| Porta-Vac Project |
|
| Instructions: |
|
|
|
|
|
|
|
| Questions: |
|
| Complete the tables below to answer the questions to the right. |
|
|
|
|
|
|
|
| 1. What is the probability that this project will be completed within the goal of 20 weeks? |
|
|
|
|
|
|
| 94.5% |
(Note =K30 with Goal set to 20 weeks.) |
|
|
|
|
|
|
|
|
|
|
| 2. What is the probability that this project will be completed faster, within 19 weeks? |
|
|
|
|
|
|
| 83.0% |
(Note =K30 with Goal set to 19 weeks.) |
|
|
| Data given by Porta-Vac Production Leaders |
|
| (see formulas and hints in green to the right) |
|
|
|
| A-E-H-I-J |
A-C-F-J |
A-D-G-J |
B-H-I-J |
|
| Activity |
Optimistic (a) |
Most Probable (m) |
Pessimistic (b) |
Expected Completion Time (weeks) |
Variance (weeks^2) |
Slack (weeks) |
On critical Path? (Yes=1 or No=blank) |
| Path 1 (Yes=1 or No=blank) |
Path 2 (Yes=1 or No=blank) |
Path 3 (Yes=1 or No=blank) |
Path 4 (Yes=1 or No=blank) |
|
| A |
4 |
5 |
12 |
6 |
1.78 |
0.00 |
1 |
| 1 |
1 |
1 |
|
| B |
1 |
1.5 |
5 |
2 |
0.44 |
4.00 |
|
|
|
|
| 1 |
|
| C |
2 |
3 |
4 |
3 |
0.11 |
2.00 |
|
|
| 1 |
|
| D |
3 |
4 |
11 |
5 |
1.78 |
1.00 |
|
|
|
| 1 |
|
| E |
2 |
3 |
4 |
3 |
0.11 |
0.00 |
1 |
| 1 |
|
| F |
1.5 |
2 |
2.5 |
2 |
0.03 |
4.00 |
|
|
| 1 |
|
| G |
1.5 |
3 |
4.5 |
3 |
0.25 |
1.00 |
|
|
|
| 1 |
|
| H |
2.5 |
3.5 |
7.5 |
4 |
0.69 |
0.00 |
1 |
| 1 |
|
| 1 |
|
| I |
1.5 |
2 |
2.5 |
2 |
0.03 |
0.00 |
1 |
| 1 |
|
| 1 |
|
| J |
1 |
2 |
3 |
2 |
0.11 |
0.00 |
1 |
| 1 |
1 |
1 |
1 |
|
|
|
|
|
|
|
|
|
| Expected completion time= |
17 |
13 |
16 |
10 |
weeks |
| (Hint: Try =SUMPRODUCT(Path,Expected Completion Time) |
|
|
| Goal to complete = |
20 |
weeks |
|
|
|
| Path variance= |
2.722 |
2.028 |
3.917 |
1.278 |
weeks-squared |
| (Hint: Same =SUMPRODUCT as above) |
|
|
|
|
|
|
|
|
|
| Path StDev= |
1.65 |
1.42 |
1.98 |
1.13 |
weeks |
| (Hint: take the square-root of the variance. =SQRT(x) |
|
|
|
|
|
|
|
|
|
| z-score= |
1.818 |
4.916 |
2.021 |
8.847 |
|
|
|
|
|
|
|
|
|
| Probability to complete within Goal = |
96.5% |
100.0% |
97.8% |
100.0% |
| Note: P = NORM.S.DIST(z-score,TRUE), with TRUE to indicate Cumulative Distribution function, as Standard-Normal Distribution has a Mean=0 and StDev=1. |
|
|
|
|
|
|
|
|
|
| Probability to complete Critical Path on-time = |
96.5% |
|
|
|
|
|
|
|
|
|
| Probability to complete all paths by the goal = |
94.5% |
| Note: All tasks must be completed on time, not just the Critical Path. Therefore, P(all) = P1 * P2 * P3 * P4 |
|
|
|
|
|
|
|
|
|
|
|
|
| Hint: Change the goal in cell D21, then paste the answers above. |