Final Project Report
Running Head: PROJECT SCOPE 1
PROJECT SCOPE 2
Project Scope
Argosy University
Sean Markl
Project Management
February 5, 2019
PROJECT SCOPE
Project Objective
To construct a high-quality, District 4 Production Warehouse Move within seven months at a value that doesn't exceed $1million.
Deliverables
· A 5,000-square-foot open single roomed warehouse with one 500-square-foot office room.
· Definition of the format of operation of the material store (OMS)
· A completed garage insulated and sheet-rocked.
· Accepted and feasible technical architecture for Operation of Material Store (OMS)
· Delivery of the software programs that will help in the material keeping process.
· Test and acceptance of material warehouse.
· Design a training and usage warehouse plan (Collins, Parrish, & Gibson 2017).
Milestones
· Permits officiated—First 5 days
· Base poured— First 20 days of the first month
· Dry in. Framing, casing, plumber work, electrical work, and mechanic scrutiny work passed-First four months of the project duration
· Workbenches finished- the beginning of the 5th month
· Equipment packing-towards the end of the 5th month
· Final inspection— towards the end of the 6th month
· Warehouse opening at the middle of the 7th month (Fuller, Valacich, George, & Schneider, 2017).
Technical Requirements
· The warehouse has to adhere to the local construction codes.
· The warehouse outer wall padding has to concede with an “A” factor of 21.
· The warehouse floor padding must have to coincide with an “R” factor of 25.
· The warehouse garage will have to put up to five large-size official cars and four 20-foot track.
· The whole warehouse formation must surpass seismic strength codes (Harrison, & Lock, 2017).
Limits and Exclusions
· The warehouse will be constructed as per the provisions and plan of the original plan given by the client.
· The warehouse client is accountable for landscaping if any.
· Warehouse Air conditioning is exclusive however the pre-wiring is inclusive.
· The warehouse outworker has the right to call out services.
· The warehouse service provider is accountable for sub-contracted work.
· The warehouse area of work is limited to Monday through Friday, 0730hrs to 1730hrs (Kerzner, & Kerzner, 2017).
Customer Review
· Vincent Omar and John King
References
Collins, W., Parrish, K., & Gibson Jr, G. E. (2017). Development of a project scope definition and assessment tool for small industrial construction projects. Journal of Management in Engineering, 33(4), 04017015.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Too, E., Le, T., & Yap, W. (2017). Front-end planning-The role of project governance and its impact on scope change management. International Journal of Technology, 8(6), 1124-1133.