MBA6231 - 1.1 - project charter.docx

CU_Horiz_RGB

Project Charter

Project Charter

Student Name

Institution

Course Code

Project Title: Michael Joseph Place, The place to be

Project Start Date: 25/7/2018

Projected Finish Date: 25/12/2018

Budget Information: $ 4,500.00

Project Manager: Student name, [email protected], 210- 105 - 6676

Business Need

The project manager will be hosting an evening lounge event that will be targeting the clientele to an upscale lounge to be built in downtown. Through such an event the city will have a positive exposure.

There will be need for effective marketing, music, modern décor and most likely investors. The menu for food and drinks will need to be within budget. The venue needs to have amiable space and adequate seats for all guests.

The first step to this project involves coming up with a plan on a piece of paper. Once this is done the next step will involve selection of vendors to various goods and services. Once everything has been put to perspective the next stage will be to involve investors who will include local business owners. These investors will be encouraged to do so with the exchange for them to market and advertise their products at the event. We will have three packages for investors including Silver, Gold and Platinum packages.

Project Objectives

The proposal is to have a social entertainment evening lounge in Chicago. The project managers will be showcasing the new concept of entertainment by holding a series of events known as “The Place to be!”

· The events will be used to showcase the atmosphere that the new lounge will be offering

· The events will offer the professional audiences an opportunity to network while at the same time being entertained.

· The events will be targeting an audience of 150 attendants

· To have an environment where attendants can dance, dine and drink socially while discussing business.

Approach

This project will be managed in accordance with the PMI approach as modified.

Assumptions/Constraints/Dependencies

The assumption is that with the provision of an exquisite and upscale venue that is mature in Chicago, IL, will be successful due to the fact that there is no such a venue within a 100 mile radius.

One of the likely constraint is finding a venue that grabs attention of the targeted crowd.

The success of these events depends on attracting two sets of individuals. One of them is investors and the other is private professionals who will attend a social event at night.

Initial Risk Factors

· Obtaining a liquor license on time for the event is the major risk factor.

· Failure of attendees despite investing money and time is another risk.

· Failing to complete the organizational plans within 30 days before the event series begin.

· Not attracting any viable investors

Regulatory cost/impact

One of the needed licensing is from the city council where I will be required to get a special event license. This will enable us to have alcohol in the premises. There will be need for security and fire reviews from the respective departments of city council. The parking code and regulations for the venue will also have to be looked into seriously.

Roles and Responsibilities

Role
Name
Organization and Position
Contact Information

Project sponsor

Michael Joseph

Chief Executive Office

[email protected]

210-321-4560

Project manager

Student Name

Michael Joseph Place

Operations Manager

[email protected]

210- 105 - 6676

<title>

<title>

<title>

Sign-Off

Michael Joseph

Student Name

Comments

No comments at this time

Revised to accommodate PMBOK® 4th edition

3

MBA6231 - 1.docx

Running head: PROJECT ANALYSIS, SELECTION, AND CHARTER 1

PROJECT ANALYSIS, SELECTION, AND CHARTER 6

MBA-FP6231: Assessment 1

Student Name

Institution

Course Code

Executive Summary

In this paper the article, “An Experiential Case Study in IT Project Management Planning: The Petroleum Engineering Economics Evaluation Software Imperative,” which was written by Charles Davis will be critically analyzed. The author will then continue to develop three major concerns from the article and at the same time offer possible solutions to the raised concerns. The paper will also try to analyze and describe potential risks that the project may likely encounter.

Introduction

The article by Charles Davis entitled, “An Experiential Case Study in IT Project Management Planning: The Petroleum Engineering Economics Evaluation Software Imperative” is crucial to scholars of project management especially in regards to the planning phase. The article has also addressed certain notions within the development of a project and certain issues that may arise in the planning process. Human resource matters within a project are crucial and therefore a need for appropriate experience level to be able to deal with the same;

Concerns and Possible Solutions

Concern 1

The first concern that faces Hopkins & Associates is the completion of the project and their credibility in the future. The credibility of a company solely depends on its continuance to produce high quality products that are of use to the clients. In case the company fails to produce a high quality product its market share and future credibility will be hurt. This therefore means that the company under all means has to produce a successful PREsys computer software. All stakeholders should be concerned with the prospects of this project since the reputation and credibility relies on its success.

One of the solutions that the company can implement is the use of simulations using real life verifiable data. A committee made up of engineers and IT experts needs to verify the results of these simulations. Once it’s ascertained that the software can provide successful situations then there is a likelihood of its success.

Concern 2

Another concern that Davis has illustrated is the very fact that the institution is not staffed with employees possessing the much needed experience in engineering. Davis (2005) writes “Ken Summers’s mentally scrolls through his rolodex of employees (all of whom appear to be incredibly talented) and none seem to “fit the bill.” Except one, his star employee or his “ace in the hole.” Gardner has the experience and needed credibility for the project however Davis notes that his ethics and judgement are a potential risk to the project, (Davis, 2005). The scope of such a huge project should not be allowed to rest on the shoulders of one man.

To deal with this concern Hopkins & Associates should employ the services of contractors who have experience in dealing with such projects. As is the case with many companies, the firm should ensure that no employee is irreplaceable due to their unique experiences. Having too much stress and pressure into a few employees from different sections of the project could proof to be disastrous. Errors and miscalculations are likely to occur costing the company its reputation and huge costs.

Concern 3

The top management of the firm and its executives do not understand the potential of this software and therefore are likely to be misguided. The top management lack of knowledge in the project is another concern raised by Davis. He states that the top management of Hopkins & Associates see it as a threat if the matter is not addressed abruptly and therefore require that the software is quickly developed and this needs to be done as soon as possible (Davis, 2005).

Software development is a tricky affair this is due to the fact that it requires coming up with the code, testing it and retesting it and the eventual editing of the same code which should be followed with more testing and adjustments. The managers want to quicken the process which is likely to lead to more errors and problems which will lead to mechanical problems. With the management not being aware of the needed time and amount of work to be put into this project the top management is risking the success of the software.

The senior management forecasts that this project will be highly successful and that the only solution is for them to trust and have faith the project managers. They should give the developers and team managers, “a reasonable chance of developing a first-rate system that will meet the needs identified while standing up to the time pressures effectively” (Davis, 2005).

Risks facing the project

From the analysis of this article there are two specific and serious risks that Davis has written about in the article. He has described the risks as being diametrically opposed to the other (Davis, 2005). One of the risks is the possibility that the system will not be ready on time. Hopkins & Associates will be at risk of losing their covetous position in the oil and gas consultation industry. The second risk that Davis points out is the fact that the PREsys software could be introduced into the market before it is ready for use. Considering the oil and gas industry this could proof fatal for Hopkins & Associates. One needs to also consider that if this software is not introduced into the market on time then another firm is likely to do the same before them leading to a monetary loss on the firm.

Investing on a project that has very many unknowns is not a wise business decision. The management of the company needs to examine and consider all relevant risk assessments and clearly understand the likely consequences if the project is not completed as planned. They should then make a decision whether the risk was worth it in the first place. It was premature to approve this project as it was important that there be a well laid out plan to enable the so=mooth running of the project.

References

Davis, C. K. (2005). An Experiential Case Study in IT Project Management Planning: The Petroleum Engineering Economics Evaluation Software Imperative. Journal of Cases on Information Technology, 7(1), 1–21.

MBA6231 - 2.docx

Michael

Joseph

Place

Project Scope Statement

Project Scope Statement

Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project.

Project Name:

1st Quarterly evening hosted by Michael Joseph

Prepared By: Student Name

Date

07/25/2018

Version History (insert rows as needed):

Version
Date
Comments

1.0

1. Executive Summary

Michael Joseph Place will be the new and most tranquil spot in the city for entertainment. The lounge offers a sophisticated environment that enables patrons to be centered on the people rather than the party. Michael Joseph Place is offering a mature, serene environment for all professionals based in Chicago, IL where they can enjoy the company of their peers. Clients will be treated to an exquisite and conservative environment as they dine and enjoy live music enabling them to focus on what matters to them most, their profession and clients. The lounge is focused towards ensuring you have an unforgettable social experience.

Note: In any instance where there is a discrepancy between the Project Charter and the Project Scope Statement, the latter is considered authoritative.

2. Business Objectives

2.1 Product Description (Solution)

The setting being proposed at Michael Joseph Place has not been witnessed in Chicago so far. An exquisite environment, Live Music coupled up with upscale dining all served under the same roof will be unique in Chicago.

2.2 Business Objectives

To capitalize on having an excellent location

To launch the new venue by having a grand opening event

Ensure tight and efficient control of operations, costs and cash by using modern technology

Ensure food provides at least 33% profit margin

Ensure that beverage revenue has 25% margin

3. Project Description

For each area below, provide sufficient detail to define this project adequately.

3.1 Project Scope: Plan for Michael Joseph Place grand opening

Includes (list deliverables):

Book artists to offer live performances

Plan catering for grand opening

Come up with a budget plan for the grand opening

Decide on a strategic day for grand opening

Develop a comprehensive marketing Campaign

Does not include:

A Website or any software

3.2 Dependencies (External and Internal)

Investors engagements

3.3 Assumptions

The date to be set to a day that there is a homecoming football game.

The project scope will not be affected.

3.4 Constraints

Employing freelancers rather than hiring full-time staff

4. Project Milestones

Target Date

Project Start

Aug. 1, 2018

Meeting with investors

Aug. 6, 2018

Hire Freelancers and Contractors

Aug. 18, 2018

Book a Live Band and other artists

Aug. 25, 2018

Project Complete

Dec 2, 2018

5. Project Approach

Briefly describe how each of the following will be handled. Provide links to relevant documents as appropriate.

5.1 Change Management

This is a sequence of events or even activities that a project manager and in some cases a change management team would use to manage the expected change after a project. This process is done in three phases which include preparation, management of the change and finally reinforcing the change.

5.2 Communication Management

Communications management is aimed at ensuring that the collection, distribution, storage and generation of information towards the project is timely and appropriate. It involves interviewing potential investors, clients and even contractors.

5.3 Quality Management

The project manager will put in place a quality management strategy that will ensure that the event and the process are both of top quality. For this project to be successful it has to meet the set quality objectives through the use of integrated quality approach that defines quality standards while measuring and continuously improving quality.

5.4 Resource Management

This is a comprehensive planning process which takes into account the available resources which includes humans to ensure that there is achievement of long term sustainable benefits. This process brings together every resource group which would otherwise work separately. Resource management involves creation of a planning team, creating an overview of the entire project, issues identification, recognizing all available resources, coming up with objectives and strategies. The process also involves implementing and monitoring the entire project.

5.5 Critical Success Factors

Customer Contentment, dining quality, number of people expected to attend the grand opening

5.6 Risk Management

The premises where the event will be held were built in the year 2000. Surveying has been done to ascertain whether the building has asbestos. The report confirmed that there was no asbestos-containing materials used.

5.7 Project Organization

Project organization is a formal structure that helps in the coordination together with the implementation of project activities. It involves investors, contractors and project managers.

6. Authorizations

The Project Scope Statement is approved by the:

Project Sponsor

Michael Joseph

Project Manager

Student Name

Project performance baseline changes will be approved by the:

Project Sponsor

Michael Joseph

Project Manager

Student Name

Project deliverables will be approved and accepted by the:

Project Sponsor

Michael Joseph

Key Stakeholders

Student Name

7. Project Scope Statement Approval

Project Name

1st Quarterly evening hosted by Michael Joseph

Project Manager

Student Name

The purpose of this document is to provide a vehicle for documenting the initial planning efforts for the project. It is used to reach a satisfactory level of mutual agreement between the Project Manager and the Project Sponsors and Owners with respect to the objectives and scope of the project before significant resources are committed and expenses incurred.

I have reviewed the information contained in this Project Scope Statement and agree:

Name
Role
Signature
Date

The signatures above indicate an understanding of the purpose and content of this document by those signing it. By signing this document, they agree to this as the formal Project Scope Statement document.

Put your organization name here

Page 6

Revised to accommodate PMBOK® 4th edition

MBA6231 - 4.xlsx

Total Estimated Costs

Michael Joseph Place Cost Estimate
Total Estimated Costs
Category Estimated Cost
Food and Beverage $ 1,700.00
Rentals and Entertainment $ 2,100.00
Location $ 500.00
Misc. Costs $ 200.00
Total $ 4,500.00
Supporting Documentation
Constraints
The highest likely constraint at the moment is related to the venue. I am worried that the venue might not pull the expected crowd for this event due to its location. Getting an approval to hold a special event is likely to be another constraint. The hired caterer will be a freelancer and therefore there is a chance that he could be late or deliver food that is not up to standards. The guests are expected to come driving, and therefore parking is likely to be an issue. The hired staffs will be serving professionals and are therefore expected to meet high standards in customer service. The temperatures will need to be well controlled to offer the expected ambience. Advertisements should be done in an orderly, timely manner to ensure that they do not interrupt the event.
Dependencies
Investors are key determinants of the success of this event which targets a private professional crowd. Marketing will also determine the level of attendance to this event and especially now that it will be at night. The event will be defined as a success if the attendance is encouraging and that the business professionals are cooperative. The staff have to arrive on time, food needs to be delicious while the ambience needs to be relaxing and well planned.
Assumptions
The assumption of this project is that once there is a good offering to the target clients they will attend. The clients need to be aware that this location will be exquisite, upscale and tranquil. The assumption is that since there is no such location in Chicago, IL within 100 miles radius clients will come. Failure to attend by the target audience will mean that the event will not be successful. The marketing strategy is that we will aim to attract a certain audience thereby enabling a connection of various professional relationships.

category A

Cost Estimate
Food and Beverage
Item # Item Price Qty Estimated Cost Explanation
1 Caterer $ 1,200.00 1 $ 1,200.00 Cost for attending to 100 guests which includes dinner and drinks
2 Staffing $ 500.00 5 $ 500.00 Total cost for 5 Staffs who will serve the food and drinks
Total $ 1,700.00 $ 1,700.00

category B

Cost Estimate
Rentals and Entertainment
Item # Item Price Qty Estimated Cost Explanation
1 Live band $ 300.00 1 $ 300.00 4 hours of performance
2 Linen $ 350.00 20 $ 350.00 Total price for 20 table cloths
3 Tables $ 200.00 20 $ 200.00 Total price for 20 tables
4 Chairs $ 250.00 110 $ 250.00 Total price for 110 chairs
5 Lighting $ 100.00 4 $ 100.00 Total price for 4 up lights
6 Advertising $ 250.00 n/a $ 250.00 Plan is to use social media adverts and a radio spot
7 Event décor $ 650.00 n/a $ 650.00 The total cost for the set up and decoration
Total $ 2,100.00 $ 2,100.00

category C

Cost Estimate
Location
Item # Item Price Qty Estimated Cost Explanation
1 Venue $ 500.00 1 $ 500.00
2 Parking Free 1 Free No cost to park
Total $ 500.00 $ 500.00

MBA6231 - 5.docx

CU_Horiz_RGB

Risk Matrix

Risk Matrix

Project Name:

Risk

#

Risk

Probability

Importance

Impact

Response to Risk

Action Plan

Person Responsible

Status

01

Catering Issues

Highly

Possible

High

High

Risk Transference

Make sure the caterer is aware of the expectations

Project Manager/ Student Name

Concerns mentioned to caterer – Successful.

02

Insecurity

Unlikely

Low

Medium

Risk Acceptance

Inform the police department and hire a guard

Project Manager/ Student Name

Security guard hired - Successful.

03

Over budgeting

Possible

High

Very High

Risk Mitigation

Continuously review the budget spreadsheet and ensure all purchases are within budget.

Project Manager/ Student name

Budget reviewed continuously and the purchases were within budget - Successful

04

High turn out

Highly Unlikely

High

High

Risk Mitigation

Use a ticketing system and use invite only attendance

Project Manager/ Student Name

System put in place - Successful.

05

Licensing

Unlikely

High

Very High

Risk Mitigation

Make application in advance and ensure all application requirements have been met.

Project Manager/ Student Name

License acquired - Successful.

06

Wrinkled Linen

Possible

Low

Low

Risk Transference

Make checks and inform the event coordinator of your expectations.

Project Manager/ Student Name

Concerns mentioned to the event coordinator - Successful

07

Poor Lighting

Possible

Low

Low

Risk Transference

Make checks before event starts and ensure event coordinator is aware of this expectation.

Project Manager/ Student Name

Concerns mentioned to event coordinator - Successful.

08

Poor Quality

Of entertainment

Unlikely

High

High

Risk Acceptance

Ensure that the choice of music is tranquil.

Project Manager/ Student Name

Concerns mentioned to event coordinator - Successful.

09

Limited Parking Slots

Possible

Low

Medium

Risk Acceptance

Check for additional parking if it will be needed.

Project Manager/ Student Name

Checked and even planned for additional parking space if it will be needed – Successful

10

Poor performance in advertisements

Highly Unlikely

High

High

Risk Acceptance

Do physical advertising which includes business meetings, issuing flyers and social media advertising.

Project Manager/ Student Name

Continuously advertised and followed up - Successful.

Revised to accommodate PMBOK® 4th edition

1

MBA6231 - 6.docx

Last Name, 5

Student Name

Institution

Course Code

Instructor Name

Table of Content

Executive Summary ………………………………………………………….……. 3

Project Charter…………………………………………………………….……….. 6

Project Scope Statement……………………………………………………………. 11

Cost Estimate…………………………………………………………………….…. 14

Risk Matrix………………………………………………………………………….. 17

Project Evaluation………………………………………………………………….. 19

Reference List……………………………………………………………………….. 21

Executive Summary

Project Background

This is a proposal for a social entertainment lounge to be hosted in Chicago, IL. The project will involve holding a series of events in Chicago with the aim of introducing into the market a new lounge in the city of Chicago IL. The series of events will be centered towards adding value to the attendees and not just the party organizers. Michael Joseph Place will focus on a mature and professional crowd living in Chicago together with those in the city for conferences among other events. This will be a place for them to not only relax and enjoy the evening but also a place for networking. The environment will be conservative and exquisite offering live music and a focus on mature clientele. All this has been done with the aim of creating and building not just a social experience but also a professional one. There is no such a place in Chicago, IL and therefore it is expected that the business will perform well.

Objectives

· Take advantage on an exquisite location

· Have a highly publicized event for the grand opening

· Ensure that the costs, cash flow and operations are well managed.

· Ensure that food costs are reduced by 33%

· The total average beverage costs to be below 25%

· The event will be used to showcase what Michael Joseph Place is offering

· Have a professional audience thereby enabling networking opportunities for them.

· Host a certain number of events with an attendance of approximately 125 patrons

· Create a lounge that allows dancing, conversation and dining as well while still maintaining its sophistication.

· .

Project Scope

The project involves creating an event that is marketable, upscale and attracts professionals in different fields. It’s expected that the project will have been completed by August of 2018. The event will involve fine dining, exquisite atmosphere, live music and social interactions. As the project manager I will endeavor to develop the vision, scope, and mission and ensure that everything is per plan and within budget as well. I will be designing the event décor, come up with a menu and hire a caterer as well. The venue will have to be selected and booked for the eventful evening. This will be done quarterly basis for the next one year. One of the most important duties for the project manager is attract investors and acquire the licenses. The investors have to be engaged and buy in the idea of the project.

· Constraints

The highest likely constraint at the moment is related to the venue. I am worried that the venue might not pull the expected crowd for this event due to its location. Getting an approval to hold a special event is likely to be another constraint. The hired caterer will be a freelancer and therefore there is a chance that he could be late or deliver food that is not up to standards. The guests are expected to come driving, and therefore parking is likely to be an issue. The hired staffs will be serving professionals and are therefore expected to meet high standards in customer service. The temperatures will need to be well controlled to offer the expected ambience. Advertisements should be done in an orderly, timely manner to ensure that they do not interrupt the event.

· Dependencies

Investors are key determinants of the success of this event which targets a private professional crowd. Marketing will also determine the level of attendance to this event and especially now that it will be at night. The event will be defined as a success if the attendance is encouraging and that the business professionals are cooperative. The staff have to arrive on time, food needs to be delicious while the ambience needs to be relaxing and well planned.

· Assumptions

The assumption of this project is that once there is a good offering to the target clients they will attend. The clients need to be aware that this location will be exquisite, upscale and tranquil. The assumption is that since there is no such location in Chicago, IL within 100 miles radius clients will come. Failure to attend by the target audience will mean that the event will not be successful. The marketing strategy is that we will aim to attract a certain audience thereby enabling a connection of various professional relationships.

Project Milestones and Deliverables

Project Start and Make Budget

Aug. 1, 2018

Meet with Investors

Aug. 5, 2018

Select Location

Nov. 15, 2018

Begin Advertisement

Dec. 27, 2018

Hire Decorator

Jan. 05, 2018

Hire Caterer

Feb. 10, 2018

Apply for Special Event license

April 01, 2018

Hire All Contractors

May 15, 2018

Book a Live Band

July. 20, 2018

Project Completion

Aug 2, 2018

These dates are an estimation of when it will take to complete one task to the other and the completion of the project management process. The milestone communicates the goals and expectations of the project manager, investor and other stakeholders. It also helps to ensure that each team is aware of the expectation in terms of both deadline and deliverables. It helps in making the plan clear and precise. There will be quarterly meetings to review the progress and also come up with any changes that may be needed.

The quarterly meeting will be held between all stakeholders who need to communicate their feedback so far and raise concerns. Changes in the process will be made and the potential risks discussed while making new plans for the future milestones. The project manager will also send monthly emails to communicate the achievement so far.

Project Charter

Project Title: Michael Joseph Place, The place to be

Project Start Date: 25/7/2018

Projected Finish Date: 25/12/2018

Budget Information: $ 4,500.00

Project Manager: Student name, [email protected], 210- 105 - 6676

Business Need

The project manager will be hosting an evening lounge event that will be targeting the clientele to an upscale lounge to be built in downtown. Through such an event the city will have a positive exposure.

There will be need for effective marketing, music, modern décor and most likely investors. The menu for food and drinks will need to be within budget. The venue needs to have amiable space and adequate seats for all guests.

The first step to this project involves coming up with a plan on a piece of paper. Once this is done the next step will involve selection of vendors to various goods and services. Once everything has been put to perspective the next stage will be to involve investors who will include local business owners. These investors will be encouraged to do so with the exchange for them to market and advertise their products at the event. We will have three packages for investors including Silver, Gold and Platinum packages.

Project Objectives

The proposal is to have a social entertainment evening lounge in Chicago. The project managers will be showcasing the new concept of entertainment by holding a series of events known as “The Place to be!”

· The events will be used to showcase the atmosphere that the new lounge will be offering

· The events will offer the professional audiences an opportunity to network while at the same time being entertained.

· The events will be targeting an audience of 150 attendants

· To have an environment where attendants can dance, dine and drink socially while discussing business.

Approach

This project will be managed in accordance with the PMI approach as modified.

Assumptions/Constraints/Dependencies

The assumption is that with the provision of an exquisite and upscale venue that is mature in Chicago, IL, will be successful due to the fact that there is no such a venue within a 100 mile radius.

One of the likely constraint is finding a venue that grabs attention of the targeted crowd.

The success of these events depends on attracting two sets of individuals. One of them is investors and the other is private professionals who will attend a social event at night.

Initial Risk Factors

· Obtaining a liquor license on time for the event is the major risk factor.

· Failure of attendees despite investing money and time is another risk.

· Failing to complete the organizational plans within 30 days before the event series begin.

· Not attracting any viable investors

Regulatory cost/impact

One of the needed licensing is from the city council where I will be required to get a special event license. This will enable us to have alcohol in the premises. There will be need for security and fire reviews from the respective departments of city council. The parking code and regulations for the venue will also have to be looked into seriously.

Roles and Responsibilities

Role
Name
Organization and Position
Contact Information

Project sponsor

Michael Joseph

Chief Executive Office

[email protected]

210-321-4560

Project manager

Student Name

Michael Joseph Place

Operations Manager

[email protected]

210- 105 - 6676

<title>

<title>

<title>

Sign-Off

Michael Joseph

Student Name

Comments

No comments at this time

Project Scope Statement

This project will consist of creating a marketable, upscale, and social events custom designed based on the professional clientele. The project will be completed by August, 2018. The evening will consist of fine dining, live music and innovative and exquisites atmosphere.

Project Name:

1st Quarterly evening hosted by Michael Joseph

Prepared By: Student Name

Date

07/25/2018

Version History (insert rows as needed):

Version
Date
Comments

1.0

1. Executive Summary

Michael Joseph Place will be the new and most tranquil spot in the city for entertainment. The lounge offers a sophisticated environment that enables patrons to be centered on the people rather than the party. Michael Joseph Place is offering a mature, serene environment for all professionals based in Chicago, IL where they can enjoy the company of their peers. Clients will be treated to an exquisite and conservative environment as they dine and enjoy live music enabling them to focus on what matters to them most, their profession and clients. The lounge is focused towards ensuring you have an unforgettable social experience.

Note: In any instance where there is a discrepancy between the Project Charter and the Project Scope Statement, the latter is considered authoritative.

2. Business Objectives

2.1 Product Description (Solution)

The setting being proposed at Michael Joseph Place has not been witnessed in Chicago so far. An exquisite environment, Live Music coupled up with upscale dining all served under the same roof will be unique in Chicago.

2.2 Business Objectives

To capitalize on having an excellent location

To launch the new venue by having a grand opening event

Ensure tight and efficient control of operations, costs and cash by using modern technology

Ensure food provides at least 33% profit margin

Ensure that beverage revenue has 25% margin

3. Project Description

For each area below, provide sufficient detail to define this project adequately.

3.1 Project Scope: Plan for Michael Joseph Place grand opening

Includes (list deliverables):

Book artists to offer live performances

Plan catering for grand opening

Come up with a budget plan for the grand opening

Decide on a strategic day for grand opening

Develop a comprehensive marketing Campaign

Does not include:

A Website or any software

3.2 Dependencies (External and Internal)

Investors engagements

3.3 Assumptions

The date to be set to a day that there is a homecoming football game.

The project scope will not be affected.

3.4 Constraints

Employing freelancers rather than hiring full-time staff

4. Project Milestones

Target Date

Project Start

Aug. 1, 2018

Meeting with investors

Aug. 6, 2018

Hire Freelancers and Contractors

Aug. 18, 2018

Book a Live Band and other artists

Aug. 25, 2018

Project Complete

Dec 2, 2018

5. Project Approach

Briefly describe how each of the following will be handled. Provide links to relevant documents as appropriate.

5.1 Change Management

This is a sequence of events or even activities that a project manager and in some cases a change management team would use to manage the expected change after a project. This process is done in three phases which include preparation, management of the change and finally reinforcing the change.

5.2 Communication Management

Communications management is aimed at ensuring that the collection, distribution, storage and generation of information towards the project is timely and appropriate. It involves interviewing potential investors, clients and even contractors.

5.3 Quality Management

The project manager will put in place a quality management strategy that will ensure that the event and the process are both of top quality. For this project to be successful it has to meet the set quality objectives through the use of integrated quality approach that defines quality standards while measuring and continuously improving quality.

5.4 Resource Management

This is a comprehensive planning process which takes into account the available resources which includes humans to ensure that there is achievement of long term sustainable benefits. This process brings together every resource group which would otherwise work separately. Resource management involves creation of a planning team, creating an overview of the entire project, issues identification, recognizing all available resources, coming up with objectives and strategies. The process also involves implementing and monitoring the entire project.

5.5 Critical Success Factors

Customer Contentment, dining quality, number of people expected to attend the grand opening

5.6 Risk Management

The premises where the event will be held were built in the year 2000. Surveying has been done to ascertain whether the building has asbestos. The report confirmed that there was no asbestos-containing materials used.

5.7 Project Organization

Project organization is a formal structure that helps in the coordination together with the implementation of project activities. It involves investors, contractors and project managers.

6. Authorizations

The Project Scope Statement is approved by the:

Project Sponsor

Michael Joseph

Project Manager

Student Name

Project performance baseline changes will be approved by the:

Project Sponsor

Michael Joseph

Project Manager

Student Name

Project deliverables will be approved and accepted by the:

Project Sponsor

Michael Joseph

Key Stakeholders

Student Name

7. Project Scope Statement Approval

Project Name

1st Quarterly evening hosted by Michael Joseph

Project Manager

Student Name

The purpose of this document is to provide a vehicle for documenting the initial planning efforts for the project. It is used to reach a satisfactory level of mutual agreement between the Project Manager and the Project Sponsors and Owners with respect to the objectives and scope of the project before significant resources are committed and expenses incurred.

I have reviewed the information contained in this Project Scope Statement and agree:

Name
Role
Signature
Date

The signatures above indicate an understanding of the purpose and content of this document by those signing it. By signing this document, they agree to this as the formal Project Scope Statement document.

Cost Estimate

Total Estimated Costs

Category

Estimated Cost

Food and Beverage

$ 1,700.00

Rentals and Entertainment

$ 2,100.00

Location

$ 500.00

Misc. Costs

$ 200.00

Total

$ 4,500.00

Supporting Documentation

Constraints

The highest likely constraint at the moment is related to the venue. I am worried that the venue might not pull the expected crowd for this event due to its location. Getting an approval to hold a special event is likely to be another constraint. The hired caterer will be a freelancer and therefore there is a chance that he could be late or deliver food that is not up to standards. The guests are expected to come driving, and therefore parking is likely to be an issue. The hired staffs will be serving professionals and are therefore expected to meet high standards in customer service. The temperatures will need to be well controlled to offer the expected ambience. Advertisements should be done in an orderly, timely manner to ensure that they do not interrupt the event.

Dependencies

Investors are key determinants of the success of this event which targets a private professional crowd. Marketing will also determine the level of attendance to this event and especially now that it will be at night. The event will be defined as a success if the attendance is encouraging and that the business professionals are cooperative. The staff have to arrive on time, food needs to be delicious while the ambience needs to be relaxing and well planned.

Assumptions

The assumption of this project is that once there is a good offering to the target clients they will attend. The clients need to be aware that this location will be exquisite, upscale and tranquil. The assumption is that since there is no such location in Chicago, IL within 100 miles radius clients will come. Failure to attend by the target audience will mean that the event will not be successful. The marketing strategy is that we will aim to attract a certain audience thereby enabling a connection of various professional relationships.

Risk Matrix

Project Name: “1st Quarterly evening hosted by Michael Joseph”

Risk

#

Risk

Probability

Importance

Impact

Response to Risk

Action Plan

Person Responsible

Status

01

Catering Issues

Highly

Possible

High

High

Risk Transference

Make sure the caterer is aware of the expectations

Project Manager/ Student Name

Concerns mentioned to caterer – Successful.

02

Insecurity

Unlikely

Low

Medium

Risk Acceptance

Inform the police department and hire a guard

Project Manager/ Student Name

Security guard hired - Successful.

03

Over budgeting

Possible

High

Very High

Risk Mitigation

Continuously review the budget spreadsheet and ensure all purchases are within budget.

Project Manager/ Student name

Budget reviewed continuously and the purchases were within budget - Successful

04

High turn out

Highly Unlikely

High

High

Risk Mitigation

Use a ticketing system and use invite only attendance

Project Manager/ Student Name

System put in place - Successful.

05

Licensing

Unlikely

High

Very High

Risk Mitigation

Make application in advance and ensure all application requirements have been met.

Project Manager/ Student Name

License acquired - Successful.

06

Wrinkled Linen

Possible

Low

Low

Risk Transference

Make checks and inform the event coordinator of your expectations.

Project Manager/ Student Name

Concerns mentioned to the event coordinator - Successful

07

Poor Lighting

Possible

Low

Low

Risk Transference

Make checks before event starts and ensure event coordinator is aware of this expectation.

Project Manager/ Student Name

Concerns mentioned to event coordinator - Successful.

08

Poor Quality

Of entertainment

Unlikely

High

High

Risk Acceptance

Ensure that the choice of music is tranquil.

Project Manager/ Student Name

Concerns mentioned to event coordinator - Successful.

09

Limited Parking Slots

Possible

Low

Medium

Risk Acceptance

Check for additional parking if it will be needed.

Project Manager/ Student Name

Checked and even planned for additional parking space if it will be needed – Successful

10

Poor performance in advertisements

Highly Unlikely

High

High

Risk Acceptance

Do physical advertising which includes business meetings, issuing flyers and social media advertising.

Project Manager/ Student Name

Continuously advertised and followed up - Successful.

Project Lessons

The project manager is an individual who has the responsibility of seeing a project from the start to completion. Their duties include planning, management of persons, resources and ensuring that the scope of the project is achieved. The individual creates objectives that they see them through to completion without any hitches. As per the project management plan and acting as the project manager I would say that the project was 95% successful. The time and budget were on point though there were some minimal errors. The project involved a small team of individuals and therefore it was easy to communicate effectively. Constant and effective communication is crucial for the completion of any project.

During the operation of the project the scope had to be modified so as to accommodate new changes and ideas. These changes were minimal and did not affect the budget nor the timeline. The ideas touched on issues such as advertisement and the event décor. All the set objectives were achieved and on time. There was an issue with the caterer and the project manager had not made provisions for a back-up. This is the reason there was a 5% area of improvement for this project. The caterer arrived late and the food was already cold. Clients did not complain as they were not aware how we had planned with the caterer. This incidence however brought stress to the schedule and therefore the overall performance of the project manager.

Achieving the set objectives was not a toll order as they were easy to understand and achievable. The plan was laid out and reviewed from time to time to ensure that there were no discrepancies. One of the key issues was ensuring that the budget was maintained. There was a to-do-list which was checked and ticked anytime that a task had been completed. The set dates were used as mile markers and in the computation of the budget in the project management process. The dating process was also used to communicate the goals and expectations to investors so as to align our strategy with theirs. All the parties were aware of the steps to be taken to ensure the completion of the project. Quarterly meetings were held to ensure that a review is done so as to make sure that everything is going as per the plan. Through this meetings there would be communication between the different units and also ensure correction or modification of the budget and schedule when there was a need. If tasked with a similar project, I would do more research especially on pricing to ensure that everything goes as per the plan.

In my future projects I will use this initial project format as a foundation for which I will then build on. I am now more familiar with the venues, caterers, event coordinators and suppliers in my area as well as the available live bands. I now have the knowledge on how to vet vendors and ensure that I get the best for my event. Having a standby caterer is crucial as well as having your own security rather than depending on the police or fire departments. The budget was well set and maintained therefore the overall success of the event.

I would advise other project managers to ensure they do a thorough research during the planning phase of a project. This will reduce stress when it comes to the implementation bit of the project. They should also ensure they have the smallest team possible. This will ensure accountability and ease of communication between the teams. Research on similar projects is also crucial in ensuring that you don’t make the same mistakes as done by other project managers before you. With this I am sure you will be able to have a successful project with minimal waste of resources as possible.

References

Larson, E. W., & Gray, C. F. (2015). A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute.