If all arcs in the network have nonnegative values then a labeling algorithm can be used to find the shortest paths from a particular node to all other nodes in the network.
The criterion to be minimized in the shortest-route problem is not limited to distance even though the term "shortest" is used in describing the procedure. Other criteria include time and cost. (Neither time nor cost are necessarily linearly related to distance.)
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Linear Programming Formulation
Using the notation:
xij = 1 if the arc from node i to node j
is on the shortest route
0 otherwise
cij = distance, time, or cost associated
with the arc from node i to node j
continued
Shortest-Route Problem
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
xij > 0 for all i and j
continued
Origin nodes i
Transshipment nodes
Destination nodes j
s.t.
Linear Programming Formulation (continued)
Shortest-Route Problem
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Susan Winslow has an important business meeting
in Paducah this evening. She has a number of alternate routes by which she can travel from the company headquarters in Lewisburg to Paducah. The network of alternate routes and their respective travel time, ticket cost, and transport mode appear on the next two slides.
If Susan earns a wage of $15 per hour, what route
should she take to minimize the total travel cost?
Example: Shortest-Route
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
6
A
B
C
D
E
F
G
H
I
J
K
L
M
Paducah
Lewisburg
1
2
5
3
4
Network Representation
Example: Shortest-Route
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Transport Time Ticket
Route Mode (hours) Cost
A Train 4 $ 20
B Plane 1 $115
C Bus 2 $ 10
D Taxi 6 $ 90
E Train 3 1/3 $ 30
F Bus 3 $ 15
G Bus 4 2/3 $ 20
H Taxi 1 $ 15
I Train 2 1/3 $ 15
J Bus 6 1/3 $ 25
K Taxi 3 1/3 $ 50
L Train 1 1/3 $ 10
M Bus 4 2/3 $ 20
Example: Shortest-Route
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Transport Time Time Ticket Total
Route Mode (hours) Cost Cost Cost
A Train 4 $60 $ 20 $ 80
B Plane 1 $15 $115 $130
C Bus 2 $30 $ 10 $ 40
D Taxi 6 $90 $ 90 $180
E Train 3 1/3 $50 $ 30 $ 80
F Bus 3 $45 $ 15 $ 60
G Bus 4 2/3 $70 $ 20 $ 90
H Taxi 1 $15 $ 15 $ 30
I Train 2 1/3 $35 $ 15 $ 50
J Bus 6 1/3 $95 $ 25 $120
K Taxi 3 1/3 $50 $ 50 $100
L Train 1 1/3 $20 $ 10 $ 30
M Bus 4 2/3 $70 $ 20 $ 90
Example: Shortest-Route
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Shortest-Route
LP Formulation
Objective Function
Min 80x12 + 40x13 + 80x14 + 130x15 + 180x16 + 60x25
+ 100x26 + 30x34 + 90x35 + 120x36 + 30x43 + 50x45
+ 90x46 + 60x52 + 90x53 + 50x54 + 30x56
Node Flow-Conservation Constraints
x12 + x13 + x14 + x15 + x16 = 1 (origin)
– x12 + x25 + x26 – x52 = 0 (node 2)
– x13 + x34 + x35 + x36 – x43 – x53 = 0 (node 3)
– x14 – x34 + x43 + x45 + x46 – x54 = 0 (node 4)
– x15 – x25 – x35 – x45 + x52 + x53 + x54 + x56 = 0 (node 5)
x16 + x26 + x36 + x46 + x56 = 1 (destination)
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Shortest-Route
Solution Summary
Minimum total cost = $150
x12 = 0 x25 = 0 x34 = 1 x43 = 0 x52 = 0
x13 = 1 x26 = 0 x35 = 0 x45 = 1 x53 = 0
x14 = 0 x36 = 0 x46 = 0 x54 = 0
x15 = 0 x56 = 1
x16 = 0
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Maximal Flow Problem
The maximal flow problem is concerned with determining the maximal volume of flow from one node (called the source) to another node (called the sink).
In the maximal flow problem, each arc has a maximum arc flow capacity which limits the flow through the arc.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Maximal Flow Problem
A capacitated transshipment model can be developed for the maximal flow problem.
We will add an arc from the sink node back to the source node to represent the total flow through the network.
There is no capacity on the newly added sink-to-source arc.
We want to maximize the flow over the sink-to-source arc.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Maximal Flow Problem
LP Formulation
(as Capacitated Transshipment Problem)
There is a variable for every arc.
There is a constraint for every node; the flow out must equal the flow in.
There is a constraint for every arc (except the added sink-to-source arc); arc capacity cannot be exceeded.
The objective is to maximize the flow over the added, sink-to-source arc.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Maximal Flow Problem
LP Formulation
(as Capacitated Transshipment Problem)
Max xk1 (k is sink node, 1 is source node)
s.t. xij - xji = 0 (conservation of flow) i j
xij < cij (cij is capacity of ij arc)
xij > 0, for all i and j (non-negativity)
(xij represents the flow from node i to node j)
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Maximal Flow
National Express operates a fleet of cargo planes and
is in the package delivery business. NatEx is interested
in knowing what is the maximum it could transport in
one day indirectly from San Diego to Tampa (via Denver, St. Louis, Dallas, Houston and/or Atlanta) if its direct flight was out of service.
NatEx's indirect routes from San Diego to Tampa, along with their respective estimated excess shipping capacities (measured in hundreds of cubic feet per day), are shown on the next slide.
Is there sufficient excess capacity to indirectly ship 5000 cubic feet of packages in one day?
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Network Representation
2
5
1
4
7
3
4
4
3
3
2
3
4
2
3
3
3
1
5
5
1
6
3
Denver
San
Diego
St. Louis
Houston
Tampa
Atlanta
Dallas
6
Example: Maximal Flow
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Modified Network Representation
4
4
3
3
2
3
4
2
3
3
3
1
5
5
1
6
3
Sink
Source
Added
arc
2
5
1
4
7
3
6
Example: Maximal Flow
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Maximal Flow
LP Formulation
18 variables (for 17 original arcs and 1 added arc)
24 constraints
7 node flow-conservation constraints
17 arc capacity constraints (for original arcs)
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Maximal Flow
LP Formulation
Objective Function
Max x71
Node Flow-Conservation Constraints
x12 + x13 + x14 – x71 = 0 (node 1)
– x12 + x24 + x25 – x42 – x52 = 0 (node 2)
– x13 + x34 + x36 – x43 = 0 (and so on)
– x14 – x24 – x34 + x42 + x43 + x45 + x46 + x47 – x54 – x64 = 0
– x25 – x45 + x52 + x54 + x57 = 0
– x36 – x46 + x64 + x67 = 0
– x47 – x57 – x67 + x71 = 0
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Maximal Flow
LP Formulation (continued)
Arc Capacity Constraints
x12 < 4 x13 < 3 x14 < 4
x24 < 2 x25 < 3
x34 < 3 x36 < 6
x42 < 3 x43 < 5 x45 < 3 x46 < 1 x47 < 3
x52 < 3 x54 < 4 x57 < 2
x64 < 1 x67 < 5
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Alternative Optimal Solution #1
Objective Function Value = 10.000
Variable Value
x12 3.000
x13 3.000
x14 4.000
x24 1.000
x25 2.000
x34 0.000
x36 5.000
x42 0.000
x43 2.000
Variable Value
x45 0.000
x46 0.000
x47 3.000
x52 0.000
x54 0.000
x57 2.000
x64 0.000
x67 5.000
x71 10.000
Example: Maximal Flow
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Alternative Optimal Solution #1
3
4
3
2
1
2
3
2
5
5
Sink
Source
10
2
5
1
4
7
3
6
Example: Maximal Flow
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Alternative Optimal Solution #2
Objective Function Value = 0.000
Variable Value
x12 3.000
x13 3.000
x14 4.000
x24 1.000
x25 2.000
x34 0.000
x36 4.000
x42 0.000
x43 1.000
Variable Value
x45 0.000
x46 1.000
x47 3.000
x52 0.000
x54 0.000
x57 2.000
x64 0.000
x67 5.000
x71 10.000
Example: Maximal Flow
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
Example: Maximal Flow
Alternative Optimal Solution #2
3
4
3
2
1
2
3
1
1
5
4
Sink
Source
10
2
5
1
4
7
3
6
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
A Production & Inventory Application
Transportation and transshipment models can be developed for applications that have nothing to do with the physical movement of goods from origins to destinations.
For example, a transshipment model can be used to solve a production and inventory problem.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Example: Production & Inventory Application
Fodak must schedule its production of camera film for the first four months of the year. Film demand (in 000s of rolls) in January, February, March and April is expected to be 300, 500, 650 and 400, respectively. Fodak's production capacity is 500 thousand rolls of film per month.
The film business is highly competitive, so Fodak cannot afford to lose sales or keep its customers waiting. Meeting month i's demand with month i+1's production is unacceptable.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Example: Production & Inventory Application
Film produced in month i can be used to meet demand in month i or can be held in inventory to meet demand in month i+1 or month i+2 (but not later due to the film's limited shelf life). There is no film in inventory at the start of January.
The film's production and delivery cost per thousand rolls will be $500 in January and February. This cost will increase to $600 in March and April due to a new labor contract. Any film put in inventory requires additional transport costing $100 per thousand rolls. It costs $50 per thousand rolls to hold film in inventory from one month to the next.
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Network Representation
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Define the decision variables:
xij = amount of film “moving” between node i and
node j
Define objective:
Minimize total production, transportation, and inventory holding cost.
Min 600x15 + 500x18 + 600x26 + 500x29 + 700x37
+ 600x310 + 600x411 + 50x59 + 100x510
+ 50x610 + 100x611 + 50x711
Linear Programming Formulation
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Linear Programming Formulation (continued)
Define the constraints:
Amount (1000s of rolls) of film produced in January: x15 + x18 < 500
Amount (1000s of rolls) of film produced in February: x26 + x29 < 500
Amount (1000s of rolls) of film produced in March: x37 + x310 < 500
Amount (1000s of rolls) of film produced in April: x411 < 500
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Linear Programming Formulation (continued)
Define the constraints:
Amount (1000s of rolls) of film in/out of January inventory: x15 - x59 - x510 = 0
Amount (1000s of rolls) of film in/out of February inventory: x26 - x610 - x611 = 0
Amount (1000s of rolls) of film in/out of March inventory: x37 - x711 = 0
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Linear Programming Formulation (continued)
Define the constraints:
Amount (1000s of rolls) of film satisfying January demand: x18 = 300
Amount (1000s of rolls) of film satisfying February demand: x29 + x59 = 500
Amount (1000s of rolls) of film satisfying March demand: x310 + x510 + x610 = 650
Amount (1000s of rolls) of film satisfying April demand: x411 + x611 + x711 = 400
Non-negativity of variables: xij > 0, for all i and j.
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Computer Output
Objective Function Value = 1045000.000
Variable Value Reduced Cost
x15 150.000 0.000
x18 300.000 0.000
x26 0.000 100.000
x29 500.000 0.000
x37 0.000 250.000
x310 500.000 0.000
x411 400.000 0.000
x59 0.000 0.000
x510 150.000 0.000
x610 0.000 0.000
x611 0.000 150.000
x711 0.000 0.000
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
Optimal Solution
From To Amount
January Production January Demand 300
January Production January Inventory 150
February Production February Demand 500
March Production March Demand 500
January Inventory March Demand 150
April Production April Demand 400
Example: Production & Inventory Application
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
End of Chapter 6, Part B
‹#›
© 2016 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part, except for use as permitted
in a license distributed with a certain product or service or otherwise on a password-protected website for classroom use.
‹#›
‹#›
2
3
4
7
6
5
11
10
9
8
1
FEBRUARY
PRODUCTION
JANUARY
PRODUCTION
MARCH
PRODUCTION
JANUARY
DEMAND
FEBRUARY
DEMAND
MARCH
DEMAND
APRIL
DEMAND
APRIL
PRODUCTION
MONTH 1
ENDING INVENTORY
MONTH 2
ENDING INVENTORY
MONTH 3
ENDING INVENTORY
500
500
500
500
300
500
650
400
500
600
500
600
700
600
50
100
50
100
50
600