Assignment Question(s):

A public accounting firm requires the following activities for an audit:

Activity

Immediate Predecessor

Activity time

A

-

3

B

A

2

C

-

5

D

B, C

2

E

A

4

F

B, C

6

G

E, D

5

a) Draw a network for this project?

b) Make a forward pass and a backward pass to determine ES, LS, EF, and LF?

c) What are the critical path?