Finance Assignment Due
When working on Major Project 1 please choose an approach you are most comfortable with.
Excel template (in a separate file) is intended to help you. If it confuses you instead, please disregard it completely or modify it the way you see necessary.
The following checklist is intended to help you verify that your work covers all major calculations and points necessary for successful completion of the project
Project 1 submission checklist
Basic Analysis |
|
|
Future Electricity prices downloaded and converted into $/kWh after adjustment for regional discount |
|
|
Depreciation using both methods is calculated, comparison is made and a justified recommendation is given |
|
|
Direct and Fixed Cost are properly identified and net income is calculated. Attention is paid to finding fixed cost based on allocation numbers and capacity |
|
|
Lost after-tax profit from Monza's cannibalized sales is properly calculated |
|
|
OCF is calculated based on approach used in earlier homework |
|
|
Opportunity costs are identified and properly calculated |
|
|
FCFs are calculated, combining together OCF, CapEx, investment in NWC, and opportunity costs |
|
|
NPV and IRR are properly calculated (attention to NPV formula use – check Excel mistakes screencast). For preliminary check, if WACC is not calculated yet, 8% can be used. For final submission, WACC calculated in WACC tab should be used |
|
WACC |
|
|
Assumptions about risk-free rate, MRP, tax rates and peer companies are made. Sources of information are provided in pink cells |
|
|
Data about peer companies downloaded from recommended sources (Yahoo Finance, EDGAR, Morning Star et al.) – levered beta, market value of equity, value of debt (book value of debt can be used instead), and possibly actual tax rates (unless assumption is made) |
|
|
D/E, E/Total Value ratios, and unlevered beta are calculated |
|
|
Mean and median of unlevered beta are found |
|
|
Zeta's relevered beta is estimated with proper Zeta's D/E ratio used |
|
|
Cost of equity is calculated using CAPM formula, calculated beta, and downloaded numbers for risk-free and MRP. |
|
|
After-tax cost of debt is calculated |
|
|
WACC is calculated |
|
Scenarios |
|
|
Electricity scenario summary is created by repeating basic analysis when using six different scenarios of electricity prices |
|
|
Sales volume scenario summary is created by repeating basic analysis when using three different scenarios of future sales volumes |
|
Electricity Breakeven |
|
|
Arbitrary year 1 electricity cost is chosen and electricity costs in subsequent years are made dependent on this initial cost |
|
|
EBIT is calculated either by using a complicated formula or by inserting extra rows and redoing calculations from basic analysis, but now as dependent on new electricity prices. DO NOT COPY VALUES of Body Materials electricity costs from Basic Analysis |
|
|
Investment in NWC is calculated either by using a complicated formula or by using already inserted extra rows |
|
|
FCF is calculated |
|
|
NPV is calculated by properly using NPV function |
|
|
Break-even year 1 electricity cost (making NPV = 0) is found either by trial and error or by using Excel Goal Seek |
|
Crystal Ball (Optional, extra 5% bonus) |
|
|
Assumptions cells are set at least for variables described in the project (Investment, Debt Financing %, interest rate, NWC Investment %, number of cannibalized cars, sales volume for each year, and electricity costs for each year). Averages should be the same as in the base case scenario. Additional assumptions can be made |
|
|
Simulation is run for NPV and IRR as forecast cells |
|
|
Probability of positive NPV is found based on NPV distribution chart |
|
|
Tornado chart is created |
|
Report |
|
|
Report starts from executive summary with your main conclusions and recommendations put there! |
|
|
Main part: · Very briefly describes work performed · Presents results · Analyzes results, focusing on risk analysis (different scenarios, sensitivities, breakeven etc.). · If simulation was performed, results are analyzed and discussed · Conclusions are drawn |
|
|
All sources used are properly cited and put in a reference list at the end. Remember that your instructor will submit your report to Turnitin. If you have your own access to Turnitin, I recommend submitting the report yourself and notify the instructor |
|
|
Formatting, spelling and grammar are checked. Proof reading helps to catch typos missed by software. |
|