Program Evaluation and Review Technique (PERT) and Monte Carlo Analyses
Refer to the activities defined in the Unit II Assignment, and complete the following tasks.
1. Create a table of the activities, and identify logical relationships by identifying predecessors.
2. Estimate activity durations using three-point estimates.
3. Create a PERT schedule, and identify the project critical path.
4. Using the breakfast schedule spreadsheet as a guide (along with the Monte Carlo simulation supplement in Chapter 7 of the textbook), model your schedule using Monte Carlo analysis (10 trial runs minimum).
To assist as you create your assignment, watch the Backward Pass Simulation video .
Also watch the Forward Pass Simulation video .
A transcript and closed captioning are available once you access the videos.
Submit your PERT and Monte Carlo analyses for grading along with a one-page written summary of the results and a brief discussion of how the results could be used to inform a project schedule risk plan. APA Style and outside sources are not a requirement for this assignment.