Risk Management

profileVignesh Sivadass
MANG646143Week5v31.ppt

MANG 6463
Project Risk Management




Mario Brito

Reading for this week

  • Chapman(2019), Chapter 7, page 338-343

*

Transcon 1
case study discussion

Discussion starting point

Start with the working assumption that the objective is

maximizing the expected value of

M = B – C,

where M = margin (contribution to profit),

B = bid (price),

C = cost (direct),

and assume we want to understand the expected values

of M, P and C plus associated risk.

Start with C for two components which are useful examples.

Your task this week is to:

  • Read Transcon 1 case study in Chapter 6 of the core textbook. Select one of the problems to discuss in the forum:

Item 3, initial operation and training, (Chapman, 2019), page 242. Which one is the best bid based on the expected margin? Zoro or Astro?

Item 4, convert existing programmes, (Chapman, 2019), page 245. Which one is the best bid based on the expected margin? Sysdoc or Datapol?

Discuss what factors have influenced your decision?

*

The create and enhance plans phase

  • This phase is not part of the PUMP process, or ‘project risk management’ as this concept is usually perceived – it is ‘project management’.
  • This phase is relatively straightforward basic project planning provided the roles of the base plans developed in this phase are seen within the basic SPP framework, with everyone involved understanding which lifecycle stage is involved and the full role of all seven Ws.
  • An understanding of related underlying modelling issues at a conceptual level is needed, including all of those aspects which might or might not be modelled operationally in the next phase, and the way the SPP generally works over all lifecycle stages as the project progresses through successive lifecycle stages, from the beginning of the concept strategy progress stage until the end of the termination stage.
  • An important basic concern is the level of detail required and the way the depth of decomposition required may need to be developed on successive passes through the process in this particular progress stage.
  • A useful place to start to understand what is involved is an overview of some of the key issues addressed in the next phase.

Design and lay a pipeline and deliver

*

Code Activity name Activity duration (days) Precedent
A Requirements 80 None
B Design 35 A
C Recruitment 40 A
D Development of the safety case 20 B
E Purchase 20 B
F Test – onshore 40 E
G Transport 10 F and C
H Test connection and deliver 10 G

Activity

  • Using the activity table design the corresponding activity-on-node network

*

A is preceded by nothing

B is preceded by A

C is preceded by B

A is preceded by nothing

B is preceded by nothing

All A and B must be completed before C can begin

B and C are preceded by A

A

B

C

A

B

C

A

B

C

Activity-on-Node network

*

ES - early start

EF – early finish

SL – slack or float

LS – late start

LF – late finish

DUR - duration

A
Requirements
B
Design
C
Recruitment
D
Safety case
E
Purchase
F
Test-onshore
G
Transport/ Assembly
H
Test/deliver
ES ID EF
SL Test-onshore
LS DUR LF

*

Activity-on-Node network – Forward propagation

0 A 80
Requirements
80
80 B 115
Design
35
80 C 120
Recruitment
40
115 D 135
Safety case
20
115 E 135
Purchase
20
135 F 175
Test-onshore
40
175 G 185
Transport/ Assembly
10
185 H 195
Test/deliver
10

*

Activity-on-Node network – Backward propagation

TS = 0 FS = 0

TS = 0 FS = 0

TS = 0 FS = 0

TS = 50 FS = 50

TS = 0 FS = 0

TS = 0 FS = 0

TS = 55 FS = 55

TS = 0 FS = 0

0 A 80
Requirements
0 80 80
80 B 115
Design
80 35 115
80 C 120
Recruitment
135 40 175
115 D 135
Safety case
165 20 185
115 E 135
Purchase
115 20 135
135 F 175
Test-onshore
135 40 175
175 G 185
Transport/ Assembly
175 10 185
185 H 195
Test/deliver
185 10 195

The shape base plans using models of some key issues phase

  • Using a general precedence diagram framework with useful special cases like the linked bar chart portrayal of activities at a very simple level to portray activity precedence relationships (not an activity-on-arrow Critical Path Method (CPM) or Programme Evaluation and Review Technique (PERT) diagrams) is one useful example.
  • Using a generalisation of simple indirect plus direct cost minimisation to seek an optimal project duration is another useful example.
  • Consider the SPP process linked bar chart used earlier first, then some other examples.

Revisiting the bar chart for the SPP considered earlier

The useful generality of this linked bar chart format and the underlying precedence diagram concept.

intense effort

on-going effort

no effort or intermittent effort

key:

ownership

quantify

evaluate

structure

phase

create & enhance

select & focus

start of the

process

end of the first

complete cycle

capture

identify

shape base plans

A simple indirect plus direct cost relationship graph

Generalising the ideas underlying ‘deterministic’ models of this kind to cope with very important ‘planning uncertainty’.

project

cost

in £

joint cost

minimum

cost

project duration in months

crash duration optimum duration normal duration

0

indirect cost

direct cost (efficient frontier)

0

Using the BP examples to outline what the concept strategy progress stage should have achieved, followed by what the DOT strategy progress stage should have achieved, prior to starting the E&D strategy progress stage, and looking back with hindsight now.

Using the WSL example discussion to outline what creating and then shaping base plans using models of some key issues ought to involve and achieve.