Concrete
Lecture 8
Estimating Concrete
Separate concrete by:
Type
Strength
Color
Special testing
Special curing
3/19/2021
2
Concrete Footings
Found on:
Wall sections
Foundation plan
Look for different sizes under different walls
Concrete Footings
Volume = Length x Width x Depth
Measured in cubic yards
Waste: 8% for slabs, 5% for other
elements
3/19/2021
3
Placing Concrete
Typical Productive Rates
Type of Placement LHR/c.y.
Continuous Footing - Direct Chute 0.4
Spread Footings – Direct Chute 0.873
Drilled Piers 0.320
Formed Piers 0.873
Foundation Walls – Direct Chute 0.5
Grade Beams 0.4
Slab – Direct Chute 0.32
6
Reinforcing Steel
Type of steel: grade, smooth/deformed, type
of coating
Size: #3 to #14
Unit: ton (2000 lbs)
Lap Splicing
Waste: 10% when the bars are cut and bent
on the job
Keeps type of placement (i.e., beams, columns, etc.) separate
Supports: chairs, spacers, bolsters, wires,...
3/19/2021
4
Rebar Properties Bar
Designation Nominal Diameter
Cross-sectional Area
Weight (pound per ft)
2 1/4” 0.05 0.167
3 3/8” 0.11 0.376
4 1/2” 0.20 0.668
5 5/8” 0.31 1.043
6 3/4” 0.44 1.502
7 7/8” 0.60 2.044
8 1” 0.79 2.670
9 1-1/8” 1.00 3.400
10 1-1/4” 1.27 4.303
11 1-3/8” 1.56 5.313
8
3/19/2021
5
9
Welded Wire Mesh
Designation: 6x6 10/10 long. spcg x
trans. spcg. gage long. x gage trans.
Available in 5' x 150' rolls
Unit: 100 sf (CSF)
Can be estimated by roll or sheet
Lap: one transverse spacing, i.e., 10%
for 6x6 10/10
Waste: 5%
BCN 5618 10
3/19/2021
6
Reinforcing Productivity
Type of Placement Productivity Rate (Labor Hrs/Ton)
Beams #3 to #7 22
Columns #3 to #7 24
Footings #4 to #7 15
Walls #3 to #7 11
Slab on Grade #3 to #7 13
Wire Mesh 1 per roll
Vapor Retarder
Estimated by the roll
Best to sketch a layout
Sq. Ft of Vapor Barrier Labor Hour per 1,000 Sq. Ft.
Up to 1,000 1.5
1,000 to 5,000 1.25
Over 5,000 1
3/19/2021
7
Accessories
Expansion joint covers
Expansion joint fillers
Waterstop
Manhole frames and covers
Trench frames and covers
14
Curing
Cement hydration requires time (3 to 14 days), favorable temperatures, and moisture. Curing options are:
leaving forms in place
sprinkling
spray mists
moisture retention covers
seal coats (curing compound)
Hot and cold concreting
3/19/2021
8
Concrete Transportation
Truck chutes
Buggies
Crane and bucket
Crane and hopper
Tower and buggies
Forklifts
Conveyors
Pumps
Forms
Often bid by the square foot contact area
Be sure include:
Both sides
Ends
Bottom (if required)
Cost is affected by number of uses
3/19/2021
9
17
Forms
Selection and design of forms are the responsibility of the general contractor.
Unit: square feet of contact area (SFCA)
Number of times the form may be reused
Length of time the form must stay in place
To rent or purchase
Types of forms: wood, metal, fiberglass
No deductions in the area for opening less than 30 sf
18
Forms Forms estimate includes: materials; labor to
assemble, erect, strip, clean, and repair; and equipment.
Factors affecting the cost of concrete wall forms: height of the wall
shape of the building
Factors affecting the cost of concrete floor floor-to-floor height
reusability of the forms
length of the time forms must be in place
type of shoring and support used
3/19/2021
10
Form Productivity
Application Productivity Rate (Labor Hours per SFCA)
1 use 2 use 3 use 4 use
Foundation Wall (Plywood) 0.44 0.28 0.25 0.22
Footings 0.14 0.09 0.08 0.07
Slab on Grade 1.2 1.1 1.0 0.8
Columns 0.180 0.146 0.143 0.140
Beams 0.2 0.18 0.15 0.14
Precast Concrete
Double tee
Single tee
I girder
Inverted T beam
Box girder
Hollow core slab
Columns
Channel slab
Wall panel
3/19/2021
11
BCN 5618 21
22
Precast Concrete
Concrete members that are cast in separate forms and then placed in the structure.
Advantages over cast-in-place concrete: faster erection during all weather conditions
consistent finishes because of controlled environment at the plant
sophisticated finishes and shapes may be produced in a plant
for longer spans prestressed concrete is used, either pretensioned or posttensioned.
3/19/2021
12
23
Precast Concrete (Unit)
floor, wall, and ceiling: SF with the thickness noted
beams and columns: LF with each different size kept separately
Anchorage devices, inserts, and any other special requirements must be noted
Responsibility of the supplier regarding installation including welding, finishing of concrete, and caulking must be determined.
Estimating Precast
Simply reinforce or prestressed?
Coordination with:
Mechanical
Electrical
Concrete fill (topping)
Fire rating
Welding