Project Initiation, Planning and Execution

profileBobby1134@
MBA642_T3_2020_Workshop_05_v01.pdf

MBA642

Project Initiation,

Planning and Execution

Workshop Week 5

Project Scheduling: Work Activity

Copyright Notice

COPYRIGHT COMMONWEALTH OF AUSTRALIA

Copyright Regulations 1969 WARNING

This material has been reproduced and communicated to you by or on behalf of

Kaplan Higher Education pursuant to Part VB of the Copyright Act 1968 (the Act).

The material in this communication may be subject to copyright under the Act. Any

further reproduction or communication of this material by you may be the subject of

copyright protection under the Act.

Do not remove this notice

Week 4 Review

• Precedence relationships

• Time and Action (Gantt)

• Crashing projects

• Understand the factors that describe a project

• Examine the process for a planning work activity

• Identify the advantages of using a work

breakdown structure

• Construct a milestone plan

Week 5 Lecture Objectives

Describing a Project

1. The purpose of the project

- Why

2. The overall scope of work

- What

3. The outputs from the project

- Deliverables at end of project

4. The areas of work

- Intermediate deliverables

1. The Purpose of the Project

The purpose of a project could include:

• A statement of a business need

– e.g., launch a new product,

• A problem to be resolved

– e.g., too many customer complaints,

reduce costs

• A strategic objective

– e.g., open a new facility

2. The Overall Scope

• The work to be undertaken:

– What is included?

– What is required to solve the problem?

– What are the benefits?

• The work excluded

– What we are NOT going to do

• Interfaces with other projects

3. The Project Outputs

• Deliverables

– Must address all the work within the scope of the project

– Not address work outside the scope

– Set parameters for managing quality, cost and time

• Quantitative measures

– Use of metrics

• Qualitative measures

– Use of expert opinion

Quantitative Measures

• Defining “what” to measure: Measures that provide the maximum

insight into the objectives and bear the maximum correlation with the

objectives should be used.

• Define the measurement framework: This involves deciding the tools

used, the frequency at which the observations will be pooled, and

assigning responsibilities for measurement and presentation.

• Collection and presentation of data: project controllers collect the

information and present it to management in an easy to digest format.

• Analysis of the data and initiating corrective action as necessary.

• Review the effectiveness of the measurement and corrective actions

by comparing “before” and “after” numbers.

Shouche, S., Borthakur, A., & Mate, N. (2006). Quantitative project management—use of metrics for effective project

management. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA:

Project Management Institute.

Qualitative Measures

• Qualitative measurements measure a project based largely on

quality determinations

• They are documents that provide requirements, specifications,

guidelines, or characteristics that can be used consistently to ensure

that materials, products, processes, and services are fit for their

purpose.

4. The Areas of Work

Areas of work emanating from the project need to be defined;

• Facilities

• Technology

• Organisation

Why?

• To monitor intermediate deliverables

• Sets a stable framework

• Controls devolution of management in the hierarchy

Workshop Activity

• In small groups of 3 or 4, prepare a project

description for the following scenario

• Share your results with the class

Scenario:

Yourself and 3 friends have

decided to go to Bali together for

a holiday. You have decided that

you want to stay for 3 days in 3

different locations. You are also

aware that you all have varying

interests.

Hierarchy of Work Activity

• Areas of Work

– Intermediate deliverables

• Milestones

– Packages of work

– Deliverables

• Activities

– Tasks

– Assigned work

Advantages of using a Work

Breakdown Structure (WBS)

1. Better control

2. Coherent delegation

3. Levels of estimating and control

4. Containment of risk

WBS 1. Better Control

• Managing through the WBS with a

single point of responsibility

• Focus on results: what is to be

achieved, not how to do it

• Balance results through the WBS

2. Coherent Delegation

• Parcelling of work is

natural

• Responsibility can easily

be assigned

• Resources can be

controlled and measured

3. Levels of Estimating and

Control

The level of estimating the WBS,

depends on:

• The size, type and duration of

a project

• The purpose for which the

estimates will be used

• The current state in the

project life cycle

• The requirements for effective

control

4. Containment of Risk

• The uncertainty introduced by risk

• The need to contain risk

Workshop Activity • In small groups of 3 or 4, identify specific

advantages and disadvantages of a creating a

WBS for the following scenario

• Share your results with the class

Scenario:

Yourself and 3 friends have

decided to go to Bali together

for a holiday. You have decided

that you want to stay for 3 days

in 3 different locations. You are

also aware that you all have

varying interests.

The Hierarchy of the WBS

• Areas of Work

– Intermediate deliverables

• Milestones

– Packages of work

– Deliverables

• Activities

– Tasks

Source: Adapted from, Turner, JR (2009) The Handbook of Project-

Based Management: leading Strategic Change in Organizations, 3rd

edn, McGraw Hill, Sydney.

Features of a Milestone

• Be understandable to everyone

• Provide qualitative and quantitative control

• Focus on decisions

• Show the logical sequence

• Give a single page overview

Source: Adapted from, Turner, JR (2009) The Handbook of Project-Based Management:

leading Strategic Change in Organizations, 3rd edn, McGraw Hill, Sydney.

Developing a Milestone Plan

1. Start by agreeing to the final milestone, the end of the project

2. Generate ideas for interim milestones

– Identify the area of work for each

3. Review the milestones

– Are these activities or key deliverables?

– Are they discrete or do they belong to other milestones?

4. Draw logical dependencies between the milestones

5. Make the final drawing

– Repeat 2,3 4 until a coherent drawing emerges

Source: Adapted from, Turner, JR (2009) The Handbook of Project-Based Management:

leading Strategic Change in Organizations, 3rd edn, McGraw Hill, Sydney.

Workshop Activity

• In small groups of 3 or 4, identify the

milestones the following scenario

• Share your results with the class

Scenario:

Yourself and 3 friends have decided to go to Bali

together for a holiday at the end of term. You have

decided that you want to stay for 3 days in 3

different locations. You are also aware that you all

have varying interests.

The Milestone Overview

Source: Turner, JR (2009) The Handbook of Project-Based Management: leading

Strategic Change in Organizations, 3rd edn, McGraw Hill, Sydney.

The WBS as a Tree

Source: Turner, JR (2009) The Handbook of Project-Based Management: leading

Strategic Change in Organizations, 3rd edn, McGraw Hill, Sydney.

The Milestone List

Source: Turner, JR (2009) The Handbook of Project-Based Management: leading

Strategic Change in Organizations, 3rd edn, McGraw Hill, Sydney.

The Milestone Statement

Source: Turner, JR (2009) The Handbook of Project-Based Management: leading Strategic

Change in Organizations, 3rd edn, McGraw Hill, Sydney.

The Milestone Plan

Source: Turner, JR (2009) The Handbook of Project-Based Management: leading Strategic

Change in Organizations, 3rd edn, McGraw Hill, Sydney.

Workshop Activity

• In small groups of 2, select one milestone from the

previous activity and prepare a milestone statement

• Share your results with the class

Scenario:

Yourself and 3 friends have

decided to go to Bali

together for a holiday. You

have decided that you want

to stay for 3 days in 3

different locations. You are

also aware that you all have

varying interests.

Summary

• A project can be described by its:

– purpose, scope, outputs

• Breaking down work activity (WBS) is a

process by which the project is subdivided

for management and control purposes:

– Areas of work

– Milestones

– Activities and Schedule

For Week 7

• Week 6 – guest lecturer

Week 7

• Understand the factors that determine

technology adoption

• Identify different types of project

management software

• Examine a range of software applications