People and Organization (P&O)
Project Success/Failure
‘On time, On Budget, On Specification:
Would these be ENOUGH?!’
MANG6311©RV2021-22 1
Southampton
Business School
MANG6311 PM – People & Organizations
Week 10
Dr Ramesh Vahidi 7th Dec 2021
Sydney Opera House
A Disaster or
A Masterpiece?
2MANG6311©RV2021-22
SOH - Project Overview
• 1957: Jørn Utzon won the bid
• 1959: Work commenced on Sydney
Opera House
• 1966: Utzon resigned
• Original estimate of the project
duration: 4 years
• Original cost estimate: $7 million
• He was awarded £5000!
• 1973: Opening of the Opera
House
• SOH opened without him
• Project’s real duration:
14 years
• Final cost: $102 million
Goal
3MANG6311©RV2021-22
Changing the World’s perception of Australians from ‘sport-mad’ to ‘vigorous cultural and intellectual’ people
4
https://vevox.app/#/m/111-694-793
Success 111-694-793
MANG6311©RV2021-22
Project Success/Failure
Question
•1. You are an Australian in 1950-60s: Is
Sydney Opera House a success or a failure?
SOH - A Controversial Construct
• Wonderful exterior
• Innovative design
• Brilliant interior
• A major tourist attraction
• Unworkable physical
properties
• Not even suited for opera!
5MANG6311©RV2021-22
6MANG6311©RV2021-22
Project Success/Failure
Question
•2. You are an Australian in 2000s: Is Sydney
Opera House a success or a failure?
https://vevox.app/#/m/111-694-793
Success/Failure 111-694-793
MANG6311©RV2021-22 7
Projects succeed and fail in any field, industry, discipline, country, environment, … (So do the Non-projects)
Is there any difference between success/failure in Operational vs. Project environments?
“Project management differs from the conventional line
management [RV: refers to operations or non-project
works] in many ways but particularly, in one most vital
respect: A project has but one chance of success,
whereas with conventional line management [RV: same as
previous notes] there is always the opportunity to “do
things better next time.” (Kharbanda and Stallworthy,
1984) Failure to recognize this vital difference has been
one of the main factors in project failure.”
(Kharbanda and Pinto, 1996, p.21)
MANG6311©RV2021-22 8
Aims
“Providing you with various traditional and contemporary dimensions
of and perspectives on project success and failure.
Learning the shortcomings and imitations of the traditional models.
Introducing a structured framework for comprehensive analysis and
management of project success and failure.”
MANG6311©RV2021-22 9
We will talk about
✓ Evolution of project success studies.
✓ Impact of time in assessing project success/failure.
✓ Structured and multi-perspective analysis of success/failure.
✓ Steps of failure management.
✓ Value of Lessons learned in project success/failure.
MANG6311©RV2021-22 10
MANG6311©RV2021-22 11
“Evolution of
Success/Failure
Studies in PM
literature … ”
Southampton
Business School
Most Traditional Perspective on Project Success
Since 1950s!
Time
Cost Quality or Performance
MANG6311©RV2021-22 12
“The basic view of how project success is
measured is that the project is finished
on time, within budget & to quality. It is
sad how people thoughtlessly trot this
out as the measure of project success.”
Turner et al. (2010, p.81)
Reminder (Week 1)
Traditional Approaches: Examples of Triangle Extensions
The Square Route (Atkinson, 1999)
Triple Constraints (Hamilton, 2001)
Tetrahedron (Davis, cited in Wideman, 2004)
The Tetrad Trade-off (Wideman, 2004),
The Project Pyramid (Marasco, 2004)
MANG6311©RV2021-22 13
Lock’s amalgamated version (Lock, 2013)
(Vahidi & Greenwood, 2009)
Success/Failure in PM Literature
Large number of projects widely studied in the last three-four decades.
Major improvements in PM theories and practices.
More and more attention to soft and external aspects/dimensions.
Multiple views on what constitutes project success or failure. (Gives you a very brief overview: Pinto et al., 2021 )
Some major organizations publish regular reports on (their) projects failure/success (e.g., UK Gov.’s report on Major Projects and Standish Group on Software projects → See the ref list)
For a comprehensive list of previous key studies and their specifications refer to: Morris (2013, p.287).
MANG6311©RV2021-22
Later Approaches: Project Success – Concepts for Analysis
MANG6311©RV2021-22 15
*Also referred to as: “Critical Success Factors (CSFs)”
Helps in: Identifying and selecting
appropriate PM methods, tools,
resources, …
Assess whether: The selected PM methods, tools,
resources, … were appropriately selected &
implemented or not.
Later Approaches: Examples of Critical Success Factors (CSFs)/Elements Lists (also more focus on industry CSFs)
Belassi and Tukel (1996, p.145) MANG6311©RV2021-22 16
Question/Criticism:
Could these models cover all the elements of
project success?
…
This is the major difference between the traditional
approaches and more contemporary ones.
MANG6311©RV2021-22 17
Later Approaches (Major Finding): Differences in Perspectives on Success/Failure
MANG6311©RV2021-22 18
Stakeholders have different:
• Expectations of the project outcome;
• Perceptions of success;
Hence, have different:
• Criteria for measuring/assessing
success;
• Factors to affect their success;
Project Success/Failure
Questions:
• You are an Australian in 1950-60s: Is Sydney Opera House a success or a failure?
• Would you hold the same view if you were:
– Utzon;
– Australian or Local Gov.;
– Engineers;
– Australian Society in 1960s;
– …
MANG6311©RV2021-22 19
MANG6311©RV2021-22 20
Question:
Could a list of success factors/criteria be all inclusive for all
projects and all stakeholders?
Read the chapter on “Contingency School of
Thought” from Turner et al. (2010)
Comprehensive Approach – (basis for Contemporary): Shenhar and Dvir’s (2007, p.29) Main Dimensions (Measures) of Success
Project Success
Efficiency Impact on customer
Impact on team
Business and direct success
Preparation for future
MUST READ: Shenhar and Dvir (2007, p.27) 21
MANG6311©RV2021-22
Meeting Schedule Meeting Budget Yield Other efficiencies
Meeting Requirements & specifications
Benefits to customer
Extent of use Customer
satisfaction and loyalty
Brand name recognition
Team satisfaction Team moral Skill development Team member
growth Team member
retention No burnout
Sales Profit Market share ROI Cash flow Service quality Cycle time Organizational
measures Regulatory
approval
New technology New market New product line New core
competency New
organizational capability
MANG6311©RV2021-22 22
Changing Perception of Success: Impact of Time
Project Success
Efficiency Impact on customer
Impact on team
Business and direct success
Preparation for future
MUST READ: Shenhar and Dvir (2007, p.30) 23
MANG6311©RV2021-22
Short Medium Long
Timeframe for Assessing Success DimensionsProject Completion
Strategic PM
Project Success/Failure
Questions:
In 2000s, who feels the project has been a success:
– Utzon;
– Australian Gov. or Local Gov.;
– Engineers;
– Australian Society;
– …
MANG6311©RV2021-22 24
Project Success
Efficiency Impact on customer
Impact on team
Business and direct success
Preparation for future
25 MANG6311©RV2021-22
Assessing Success Dimensions: Sydney Opera House
D I
M E N S I O N
S/ M/ L
26MANG6311©RV2021-22
Project Success/Failure
Question
•3. Sydney Opera House: Which dimensions
did the project fail in?
https://vevox.app/#/m/111-694-793 Success/Failure
111-694-793
27MANG6311©RV2021-22
Project Success/Failure
Question
•4. Is a project like SOH a success or failure?
https://vevox.app/#/m/111-694-793 Success/Failure
111-694-793
28MANG6311©RV2021-22
Project Success/Failure
Question
•
5. As a PM professional-to-
be, which one of the views
you would take to manage
and analyse the
success/failure of your
projects?
1
2
3
4
https://vevox.app/#/m/111-694-793 Success/Failure 111-694-793
29MANG6311©RV2021-22
Project Success/Failure
Question
•
If your answered 1-3: you will
need to spend a good time on
in-depth reading of the sources
on the reference list. Also
review the Lecture/readings
from Week 1 very carefully.
1
2
3
4
https://vevox.app/#/m/111-694-793 Success/Failure
111-694-793
MANG6311©RV2021-22 30
“Success/Failure
Studies in PM
literature … ”
Southampton
Business School
Valid Reports on Projects’ Contribution to Economy:
MANG6311©RV2021-22 31
Examples of UK:
- Project management industry adds £156 billion of value to UK economy (15 April 2019 Consultancy.uk) https://www.consultancy.uk/news/20997/project-management-industry-adds-156-billion-of- value-to-uk-economy
- National Infrastructure Delivery Plan 2016–2021
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/ file/520086/2904569_nidp_deliveryplan.pdf
- Government reports on Major Projects at the end of 2013: Delivery of 95% of the government’s policies through 191 major projects, worth £354 billion:
– Some historical reasons for major projects failure in meeting their set expectations: • Poor (internal) project management;
• External factors;
• Over-optimism in estimations;
– Some of the main reasons for failure in estimation were weaknesses in: governance; stakeholder management; initial approval; quality; skills and resources management, etc.
Read and look for more in your study time
Example of Reports: Success/failure in IT Projects
MANG6311©RV2021-22 32
Factors in increasing success:
“… looking at the entire project environment of processes,
methods, skills, costs, tools, decisions, optimization, internal
and external influences, and team chemistry.”
(The CHAOS Manifesto, 2013, p.1) Interesting reports are published by Standish Group but not all in public domain anymore. Read specifically if you are analysing a software project. (Thinks: Is their perspective traditional or contemporary?
Read and search for examples in your study time
MANG6311©RV2021-22 33
Professor Peter Morris - UCL
In 1980 Prof. Peter Morris found out project
overruns were mainly associated with “contextual
things like stakeholders, geographical conditions,
weather and other exogenous factors, as well as
poor technology management, commercial issues
and people (Appendix 1)”. (Morris, 2013)
MUST Read:
Appendix 1 from the following textbook: http://site.ebrary.com/lib/soton/reader.action?ppg=313&docID=10674845&tm=141 7723442478
Example of Literature: Projects Failure Rates
MANG6311©RV2021-22 34
“Failure Happens! … ”
Southampton
Business School
Case Study
MANG6311©RV2021-22 35
Walkie-Talkie Skyscraper
Located in London
£200m building
Curved 37-story
Was due to open early 2014
Became a tourist attraction in
Sept 2013!
https://www.youtube.com/watch?v=TGnZz8-PvdY
MANG6311©RV2021-22 36
Walkie-Talkie Skyscraper
Concave shape: curved mirror & downdraught
Beams of light up to 117 °C: Melted metal, plastic parts, cooked eggs, …
Strong wind tunnel: Blown away people, shopping trollies, …
Winner of London’s worst building of the year 2015
http://www.bloomberg.com/news/2013-09-05/london-s-walkie-talkie-fryscraper-draws-crowds-in-heat.html
MANG6311©RV2021-22 37
http://www.dezeen.com/2015/07/23/walkie-talkie-skyscraper-rafael-vinoly-blamed-powerful- downdraught-london/ http://www.theguardian.com/artanddesign/architecture-design-blog/2015/sep/02/walkie-talkie- london-wins-carbuncle-cup-worst-building-of-year
Skyscraper or Fryscraper
A project representative: “very strange phenomenon and certainly not something we were expecting to happen”.
Guardian (cited in Bloomberg Business): “A hotel and spa In Vegas designed by the same designer produces a similar effect because of its curved shape!!”
http://www.bloomberg.com/news/2013-09-05/london-s-walkie-talkie-fryscraper-draws-crowds-in-heat.html
MANG6311©RV2021 -22
38
Lessons Learned: Do we learn?
MANG6311©RV2021-22 39
Lessons Learned: How far we learn? What
we learn?
http://www.dezeen.com/2015/07/23/walkie- talkie-skyscraper-rafael-vinoly-blamed- powerful-downdraught-london/
“Following the string of complaints about
the Walkie Talkie and other skyscrapers,
The City of London Corporation is now
demanding independent assessment of
the wind reports submitted at the
planning stage, at property developers'
expense.”
MANG6311©RV2021-22 40
Read more interesting stories:
1) How some of the stakeholders’ perceive
the building as a success.
http://www.dezeen.com/2015/07/23/walkie-talkie- skyscraper-rafael-vinoly-blamed-powerful- downdraught-london/
Skyscraper or Fryscraper
2) How the Building is becoming a tourist attraction:
http://www.cityam.com/206340/walkie-talkie-sky-garden-how-book-visit-stunning- park-views-across-london
MANG6311©RV2021-22 41
The end of the world?!
…
Which stakeholder(s) to
blame?
Fire or
shoot the
project
manager in
the head?!
Potentially the
first reactions
would be …
MANG6311©RV2021-22 42
Success/Failure Responsibility
• Who’s ultimately responsible for Success and/or Failure?
• How do we know?
Potential sources: “Governance/RACI Matrix/Stakeholder Analysis/Contract”
Success/Failure: Project Manager’s Responsibility?
MANG6311©RV2021-22 43
– Extent of PMs responsibilities?
Proportionate to the level of given/received authority/support at the start and throughout the project lifecycle.
– Required competencies:
Examples: Technical, social and contextual competencies besides leadership.
– Project’s characteristics:
Organizational impact, size, disciplines involved, sensitivity, governance structure, etc.
Management of Failure
The stages of the management of failure:
– Identify that something has gone wrong;
– Appreciation and acceptance of the
problem;
– Prevent further damage or escalate the
problem;
– Take recovery actions to regain the
customer’s confidence;
– Prevent repetition by change practices.
(Maylor, 2010, p.211)
MANG6311©RV2021-22 44
Management of failure: Any suggestions?
MANG6311©RV2021-22 45
• Identify that something has gone
wrong;
• Appreciation and acceptance of the
problem;
• Prevent further damage or escalate
the problem;
• Take recovery actions to regain the
customer’s confidence;
• Prevent repetition by change
practices.
Lessons Learned
‘We don’t carry out “lessons learned reviews” at the end of projects now. We carry out “lessons identified reviews”. We know we don’t learn.’ (Programme Manager, major UK government agency)
(Maylor, 2010, p.360)
Lessons Learned:
✓ Audits/ Reviews
✓ Formal or Informal Procedures
✓ Documentation
MANG6311©RV2021-22 46
MANG6311©RV2021-22 47
• US Navy initiated an Enterprise Resource Planning System (RRP) system in 1997 with the cost of 1 billion dollars.
• This was never implemented.
• According to the congress it was a waste of money.
• They claimed: the acquired knowledge had been used to the benefit of the other projects.
Lessons Learned: Value (a different perspective)
Now You Tell Me …
• What were the most important things you learned from this lecture?
• How will you use these as a project manager?
• How will you use these in analysing a case study?
MANG6311©RV2021-22 48
Tips for Coursework Project Selection
Essential
• Controversial throughout or at least at some phases of the project
• Failed completely or in some parts
• Could not deliver what it was supposed to deliver
• Stakeholders have very contrasting views on it success or failure (e.g., environmental damaging projects)
MANG6311©RV2021-22 49
• How failure was managed in SOH?
• What lessons did you learn from SOH case?
MANG6311©RV2021-22 50
Home Exercise
References
MANG6311©RV2021-22 51
Project Success:
Morris, P. W.G. (2013) Reconstructing Project Management. Somerset, NJ, USA:
John Wiley & Sons. [Online: ProQuest ebrary]. Appendix 1.
Shenhar, A.J., Levy, O. & Dvir, D. (1997) ‘Mapping the dimensions of project
success’. The Professional Journal of Project Management Institute, 28(2), pp.5-13.
http://www.reinventingprojectmanagement.com/material/other/7.%20Mapping%20di
mensions%20of%20projects%20success%20PMJ%201997.pdf
(→ Important: this source does not the team dimension as it was added in their 2007 book in
below. The is still a very good source for you to read. Anyway, you should add the team
satisfaction as well, as suggested on the slides and the below book.)
Shenhar, A.J. & Dvir, D. (2007) Reinventing project management – The diamond
approach to successful growth and innovation. Boston: Harvard Business School
Press.
https://rl.talis.com/3/soton/lists/73804936-02A6-7CD1-40F6-
B501CB61A481.html?draft=1&lang=en-GB&login=1
References
MANG6311©RV2021-22 52
Vahidi, R. & Greenwood, D.J. (2009) ‘Triangles, Tradeoffs and Success: A Critical
Examination of Some Traditional Project Management Paradigms’. in Barrett, P;
Amaratunga, D; Haigh, R; Keraminiyage, K & Pathirage, C (eds) Procs. CIB Joint
International Symposium 2009. Dubrovnik, Sep, 27-30, 2009. (accessible online) online)
Pinto, J., Davis, K., Ika, L., Jugdev, K. and Zwikael, O. (2021) ‘Call for Papers for Special Issue on Project Success’. International Journal of Project Management. 39, pp. 213– 215. (Note: this is to give you a brief overview of: 1) how important the topic is, 2) it is still under investigation, and 3) how insufficient the traditional views based on Triangle are. Its list of refs could be a good source for finding and reading more papers in your study time.)
References
MANG6311©RV2021-22 53
Example Reports on or related to Project Success:
Chaos Manifesto 2013 - Think Big, Act Small. By: The Standish Group (2013)
http://www.versionone.com/assets/img/files/CHAOSManifesto2013.pdf
The Major Projects Report 2013. By: The Comptroller and Auditor General (2013). Published by:
National Audit Office (2013). Access: http://www.nao.org.uk/wp-content/uploads/2015/02/The-
Major-Projects-Report-2013.pdf
Chaos Manifesto 2015 -
https://www.standishgroup.com/sample_research_files/CHAOSReport2015-Final.pdf
Annual Report on Major Projects 2019-20 - Gov.uk
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/fil
e/899401/IPA_AR_MajorProjects2019-20.pdf
54 MANG6311©RV2021-22