Running head: PROJECT IMPLEMENTATION PHASE II & III 1

PROJECT IMPLEMENTATION PHASE II & III 3

Project Implementation Phase II & III

Michael J. Wallace

Grand Canyon University MGT-655

3 October 2018

Methodologies and Strategies, I will implement to meet the Goals

The methodologies and strategies used to implement a project in a hospital depend on the objectives and the risk one wants to take. The formulation of a strategy for the implementation of the project can be seen from two perspectives: Degree of propensity or aversion to change and Specific goal (Chapman, 2011). The Degree of propensity or aversion to change Typically follows three paths to which are: Implementation of an elementary version, Implementation in a single effort and Implementation with deployment. The Implementation of an elementary version Sometimes is said that it starts with the "out of the box" which means that the system is accepted as it is ("as is") to then add, gradually, additional functions once the basic functions work and do it satisfactorily. On the other hand, Implementation in a single effort strategy is the most ambitious strategy which makes it is possible to propose different approaches, ranging from the implementation of isolated modules, which will gradually be linked to the legacy systems of the project until the implementation of the complete system. Finally, the Implementation with deployment or roll out is variant to both (Bakeev, 2010).

Business Functions that will be impacted by My Action Plan

The main responsibility of a project team is developing a plan and supervising the execution of the project, which will maintain relationships with external programmers (consultants), administrators and cooperative members. It will also impact business plans such as the human resource because the action plan must Determine all the tasks necessary to achieve each objective where fundamental human resources, capital and budget needs, express analysis of risks, training plans, pilot plan, and execution plan are put into consideration, and they involve human recourse. The action plan has to Define the duration and resources required for each task, and it also has to Determine and calculate the costs that will be used in the project thus affecting the accounting and bookkeeping function of a business. Consultation strategy is very crucial to implement the strategy across business functions. Involving all the stakeholders in every stage of implementation will also ensure that the action plan is fully implemented and every stakeholder will feel being part of the plan (Sheikh et al., 2011).

Project Implementation Timeline

Item

Deliverable

Description

Responsibility or acceptance criteria

Suggested timeframe

Estimated delivery date

Status

1

Contact made to the cite of implementation

Notification that there is a project that is commencing at the specified cite

manager

2

Documentation of agreements between stakeholders

A formal is made through consultation between the stakeholders

Project sponsor

7-14 days

3

Nomination of implementation team

There is nomination for core stakeholder’s group

Formal invitations to the identified potential team.

7-14 days

4

Confirmation of the implementation team

Invitees accept invitation

Implementation team is confirmed

14-28 days

5

Project team starts working on the project

Each member of the project team is given roles to play

Project manager

One year

6

Evaluation of the project by the stakeholders

The status of the project is reviewed, any hitches are addressed by the stakeholders

Project manager and stake holders

6 months

7

Official handover of project to the hospital management

A complete project is handed over to the management of the hospital

Project manager, stakeholders and hospital management

2 moths

Communication plan

The method that will be used in the communication plan are presentations, official documentation, and email. This is because they can be used as a reference when needed and they make it possible for follow-up. The communication plan will help me fully implement the plan because stakeholders have fully agreed on it and my duty are to remind them.

References

Bakeev, K. A. (Ed.). (2010). Process analytical technology: spectroscopic tools and implementation strategies for the chemical and pharmaceutical industries. John Wiley & Sons.

Chapman, R. J. (2011). Simple tools and techniques for enterprise risk management (Vol. 553). John Wiley & Sons.

Sheikh, A., Cornford, T., Barber, N., Avery, A., Takian, A., Lichtner, V., ... & Morrison, Z. (2011). Implementation and adoption of nationwide electronic health records in secondary care in England: final qualitative results from prospective national evaluation in “early adopter” hospitals. Bmj, 343, d6054.

3

Communication

Item

Schedule /

How Often/

Due DatesRecipientsPerson Responsible

Format and

Method of

Distribution

IntroductiononceStakeholdersProject manager

Presentation

and bulletins

Project

Overview

Project Kickoffonce

Stakeholders and

team membersProject manager

Emails and

phone calls

CharterOnce

Stakeholders and

team membersProject manager

Presentation

and bulletins

Core

Documents/

ResearchEvery week

Stakeholders and

team membersProject manager

Official

documents

Project

Schedule/timeli

neonce

Stakeholders and

team members

and hospital

managementProject managerMemo

WorkplanOnceTeam membersProject managerMemo

Communication

plan Weekly

Stakeholders and

team membersProject managerMemo

Education PlanWeeklyTeam membersProject managerMemo

Testing PlanOnce

Stakeholders and

team membersProject managerMemo

Implementatio

n planOnce

Stakeholders and

team membersProject manager

Bulletins,

official

documents

and

presentation

Meeting

MinutesEvery meeting date

Stakeholders and

team membersProject manager

Official

documents

Email Groups:

define groupOnceTeam membersProject managerEmail

Project UpdatesAlways/ when requested

Stakeholders and

team members

and hospital

managementProject manager

Presentation

and official

documents

Project

PresentationsOnce a week

Stakeholders and

team membersProject manager

Presentation

s and official

documents

Project SurveysOnce

Stakeholders and

team membersProject manager

Official

documents

Project

Assessments/

anaysis Every month

Stakeholders and

team membersProject manager

Presentation

and official

documents

Information

updates Daily

Stakeholders and

team membersProject managerEmail

Change

RequestsWhen needed

Stakeholders and

sponsorsProject manager

Official

documents

Documentation

of OutcomesOnceTeam membersProject manager

Official

documents