Operations Management Case Analysis

profilePineapples4eva
M3A1casestudy.pdf

96 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

ISSN: 1676-4285

96

Project management for hospital accreditation: a case study Elana Maria Ramos Freire1, Renata Cristina Rocha Batista1, Maria Regina Martinez2

1 Federal University of Minas Gerais 2 Federal University of Alfenas

ABSTRACT Aim: describe the implementation of Project Managing techniques, based on the propositions of the Project Management Body of Knowledge (PMBOK), which was used on a Sterilization Central Supply, to help it meet the quality standards needed to get accredited. Methods: a descriptive case study. Participant observation, document analysis and a structured questionnaire were used to collect data. Results: the development and management of the project actions were based on eight PMBOK knowledge areas - Project Integration, Scope, Time, Quality, Human Resource, Communications, Risk and Stakeholder Management. Conclusion: project management made it possible to implement the project at the expected time and scope, meeting the quality standards, and allowing the team to better engage and compromise to the project.

Descriptors: Quality Management; Accreditation; Nursing.

97 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

INTRODUCTION

In a globalized scenario - defined by easy access to information, constant changes, tech- nological advances and growing competition in several activity fields - quality becomes essential when talking about attracting customers and customer loyalty. This is even more important in health care institutions, where surviving the market has become a challenge.

In an attempt to familiarize themselves with social and technological changes and meet the requirements of increasingly demanding customers, Health Care Managers have begun taking new approaches to implement increasing “quality” standards in the services they provide.

Quality is essential in healthcare, as it im- pacts greatly on society and in others systems of the field(1). However, meeting expectations and assuring the rights of the customer, and assuring a safe and qualified assistance during the present healthcare scenario, permeated by the continuous increase in care costs, a shorta- ge in investments and an ineffective use of the available resources, is challenging.

Due to this situation, hospitals have been investing in new care and management models, in order to achieve satisfactory results and be able to optimize resources, promote humanized care and improve the services provided and their outcomes(2), while focusing on patient safety.

It is noted a growing movement of hospi- tals seeking certification and quality assessment programs that demonstrate its results, improve the application of resources and expand the productivity and satisfaction of internal and external customers(3).

The hospital accreditation lies amongst ma- jor healthcare quality assessment programs, es- tablishing interdependent standards that must be thoroughly met to enable the healthcare facility reaches the pre-established quality levels.

According to the approach used by the Brazilian Accreditation System (Sistema Bra- sileiro de Acredição - ONA), accreditation is a process of evaluating institutional resources; it is an unforced, recurrent, private and confi- dential practice used to assure care assistance, based on previously approved standards. The standards could be either be minimal or more elaborated, establishing different levels of sa- tisfaction and qualification: level I or accredited, level II or fully accredited and level III or excel- lence accredited(4). An accredited healthcare institution distinguishes itself from others by the quality and safety shown in by its services, obtaining, therefore, more trust from its clients and social credibility(4).

Furthermore, being an accredited healthca- re institution makes it possible to promote orga- nizational changes, as it encourages habits and behavioral changes, enforcing the interruption of mechanized care, therefore improving qua- lity and providing a top quality organizational environment.

Healthcare Institutions that do not meet the desirable standards for accreditation have incongruities that need to be corrected through improvement projects, to fulfill established re- quirements and meet required quality standards.

Given that, healthcare projects are develo- ped to improve infrastructure, management and organizational processes.

A project works like a plan or temporary un- dertaking, presented to meet a proposed target, using resources in order to create a unique result in a limited time period(5). Projects are important change makers in healthcare institutions, as they provide the possibility of turning goals and strategies into real results.

Their creation goes beyond merely docu- ments and reports; projects are linked to day- -to-day company activities, and are therefore an import management tool for achieving good

98 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

results. Yet, for this to happen, the steps of the project need to be well performed(6).

In this context, managing the steps of a project is a marketplace challenge, as most companies do not have a proper organizational structure to do so.

Their management processes are based on traditional models, which limit the projects to their functional areas; these, in turn, may not always include the skills and capacities required to manage a project, once everyday activities have been prioritized(7).

Applying methodologies oriented to project management motivates employees to achieve strategic organizational goals, increa- sing the competitive edge. However, these me- asures are still rare when it comes to healthcare organizations(8,9).

Given that, professional project manage- ment, backed by scientific literature, becomes the key for developing and executing healthcare projects. Managing projects means applying knowledge, skills, tools and technique to project activities, with the aim of reaching or exceeding project requirements and expectations(5).

Project management goes from planning to subsequent implementation, in order to meet a particular purpose. Its primary focus is planning the scope of a project, so it can be finalized ac- cording to the established schedule and budget.

The finalization of the overall scope of a qualified project, within the planned schedule and without exceeding the budget, brings a sen- se of satisfaction to the client and to everyone involved in the project.

Amongst the existing Project Management procedures and guidelines, the Project Manage- ment Body of Knowledge (PMBOK) can be found. It consists of a guidebook containing facts about Project Management. The Project Management Institute (PMI) developed it, and it is recognized worldwide as a base reference in the field.

PMBOK compiles a set of project mana- gement tools and techniques, categorized in process groups or knowledge areas, which are recognized as “good practice” in the field, follo- wing the idea that a project is accomplished through a series of steps or actions to reach its goals and meet its requirements(5).

PMBOK uses five process groups and ten field areas to explain project management.

The process groups are initiating, planning, executing, monitoring/controlling and closing. The ten knowledge areas are project integration, scope, time, quality, human resource, commu- nications, risk, procurement and stakeholder management(5). Project Management makes projects faster, more organized, dynamic and interactive, therefore helping healthcare mana- gers when developing projects.

Scientific studies using project management are justified, as they provide an excellent oppor- tunity to improve and motivate the managing of projects in the healthcare field. So, helps nurse managers and other healthcare professionals to achieve autonomy and governability, using their competencies, specific health care skills and knowledge about project management. In addition, there are still very few scientific studies in literature, which approach this subject.

Given all the above, this present study ai- med to describe the implementation of Project Management Processes, based on the PMBOK propositions. The Project Management Proces- ses were used to develop an adaptation project to help a Central Sterile Supply (Central de Ma- teriais e Esterilização – CME) meet the standards established to get level I accreditation.

‑METHODS

A descriptive study was carried out, whi- ch deeply analyzed and described an atypical

99 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

situation, which occurred in a healthcare insti- tution. A case study seeks to explore a particular situation, which takes place in contemporary real life. It is well defined and contextualized in space and time, allowing the investigator to perceive the holistic and significant aspects of the events(1).

The study was held in a small private hos- pital, located in a town in the southern part of the state of Minas Gerais.

The hospital has room for 50 beds, which are allocated to ambulatory, adult ICU, NICU and observation beds in the Emergency Department. The facility also includes a surgical wing, image and laboratory diagnostic services and medical offices. Since the hospital was visited by a cer- tified accrediting institution (CAI) in 2006 and received its organizational diagnosis, it has been pursuing its accreditation.

Ever since, the establishment has been investing in continuous improvements of proce- dures and infrastructure, receiving accreditation from the National Accreditation Organization (Organização Nacional de Acreditação - ONA) in 2013, reassuring its commitment to quality and patient safety. The present case study in- cludes the CME of the aforementioned hospital; the object of analysis was the management of the CME Adaptation Project, which was based on the requirements for project management, prescribed by the PMBOK.

The study took place from May 2011 to May 2012, and it was conducted with approval from the institutional ethic committee at the Univer- sidade Federal de Alfenas (Code 085/2011). Due to ethical and privacy reasons, the research field was named Hospital X.

The CME was chosen as the study case, ba- sed on the premise that it is a hospital area that needs help to eliminate nonconformities and bring it up to standard to meet the requirements for hospital accreditation, all within a year.

Participant observation, document analysis and a structured questionnaire were used to collect data.

The participant observer was the resear- cher, who was not employed by the hospital, but joined the working team as the project manager. The observer was responsible for planning and managing the projects, acting as a team member in the organizational environment and partaking in the situations analyzed, therefore being an essential decision maker in the activities that were carried out(11).

The observation was carried out during the entire research process; the data, registered without a structured script, was documented in a field journal.

During the project planning and imple- mentation, daily activities and the behavior of the CME professionals and others involved in the project were observed. This was done to obtain information, in order to manage the team’s engagement and embracement of the suggested activities.

The analyzed document consisted of the organizational diagnosis report, which provided essential information to evaluate the adequacy needs of the CME.

To determine the team’s satisfaction with the project and its results, structured scripts were used during the quality control stage. Two questionnaires were elaborated; five CME staff members answered one and two members of the Hospital Coordination Unit - the Hospital Coordination Unit Nurse Manager and the coordinator of the Hospital Infection Control Committee, answered the other.

The questionnaires consisted of 12 closed questions (Likert Scale) and an open question, which was used for criticisms and suggestions. Opinions regarding the changes made to the techniques and infrastructure of the CME, as well as the evaluation of the project manage-

100 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

ment, considering time, scope, quality, com- munication, risk management, the relationship between the manager and team members and the achievement of desired outcomes, were all topics included in the questionnaires. During this particular research stage, only the workers who were directly involved in the execution and/or planning of the project were allowed to participate.

The investigation was divided into three phases. In the first phase, an organizational diag- nosis of the CME was made, with the purpose of identifying nonconformities that could prevent it getting a level I accreditation.

The second phase consisted of elabora- ting the CME Adaptation Project, carried out in partnership with the hospital administration, establishing the goals and targets to be met.

Finally, the third phase - and the main point of this article - included the execution of the project and its follow up, with the help of free software called OpenProject and based on the propositions of the Project Management Body of Knowledge (PMBOK).

The data found was analyzed and presen- ted in a descriptive manner, using a chronologi- cal approach(11), following the sequence in which the events occurred throughout the study. It was divided into two phases: CME Situational Diag- nosis presentation(12) and elaboration/execution of the CME Adaptation Project.

RESULTS

Situational Diagnosis

Situational diagnosis was conducted to identify existing inconsistencies, related to both the quality standard required for level I accreditation by ONA(5) and also to the current

legislation, ANVISA RDC 50(13) and RDC 15(14) reso- lutions. The situational diagnosis made outlining a profile of the CME possible; this profile provi- ded the necessary information for developing the department’s adaptation project(1,2).

CME Adaptation Project

The CME Adaptation Project formally star- ted after a meeting between the researcher, a member of the hospital administration, the nurse coordinator and the CME nurse. At this me- eting, they determined the actions that would take place, taking in account their priorities and the resources available (human, material and financial resources).

The project was managed based on the five PMBOK management process groups, taking into consideration seven knowledge areas (CHART 1).

Cost and acquisition management were not explored in this research, as the hospital had a functional and organizational structure, defined by a lack of specific funds for developing the project and limited resources - which were controlled by senior management - resulting in restricted authority for the project manager. Consequently, a non-involvement policy regar- ding the cost and acquirement areas was created for the project manager.

Initiation Processes

Performed in order to define a new project, initiation processes identify the project needs, goals and targets, also defining its team and manager(5).

During the CME Adaptation Project, the following initiation processes were performed: • Development of the project’s opening form: a

document that formally authorizes the execu- tion of the project and includes the stakehol-

101 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

ders’ needs and expectations. Thanks to the si- tuational diagnosis, it was possible, not only to display the project demands and necessities, but also to elaborate the organizational chart of the project, which holds information such as the demands that brought the project to life, its purpose, propositions, organizational constraints, the assigned manager and team.

• Stakeholder identification: identifying peo- ple or organizations that somehow could be influenced by the project, in a negative or

positive way, and information related to their interests, involvement with the project and the type of impact on it (Figure 1).

In Figure 1, the positive rating refers to the stakeholders who are likely to benefit from the project’s successful conclusion, while the nega- tive rating refers to those who are inclined to be damaged or inconvenienced.

The level of interest is equivalent to the level of concern with the results; the subjects’ active participation in developing and executing

Chart 1 - Project Management process groups or knowledge areas used in the Adaptation Project of the CME. Minas Gerais, 2012.

Knowdlege Area

Project Managing Process Groups

Initiation Pro- cess Group

Planning Proces- ses Group

Execution Pro- cesses Group

Monitoring and Controlling

Processes Group

Closing Processes

Group

Project Integra- tion Management

Develop the project opening form.

Guide and ma- nage the project execution.

Close the project.

Project Scope Management

Gather requirements and defining scope. Verify the scope.

Develop the WBS.

Project Time Management

Define and sequence the activities, estima- te human resources, estimate duration and develop the schedule.

Control the sche- dule.

Project Quality Managament

Quality planning. De- velop a Quality Plan.

Establish quality control.

Project Human Resource Mana- gement

Develop the HR plan. Mobilize, develop and manage the project team.

Project Commu- nication Manage- ment

Communications planning.

Distribute the informations.

Project Risk Ma- nagement

Identify the risks, do a qualitative risk analysis, risk response planning.

Monitor and con- trol the risks.

Project Stakehol- der Management

Identify stakehol- ders.

Manage the stakehol- ders expectations.

Caption: Work Breakdown Structure (WBS); Central Sterile Supply (Central de Materiais e Esterilização – CME). Source: Authors’ personal archive.

102 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

actions is comparable to their engagement with the project, while the ability to make changes in the project planning and execution matches the project impact.

Figure 1 - Stakeholders register of the SCS Adaptation Project. Minas Gerais, 2012.

Stakehol- ders

Rating Interes- se

Envolvi- mento

Im- pacto

Hospital Administra- tion

Positive High Low High

Nursing Co- ordination

Positive High High High

Project Manager

Positive High High Inter- media- te

SCS workers

Positive High Interme- diate

Low

Hospital Infection Control Committee

Positive High Low Low

Patients Positive High Low Low Private Practices

Positive High Low Low

Caption: Central Sterile Supply (Central de Materiais e Esterilização – CME). Source: Archive taken from the CME Adaptation Project.

Planning Processes

Planning processes are applied to planning actions and define the path or course of the project, in order for it to meet its established goals and targets.

The planning processes used in this rese- arch were: • Gather Requirements - using situational diag-

nosis, it was possible to raise some project demands that were secured after a meeting with the hospital administration, the nursing coordination and the CME nurse. The CME workers were also informally interviewed, in order to confirm the necessity of the defined

changes, and, if needed, to add or eliminate determinations.

• Scope definition - consists of making an ela- borate report of the project and the services provided by it, describing its goals, the project base, acceptance criteria, time estimated to execute it, project constraints and deadline dates. Creation of a work breakdown structure - is an oriented decomposition of the project into smaller components for easier manage- ment, resulting in a hierarchical decomposi- tion of the total scope of work, organizing and displaying it, in order to achieve better control and supervision of the project.

• Activities definition and sequencing, activity resources estimation and development of the project calendar - actions were determined, in order to reach the project handover phase. The activities were arranged according to their connection with the project, while estimating the number of materials, equipment and people required for developing each project activity. The work time necessary to conclude each activity, using the available resources, was also estimated, as shown in Figure 2.

• Project Quality Management(8) - there were defined ways to demonstrate when and how the quality range would be measured throu- ghout the project. Signing off the project in the established time, respecting 90% to 100% of the scope, the CME employees’ satisfaction and acceptance of the project outcomes, and the organization’s satisfaction with the project were established as standards to measure the project quality.

• Human resources planning - used to determi- ne who would be responsible for each work package, establishing roles, responsibilities and hierarchical relationships.

• Communications Planning - used to define each stakeholder’s need for information, as well as to establish when it should be passed

103 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

Figure 2 - List of sequenced activities, dependency listing and duration of the activities of the Adap- tation Project of the SCS. Minas Gerais, 2012.

Name Duration Beginning Ending Prede-

cessor Resource Name

1 Permanent Health Education 1 day 11/29/2011 08:00:00 11/29/2011 17:00:00 Project Manager 6 ! Centralize equipment storage 3 days 01/12/2011 08:00 12/05/2011 17:00 Functional Manager 7 Arrange a thermosthat 2 days 12/01/2011 08:00 12/02/2011 17:00 Functional Manager

8 Form for daily temperature and humidity controlling

1 day 02/12/2011 08:00 12/02/2011 17:00 Functional Manager

9 Empty and clean storage cabinets 1 day 12/05/2011 08:00 12/05/2011 17:00 SCS staff 10 Put away sectors equipment 1 day 12/05/2011 08:00 12/05/2011 17:00 9 SCS staff 11 Arrange exclusive uniform 10 days 12/02/2011 08:00 12/15/2011 17:00:00 Functional Manager 2 ! Limit area access 3 days 12/05/2011 08:00 12/07/2011 17:00 Functional Manager

3 Meeting between SCS staff and other hospital workers

2 days 12/05/2011 08:00 12/06/2011 17:00 Functional Manager

4 Display signs of “restricted area” 1 day 12/05/2011 08:00 12/05/2011 17:00 Functional Manager 5 Continuous supervision 3 days 12/05/2011 08:00 12/07/2011 17:00 Functional Manager 12 Adaptation of a changing room for the SCS 7 days 12/08/2011 08:00 12/16/2011 17:00:00 Functional Manager

14 ! Designated area for sterilization 48 days 12/19/2011 08:00:00 02/22/2012 17:00:00 Project Manager; Functional Manager

15 Planning 15 days 12/19/2011 08:00:00 01/06/2012 17:00 Functional Manager

16 Construction 30 days 01/09/2012 08:00 02/17/1217:00:00 Construction workers and co...

17 Implementation of routines 3 days 02/20/2011 08:00:00 02/22/2012 17:00:00 Project Manager

18 Uptade of the Rules and Regulations Hand- book

30 days 01/10/2012 08:00 02/20/2012 17:00:00 Project Manager

19 ! Strategies for tracing the instruments in use 7 days 02/08/2012 08:00 02/16/2012 17:00:00 Project Manager 20 Defining specific form 2 days 02/08/2012 08:00 02/09/2012 17:00 Project Manager

21 Qualify workers to use the form 1 day 02/10/2012 08:00 02/10/2012 17:00 20 Project Manager; Functional Manager

22 Follow the implementation of the new form 4 days 02/13/2012 08:00:00 02/16/2012 17:00:00 21 Project Manager

24 ! Elaborate strategies to biologically control implantable medical devices

20 days 02/29/2012 08:00:00 03/27/2012 17:00:00 Project Manager

25 Study budget 7 days 02/29/2012 08:00:00 03/08/2012 17:00 Project Manager 26 Make the request and wait for return 13 days 03/09/2012 08:00 03/27/2012 17:00:00 25 Functional Manager

27 Arrange air conditioning system for clean- -room and sterile area

20 days 03/01/2012 08:00 03/28/2012 17:00:00 Functional Manager

23 Elaborate strategies to date packages 30 days 03/20/2012 08:00:00 04/30/2012 17:00:00 Project Manager

13 Arrange automatic touchless faucet for clean- -room

15 days 04/02/2012 08:00 04/20/2012 17:00:00 HICC Nurse

Souce: Archive taken from the CME Adaptation Project.

on, the best methods to do so and a person responsible for reporting the information for each method chosen.

• Risk identification, quantitative risk analysis and risk response planning - the identified risks were classified, taking in account the pro- bability of occurrence, the time impact and the impact they would have on the project scope (Figure 3). For each risk, a response or action was developed: mitigate it, eliminate it or ignore the risk factor. Both the identified risks and the determined actions were defi- ned during management meetings between the Functional Manager, the researcher (the

Project Manager), the CME nurse and other stakeholders.

Executing Processes

Consist of developing the scheduled activities, in order to conclude the project in accordance with the established requirements. The Executing Processes used were: • Project Execution Managing and Directing –

consists of doing the activities according to the schedule, aided by activity monitoring, schedule control and team management, conflic ts management, communication

104 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

management and risks and changes mana- gement, aimed at achieving a better work environment and greater accomplishment of the project requirements. Mobilize, develop and manage the project team - assigning professionals for each activity, so the pro- ject can obtain the adequate resources for its execution, as proposed in the human resource planning.

Team Training, doing periodic performance evaluations, establishing direct contact by the Project Manager with the staff while the activi- ties are being executed. • Distributing Information and managing

the expectations of the stakeholders - dis- tributing information according to the communication management plan. Group or individual meetings were held to give the stakeholders unexpected information. The manager sought to have a positive rela- tionship with all stakeholders, which made establishing trust relationships, resolving conflicts and accepting changes easier for both parties.

Monitoring and Controlling Processes

Responsible for monitoring the activities to make sure they are concluded as scheduled. The Monitoring and Controlling Processes used were: • Project Scope Verification - a meeting was

held between the Functional Manager and the hospital administration to review the de- livery of the project’s goals and to make sure the scheduled scope was delivered.

• Schedule Control - weekly meetings betwe- en the Project Manager and the Functional Manager were held to compare the planned schedule with the actual project status. These meetings were also used to distinguish the finalized activities from the delayed ones.

Next, responses were elaborated, in order to correct possible delays encountered or even to postpone delivery dates. The schedule was updated after discussion between the concerned parties.

• Quality Control(8) - used to ensure that the project met the quality standards established in the Quality Planning process. The aims described in the scope and also the deadlines were verified to check if they had been met according to the schedule. Structured ques- tionnaires were given to the CME staff, nur- sing coordination and the Hospital Infection Control Committee, in order to evaluate their satisfaction level with the project outcomes. Consequently, the quality standards were positively evaluated, meeting the hospital workers’ expectations.

• Risk Monitoring and Control - the process of following and monitoring risks that have already been identified, identifying new risks, and executing the plan for identifying and controlling them.

Closing Processes

These are done in order to bring the project and all planned activities to a close. • Project Closure: during this process, all the

planned work was checked to make sure it had been concluded and that the objectives that were predicted before the project started had been fulfilled; all the resulting paperwork was filed. Finally, a meeting with the Functio- nal Manager was held, in order to formalize the closure of the project activities and to confirm all the aims of the project were deli- vered. The Project Manager went through the remaining executed processes, verifying if the planned requirements had been fulfilled. The aims that were not concluded were included in the hospital’s strategic planning.

105 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

DISCUSSION

Companies have been investing in metho- ds and techniques to achieve desired results and answer clients expectations(6) in order to main- tain the competitive lead. Project Management is a powerful tool for this purpose.

Management Processes are suitable for most projects, having an increasingly approval in the most diverse fields(5).

Companies of different fields have been using the PMBOK as a foundation to acknow- ledge its advantages in order to increase the success of their projects. It is also a vast field to be explored in studies proposing development of new products, services and/or systems for healthcare organizations(15).

In this present research, project manage- ment processes were of great importance for developing the CME Adaptation Project in a prompt and organized way, especially when it came to communication, engagement of the team with project activities and reaching the

results within the time and scope predicted, meeting the institution expectations. Sup- porting these results, in a hospital research during which PMBOK processes were used to the implementation of a Costs Center Project, communication and stakeholder managing were fundamental to the project success, as it enabled team awareness, decrease of internal resistance and a higher acceptance of the final deliveries. The identification and engagement of the stakeholders were designed in the planning phase and put into practice in the execution, monitoring and controlling phases, considering that, in an organization, change processes are very likely to cause resistance, which must be considered in its scope and planning.

One of the main difficulties when mana- ging this research project consisted of the fact the hospital is a functional structure organiza- tion, in which the workers couldn’t dedicate the- mselves exclusively to the project or even had an hourly load dedicated to its activities, having

Figure 3 - Risk Identification and Control Plan for the CME Adaptation Project. Minas Gerais, 2012.

Risks Probabi-

lity Time

Impact Scope Impact

Actions

Finance division not releasing bud- get to: construction of the scrubbing area, air conditioning system for clean-room and sterile area, biologi- cal testing for all devices, touchless faucet for clean-room

High High High

Mitigate the risk: renegociate the deadline, placing the activity as a priority in the organization strategic planning so it can be accompli- shed in another moment or given deadline.

The arise of other priorities in the hospital

Interme- diate

Interme- diate

Interme- diate

Renegociate with the project team a way to conciliate the project and the priority in question, define work hours.

CME staff not adopting the imple- mented routine

Low Low Low

Prevent risk: introduce and involve the staff in the project planning process, keep a good relationship between the team members, qualify and train the team before the imple- mentation of the new routines.

Caption: Central Sterile Supply (Central de Materiais e Esterilização – CME). Source: Archive taken from the SCS Adaptation Project.

106 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

to conciliate activities related to the project with professional routine.

Besides, the Project Manager did not have autonomy to make decisions regarding costs and resources allocation.

The fight for resources (material, financial, human) and the involvement of these in multiple projects inside one organization is a significant institutional projects problem, worsening in functional organizations, where the managers usually are responsible for certain decisions, but do not hold the authority over the company resources. Given that, it is necessary to invest in studies, researches and efforts to adapt manage- ment models that integrate innovation activities to the organizations daily activities.

Regarding the viability of the implementa- tion of PMBOK propositions in healthcare pro- jects management, another study demonstrated that its application to the field was viable and promising to the project development. It also significantly contributed to the project perfor- mance in terms of communication, teamwork and experience, making it possible to deliver the project within the scheduled time and allocated budget and corroborating this present research. Implementing PMBOK can benefit both mana- gement processes and medical and healthcare scientific research results.

Regarding Nursing, although Registered Nurses are not taught to manage during gradu- ation school, there are many abilities and skills developed throughout nursing school and sub- sequent career that can be helpful in their work environment(18). Leadership, administration and management, communication, decision making and permanent education are some of the administrative skills learned during a Nursing graduation course.

Based on the above considerations, the PMBOK application is viable and can contribu- te in the improvement of healthcare projects.

More studies approaching this thematic are needed in order to encourage and stimulate Project Management in healthcare institu- tions. As soon as the CME Adaptation Project was over, the institution was submitted to the ONA certification evaluation, receiving the title of Accredited Hospital. Thus, it can be concluded that the project contributed to the CME adaptation to the quality standards, and, consequently, to its certification.

Consisting evidences indicate that accredi- tation programs improve in a significant manner the healthcare outcomes, should then be viewed as an incentive tool to improve the quality of the services provided.

CONCLUSION

The utilization of management techni- ques in healthcare projects can help healthcare managers improve the quality of the service they provide and obtain hospital accreditation certifications.

In this study context, Project Management allowed for a professionalized management model, based on scientific literature, which con- tributed to achieving the project goals within the planned time and scope. It also allowed for an increase in the effectiveness of the commu- nication and commitment of the professionals, seeking organization, agility and quality results. In healthcare institutions, nurses are responsible for managing health assistance and services, as they have a good knowledge of the hospital sectors and processes. They also work toward quality results.

Given that, nurses have all the abilities and skills needed to take on Project Management in these organizations.

107 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

ACKNOWLEDGEMENTS

To Coordination for the Improvement of Higher Education Personnel (Coordenação de Aperfeiçoamento de Pessoal de Nível Supe- rior – CAPES), for the financial support; and to Observatory Extension Program of Healthcare Management of the Federal University of Alfenas (Programa de Extensão Observatório de Gestão Hospitalar da Universidade Federal de Alfenas - Unifal-MG).

REFERENCES

1. Manzo BF, R HCTC, Brito MJM, Alves M. Nur- sing in the hospital accreditation process: practice and implications in the work quo- tidian. Rev. Latino-Am. Enfermagem [Inter- net]. 2012 Feb [cited 2016 Jan 28]; 20(1): 151-158. Available from: http://www.scielo. br/scielo.php?script=sci_arttext&pid=S0104- - 1 1 6 9 2 0 1 2 0 0 0 1 0 0 0 2 0 & l n g = e n . d o i : h t t p : / / d x . d o i . o r g / 1 0 . 1 5 9 0 / S 0 1 0 4 - 11692012000100020.

2. M BF, Brito MJM, Corrêa AR. Implications of hospital accreditation on the everyday lives of healthcare professionals. Rev. esc. enferm. USP [Internet]. 2012 Apr [cited 2016 Jan 28]; 46 (2): 388-394. Available from: http://www.scielo. br/scielo.php?script=sci_arttext&pid=S0080- -62342012000200017&lng=en. doi: http://dx.doi. org/10.1590/S0080-62342012000200017.

3. Vituri DW, Évora YDM. Total Quality Mana- gement and hospital nursing: an integrative literature review. Rev. Bras. Enferm. [Inter- net]. 2015 Oct [cited 2016 Jan 28]; 68 (5): 945-952. Available from: http://www.scielo. br/scielo.php?script=sci_arttext&pid=S0034- -71672015000500945&lng=en. doi: http:// dx.doi.org/10.1590/0034-7167.2015680525i.

4. Organização Nacional de Acreditação. Manual das Organizações Prestadoras de Serviços de Saúde. 2014. Brasília: Organização Nacional de Acreditação; 159 p.

5. PMI. Project Management Institute. A guide to the Project Management Body of Knowledge. 5 ed. Pennsylvania: Project Management Institute Inc; 2012. 589 p.

6. Menezes YS, Ribeiro Neto AS. A gestão de pro- jetos segundo o pmbok para a captação de recursos no Hospital Padre Colombo, na cidade de Parintins-AM. Revista Contribuciones a las Ciencias Sociales, n. 30 octubre-diciembre 2015. Available from: http://www.eumed.net/rev/ cccss/2015/04/pmbok.html

7. Rabechini Junior R, Carvalho MM, Rodrigues I, Sbragia R. A organização da atividade de geren- ciamento de projetos: os nexos com competên- cias e estrutura. Gestão & Produção. [Internet]. 2015 Oct [cited 2016 Jan 28];18(2):409-424. Available from: http://www.scielo.br/scielo. php?script=sci_arttext&pid=S0104-530X2011 000200014&lng=pt&tlng=pt.doi:http://dx.doi. org/10.1590/S010430X2011000200014.

8. Freire EM, Martinez MR. Gerenciamento da qualidade de um projeto de adequação de uma central de materiais e esterilização: um estudo de caso. 2013. Anais online- Ano 2013. II Con- gresso Online - Gestão, Educação e Promoção da Saúde. Available from: http://www.convibra. com.br/upload/paper/2013/61/2013_61_6457. pdf

9. Hors C, Goldberg AC, Almeida EHP, Babio Júnior FG, Rizzo LV. Application of the enterprise ma- nagement tools Lean Six Sigma and PMBOK in developing a program of research management. Einstein (São Paulo) [Internet]. 2012 Dec [cited 2016 Jan 28]; 10 (4): 480-490. Available from: http://www.scielo.br/scielo.php?pid=S1679- - 4 5 0 8 2 0 1 2 0 0 0 4 0 0 0 1 5 & s c r i p t = s c i _ a r t - tex t. d o i : ht t p : / / d x . d o i . o rg / 1 0 . 1 5 9 0 / S 1 6 7 9 45082012000400015.

10. Gido J, Clements JP. Gestão de projetos. São Paulo: Cengage Learning; 2011. 472 p.

11. Yin RK. Estudo de caso: planejamento e métodos. 4 ed. Porto Alegre: Bookman; 2010. 212 p.

12. Freire EMR, Martinez MR. Situational diagnosis: an aid tool in quality management. Rev enferm UFPE [online]. 2014 Dec [cited 2016 Jan 28] ;8 (5): 1405-12. Available from: http://www.revista.ufpe. br/revistaenfermagem/index.php/revista/article/

108 Freire EMR, Batista RCR, Martinez MR. Project management for hospital accreditation: a case study . Online braz j nurs [in- ternet] 2016 Mar [cited year month day]; 15 (1):96-108. Available from: http://www.objnursing.uff.br/index.php/nursing/ article/view/5158

download/4310/9145. http://dx.doi.org/10.5205/ reuol.5863-50531-1-ED.0805201440.

13. Brasil. Ministério da Saúde, Agência Nacional de Vigilância Sanitária. Resolução n° 50, de 21 de fevereiro de 2002, com texto alterado pela resolução RDC nº 307, de 14 de novembro de 2002. Dispõe sobre o Regulamento Técnico para planejamento, programação, elaboração e avaliação de projetos físicos de estabeleci- mentos assistenciais de saúde. Available from: http://portal.anvisa.gov.br/wps/wcm/connect/ ca36b200474597459fc8df3fbc4c6735/RDC+N %C2%BA.+50%2C+DE+21+DE+FEVEREIRO+ DE+2002.pdf?MOD=AJPERES.

14. Brasil. Ministério da Saúde, Agência Nacional de Vigilância Sanitária. Resolução nº 15, de 15 de março de 2012. Dispõe sobre requisitos de boas práticas para o processamento de produtos para saúde e dá outras providências. Available from: http://portal.anvisa.gov.br/wps/wcm/co nnect/7599770043e684468b198f45f4f7d4e4/ rdc0015_15_03_2012.pdf?MOD=AJPERES.

15. Grell AP, Rosa CDP. Gestão de projetos como agente facilitador na implantação do sistema de custos por departamento em um hospital pú- blico. Revista Acadêmica São Marcos. [Internet]. 2015 Jul [cited 2016 Jan 28]; 5 (1): 2-24. Available from: http://www.saomarcos.br/ojs/index.php/ rasm/article/view/114/84.

16. Quartaroli C, Martins LCS. Gestão das comunica- ções em projetos de tecnologia da informação. PM World Today. [Internet]. 2010 [cited 2016 Jan 28]; 12 (1): 1-11. Available from: http://www. pmies.org.br/clickadmin/midias/data/artigo- -PMI_RIO.

17. Payne JM, et al. Researchers’ experience with project management in health and medical re- search: Results from a post-project review. BMC Public Health. 2011 [cited 2016 Jan 28]; 11 (424): 1-11. Available from: http://www.ncbi.nlm.nih. gov/pubmed/21635721. doi: http://dx.doi.org/ 10.1186/1471-2458-11-424.

18. Overgaard PM. Get the keys to successful project management. Nursing Management. 2010 [cited 2016 Jan 28]; 41 (6): 53–54. Available from: http:// journals.lww.com/nursingmanagement/Full- text/2010/06000/Get_the_keys_to_successful_

project_management.12.aspx. doi: http://dx.doi. org/10.1097/01.NUMA.0000381744.25529.e8 2010.

19. Caveião C, Zagonel IPS, Coelho ICM, Peres AM, Montezeli JH, Venturi KK. Students’ Competen- ces with Regard to Nursing Administration: an exploratory and descriptive research. Online braz j nurs [Internet]. 2014 December [Cited 2016 Jan 28]; 13 (4): 602-12. Available from: http://www. objnursing.uff.br/index.php/nursing/article/ view/4770. doi: http://dx.doi.org/10.5935/1676- 4285.20144770

20. Alkhenizan A, Shaw C. Impact of Accreditation on the Quality of Healthcare Services: a Systematic Review of the Literature. Annals of Saudi Medici- ne. 2011 Ago [Cited 2016 Jan 28]; 31 (4): 407-16. Available from: http://www.ncbi.nlm.nih.gov/ pmc/articles/PMC3156520/. doi: http://dx.doi. org/10.4103/0256-4947.83204.

All authors participated in the phases of this publication

in one or more of the following steps, in According to

the recommendations of the International Committee

of Medical Journal Editors (ICMJE, 2013): (a) substantial

involvement in the planning or preparation of the

manuscript or in the collection, analysis or interpretation

of data; (b) preparation of the manuscript or conducting

critical revision of intellectual content; (c) approval of the

version submitted of this manuscript. All authors declare for

the appropriate purposes that the responsibilities related to

all aspects of the manuscript submitted to OBJN are yours.

They ensure that issues related to the accuracy or integrity

of any part of the article were properly investigated

and resolved. Therefore, they exempt the OBJN of any

participation whatsoever in any imbroglios concerning

the content under consideration. All authors declare that

they have no conflict of interest of financial or personal

nature concerning this manuscript which may influence the

writing and/or interpretation of the findings. This statement

has been digitally signed by all authors as recommended

by the ICMJE, whose model is available in http://www.

objnursing.uff.br/normas/DUDE_eng_13-06-2013.pdf

Received: 02/10/2015 Revised: 01/25/2016 Approved: 01/25/2016

Copyright of Online Brazilian Journal of Nursing is the property of Fluminense Federal University, Online Brazilian Journal of Nursing and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.