Module 04 Course Project - Status Update and Software Installation Plan

profileNovaXander98
Module04_StatusUpdateSample.docx

Module 04 Status Update Sample

Network Administration Capstone

Project Status Summary Percent Complete: xx%

The project schedule is 7% behind schedule due to inclement weather which has affected the installation of the fiber optics throughout the campus. This should not affect the project completion date as crews are planning to make up the time by working weekends and extended hours next month.

The project risks is red due to the inclement weather and servers which were delivered last month weren't configured with the correct hardware specifications. The impact of the inclement weather on the schedule will be mitigated by having crews make up the time by working weekends and extended hours next month. Currently we are working with the server vendor to resolve the server hardware configuration problem. The configuration delivered will not handle the work load of going live in two months; however, it is sufficient for development and testing activities scheduled prior to going live.

Work Planed for Last Month

For this section you can copy the "Worked Planned for Next Week" section from last week's status report and paste it into this section.

Work Completed Last Week

In this section you should provide a highlight of work performed and milestones and/or deliverables met during the past week.

Work Planned For Next Week

Provide an overview of the work being performed during the next week and any milestones or deliverables you expect to meet.

Open Issues

This section should contain a list of open issues along with their status.

Open Risks

This section should contain a list of all open risks (risks which have occurred, or are on the verge of occurring).

Deliverables and Milestones

Milestone

WBS

Planned

Forecasted

Actual

Status

Deliverable

WBS

Planned

Forecasted

Actual

Status

Open Change Requests

Change Request Name

Change Request Number

Request Date

Current Status

Add xyz Functionality

CR55043

3/14/20xx

In Review by Change Control Board

Add Redundant Servers

CR55012

2/17/20xx

Approved and Being Added to the Project Plan

Key Performance Indicators (KPI's)

Schedule - Project is Ahead of Schedule

Schedule Variance (SV): $xxxx

Schedule Performance Index (SPI): x.xx

Cost - Project is Under Budget

Cost Variance (CV): $xxx

Cost Performance Index (CPI): x.xx