Project schedule problems

profilesuse_q
MGT640Topic2InitialProjectScheduleTEMPLATEsecone.pdf

ID ID Task Mode

WBS Task Name Duration Start Finish Predecessors Successors

1 1 1 TECHNOLOGY REFRESH PROJECT 1 day? Mon 1/4/16Mon 1/4/16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 1

Project: MGT 640, Topic 2 Assignm Date: Fri 7/11/14

Total Slack

0 days? 1/4 1/4 Dec Jan Feb Mar

Qtr 4, 2015 Qtr 1, 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 2

Project: MGT 640, Topic 2 Assignm Date: Fri 7/11/14