Project Initiation, Planning and Execution

profileBobby1134@
MBA642_T3_2020_Workshop_03.pdf

MBA642

Project Initiation,

Planning and Execution

Workshop Week 3

Project Scheduling: Duration

Estimation and Critical Path

Copyright Notice

COPYRIGHT COMMONWEALTH OF AUSTRALIA

Copyright Regulations 1969 WARNING

This material has been reproduced and communicated to you by or on behalf of

Kaplan Higher Education pursuant to Part VB of the Copyright Act 1968 (the Act).

The material in this communication may be subject to copyright under the Act. Any

further reproduction or communication of this material by you may be the subject of

copyright protection under the Act.

Do not remove this notice

Week 2 Review

• Scheduling

• Network Diagrams

• Activity Networks

• Activity on Node

• Perform activity duration estimation based on the use of probabilistic estimating techniques

• Construct the critical path for a project schedule network using forward and backward passes

• Identify activity float and the manner in which it is determined

• Understand the steps that can be employed to reduce the critical path

Week 3 Lecture Objectives

Workshop Activity In groups of 3 or 4, using your smartphone or tablet, do

a search on the Internet of the term “project

scheduling”. Thousands of hits will be generated.

Examine a selection of these results and discuss with

the class what common themes you found. Take the

best features of these and write your own definition.

Explain why it is the best version.

Duration Estimation – How?

Two primary means for developing duration estimates:

1. Deterministic models for activity durations where project

tasks are fairly predictable (i.e. little variation in the activity

completion time).

2. Mathematical models for where tasks are unpredictable,

we may use to predict likely duration.

Activity Durations – How?

Experience

– If similar work, we can use past experience as a guide. This approach is

relatively easy

– Main weakness is that it assumes what worked in the past will be

relevant today.

– We must also be aware of the potential for using distorted or outdated

information.

Activity Durations – How?

Expert opinion

– Intuitively this approach would seem to be useful.

– Potential weakness: an expert’s estimate of completion time may not

necessarily be valid for non-experts doing the same activity.

Mathematical derivation

– Benefit: offers a more objective approach to activity duration estimation

and avoids many of the problems that can be found in more subjective

methods.

– This method involves developing duration probability based on a logical

analysis of best-case, most likely case, and worst-case scenarios.

Workshop Activity

On your smart phone or tablet, use a search engine to

find “how long does it take to build a house?”

In groups of 3 or 4, discuss your findings. What are

some of the variables that impact on the time taken to

build a house?

How might you go about planning for such a project?

Duration Estimation

To derive a reasonable probabilistic estimate for

an activity’s duration, we need to identify three

values:

1. The activity’s most likely duration

2. The activity’s most pessimistic

duration

3. The activity’s most optimistic duration

Workshop Activity The following terms are commonly used in probability

statistics when applied to Duration Estimation for projects:

• Mean

• Median

• Mode

• Standard deviation

• Normal distribution

• Standard deviation

• Variance

• Confidence interval

Divide into groups of 3 or 4 and select 2 terms and explain

them to the rest of the class using simple examples. You can

use internet searching for this task if that helps.

Duration Estimation Using Probability

• Probability distributions can either be:

- Symmetrical (normal distribution) or

- Asymmetrical (beta distribution)

• Normal distribution – implies that the probability

of an event taking the most likely time is one that

is centered on the mean (average) of the

distribution.

• Pessimistic and optimistic values – estimated

at the 95% CI from either end of the distribution,

so cancel each other out.

• Hence the mean value is the expected duration

time for the activity.

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

Symmetrical (Normal) Distribution

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

Asymmetrical (Beta) Distribution for Activity Duration estimation

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

Two assumptions for converting the values of m, a, and b into

estimates of the expected time (TE) and variance (s2) of the duration

for the activity:

1. The standard deviation (a measure of how spread out your data is)

of the duration required to complete the task (s) equals one-sixth of

the range for reasonably possible time requirements.

2. Because the probability distribution are not symmetrical about the

mean, beta represents the distribution of possible alternative

expected duration times (TE) for estimating activities.

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

The beta distribution suggests that the calculation for deriving TE is

shown as:

TE = (a + 4m + b) / 6

where

TE = estimated time for activity

a = most optimistic time to complete the activity

m = most likely time to complete the activity (mode of the

distribution). The mode of a set of data values, is the value that appears

most often.

b = most pessimistic time to complete the activity

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

Duration Estimation Using Probability

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p329

Workshop Activity

Duration Estimation

Activity Optimistic Likely Pessimistic Beta (1:4:1)/6

Planning 4 6 8

Foundations 2 3 7

Framing 3 5 10

Windows and Doors 1 2 5

Brickwork 3 5 8

Roof covering 2 3 6

Flooring 1 2 4

Electrical and

Plumbing

1 2 5

Painting 3 5 7

Constructing the Critical Path

• Critical path calculations link activity

durations to the pre-constructed project

activity network.

• Project network – we’ve developed using

activity precedence logic.

• Next, following task duration estimates, the

values are applied in a structured process to

each activity to determine overall project

length.

Constructing the Critical Path

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p331

Constructing the Critical Path

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson

Education Inc., p332

Partial Project Activity Network with task Durations

Four separate paths can be identified, labelled as follows:

Path One: A - B - E - H

Path Two: A - B - D - F - H

Path Three: A - C - D - F - H

Path Four: A - C - G - H

Constructing the Critical Path

Critical path (definition) – “series of interdependent

activities of a project, connected end-to-end, which

determines the shortest total length of the project.”

In the previous example; the shortest total length of

time needed to complete a project is determined by

the longest path through the network.

The length of the four paths listed above can be

derived simply by adding their individual activity

durations together.

Constructing the Critical Path

The length of the four paths can be obtained simply by

adding their individual activity durations together.

Hence,

Path One: A - B - E - H : 18 weeks

Path Two: A - B - D - F - H : 29 weeks

Path Three: A - C - D - F - H : 30 weeks

Path Four: A - C - G – H : 22 weeks

Path Three is the critical path for this activity.

Workshop Activity In groups of 3 or 4, using your smartphone or

tablet to find definitions for “forward pass” and

“backward pass”.

Why are these concepts important in Project

Management? Share your thoughts with the

class.

The Forward Pass

The forward pass – used to

determine the earliest times

each activity can begin and the

earliest it can be completed.

A. Starts day 0, takes 5 days,

so finishes day 5.

B. Starts after A finishes on

day 5, takes 5 days, so

finishes day 10 (5+5).

Partial Activity Network with Merge Point at Activity D

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p333

The Forward Pass

Activity Network with Forward Pass

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p334

The Backward Pass

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p334

Activity Network with Backward Pass

The Backward Pass

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p335

Project Network with Activity Slack and Critical Path

Note: Critical path is indicated with bold arrows.

The Backward Pass

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p336

• Note that activity float is determined as a result of

performing the forward and backward passes

through the network.

• Until we have done the calculations for ES, EF, LS,

and LF, we cannot be certain which activities have

float associated with them and which do not.

• Using this information to determine the project critical

path suggests that the critical path is the network

path with no activity slack associated with it. In our

project, we can determine the critical path by linking

the nodes with no float: A - C - D - F - H.

The Backward Pass

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson

Education Inc., p336

• We can also determine path float; that is, the linkage of each

node within a noncritical path.

• The path A - B - E - H has a total of 13 weeks of float; however,

it may be impossible to “borrow” against the float of later

activities if the result is to conflict with the critical path.

• Although there are 13 weeks of float for the path, activity B

cannot consume more than one week of the total float before

becoming part of the critical path.

• This is because B is a predecessor activity to activity D, which

is on the critical path.

• Using more than one week of extra float time to complete

activity B will result in delaying the ES for critical activity D and

thereby lengthening the project’s critical path.

Workshop Activity

In groups of 3 or 4, go to the following website:

https://theconstructor.org/construction/critical-path-method-cpm-

advantages/6873/

Select one of the stated advantages of CPM (Critical Path Method)

and be prepared to critique it with the rest of the class.

Steps to Reduce the Critical Path

Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p340

Often when constructing an activity network and seeing the

expected duration, we may look for ways to shorten the

project. The list below shows some of the more common

methods for reducing the critical path.

Summary

• Understand the practical application of scheduling

terminology.

• Apply the logic to create activity networks.

• Develop an activity network using Activity-on-Node

techniques.

• Perform activity duration estimation based on the

use of probability estimating techniques.

• Construct the critical path for a project schedule

network using forward and backward passes.

• Identify activity float and how it is determined.

• Apply lag relationships to project activities

• Construct and comprehend Time & Action

(Gantt) charts

• Recognise alternative means to accelerate

projects, including their benefits and drawbacks

• Understand the trade-offs required in the decision

to crash project activities

Next Week