Risk & quality management

profileWright
MGT553_Assignment4.rtf

1

MGT 5 53. Risk and Quality Mangement

Assignment 4

Monte Carlo Simulation Exercise

E quipment Installation at Globus Enterprises

The equipment installation group at Globus Enterprises is about to make a cost estimate to determine how much it will cost to install a back-up generator at a government laboratory facility. Over the years, this group has carried out more than 100 such installations and has developed a database reflecting past experience. Data on the distribution of cost for design work, building effort, and testing effort is provided in Table 1.

Cheapest

($/%)

Usual

($/%)

Expensive

($/%)

Design

9,000/30

10,000/40

12,000/30

Build

60,000/20

70,000/60

80,000/20

Test

18,000/20

20,000/50

24,000/30

Table 1. Historical Data on Cost Distributions

The data in the table picture the cost of an effort and the percentage of times this cost is achieved. For example, 30% of the time, “Design” cost $9,000; 40% of the time it cost $10,000; 30% of the time it cost $12,000.

00 16 45 84 18

83 28 82 36 91

95 14 80 68 34

54 55 13 20 70

57 68 61 37 30

09 81 24 55 21

Table 2. Two-digit Random Numbers

Questions

  • Conduct a Monte Carlo simulation to create a distribution portraying total estimated project costs. Employ ten iterations in your computation. Display the distribution graphically.

  • On the average, how much does it cost to carry out this project?

  • What is the standard deviation of the distribution that you generated (use the formula: SD = √Σ(Xi – X-bar)2/N, where SD = standard deviation, √ = square root symbol, Σ = the summation sign, Xi = the ith value of X, X-bar = the mean of the X values, and N = the number of values being considered)? What information does the standard deviation offer us that helps us develop a better understanding of risk in this case? (For more help on computing standard deviation, see below.)

  • Roughly what is the probability that the project will cost more than $105,000?

Computing standard deviation for following numbers: 8, 4, 10, 7, 6

X

X-bar

x - X-bar

Squared

8.00

7.00

1.00

1.00

4.00

7.00

-3.00

9.00

10.00

7.00

3.00

9.00

7.00

7.00

0.00

0.00

6.00

7.00

-1.00

1.00

Total =

35.00

20.00

Average = X-Bar =

7.00

4.00

(Sum Squared)/N = Variance

2.00

Sqrt(Variance) = Standard Deviation

Computing standard deviation for following numbers: 6, 7, 5.5, 8, 8.5

X

X-bar

x - X-bar

Squared

6.00

7.00

-1.00

1.00

7.00

7.00

0.00

0.00

5.50

7.00

-1.50

2.25

8.00

7.00

1.00

1.00

8.50

7.00

1.50

2.25

Total =

35.00

6.50

Average = X-Bar =

7.00

1.30

(Sum Squared)/N = Variance

1.14

Sqrt(Variance) = Standard Deviation

Note that the spread of numbers in the first case above is greater than the second case, so that

standard deviation in the first case (SD = 2.00) is greater than in the second (SD = 1.14)