Project Management MGT 400

Group Assignment 2 (15%, Chapter 6 & 2)

Start Date: 26 November 2020 - 11:59 pm

Due Date: 1 December 2020 - 11:59 pm

( Please upload your assessment on Moodle using Group Assignment-2 Turnitin submission link )

Student Name

Student ID

1

2

3

Section: O2

Total Earned Points: /100

3

Project Management (MGT 400) Fall 2020

Please answer the following questions (100 points)

Q1. Explain the Project types in detail and provide proper examples for each of them (15 points).

Q2. Explain the environmental factors which affects the project objectives in strategic management process (15 points)

Q3. Draw the network diagram and list the all paths (20 points).

Q4. Answer the following questions with given project network data (40 points).

a) Draw the network diagram (Use the data box for each activity)

b) Calculate Forward, Backward, Slack, CPM duration (weeks)

c) List the all paths and calculate durations for each (show the CPM path)

Q5. Prepare task identification table according to Q4 results (10 points).

1

Project Management (MGT 400) Fall 2020

ActivityABCDEFGHIJK

Predecessor---ABACDEF, HG, I

ActivityDurationPredecessor

A13-

B18-

C13A

D22A,B

E15C

F16C

G21D, E

H15F, G

I14F,H

ActivityDurationESEFLSLFSlack

A

B

D

E

F

G

I