Site works-Excavation

Lecture 7

2

Division 2 – Existing

Conditions

Surveys

Geotechnical Investigation

Site Demolition

Transportation and Disposal of Hazardous Materials

Asbestos Remediation

Lead Remediation

Mold Remediation

3/2/2021

2

3

BCN 5618 4

3/2/2021

3

5

Division 31 - Earthwork

Site Clearing

Earth Stripping & Stockpiling

Excavation and Fill

Erosion and Sedimentation Control

Dewatering

Excavation Support/Protection

6

Earthwork

Specifications

 Excess excavated materials (how far must it be hauled)

 Clearing and grubbing (who is responsible?)

 Topsoil (must it be stockpiled for future use? Where?)

 Trenching for mechanical and electrical work (who is responsible for?)

3/2/2021

4

7

Type of Soil

Soil Borings

Visiting the site

8

Calculating Excavation

 Unit (cubic yard, 1 cy = 27 cf)

 Swell and shrinkage

 1.0 cy in natural condition (bank yard) = 1.25 cy after digging (loose yards) = 0.9 cy after compaction (compacted yards)

 swell factor = loose yard/bank yard

 shrinkage factor = compacted yard/bank yard

3/2/2021

5

9

10

Equipment

 Minimize hand digging and shoveling

 Select suitable equipment  The bulldozer is suitable for moving soil for

short distances only up to about 150 ft.

 Rubber-tired scrapes are excellent for earthmoving up to 1.5 miles.

 Dump trucks are used for hauls beyond the economic range of rubber-tired scrapers.

3/2/2021

6

11

Equipment Selection

 The sheeps foot roller is suitable for compacting very

cohesive soil in lifts of about 6 in or less.

 Vibration is an excellent means of compacting sands,

and vibratory rollers are designed to use this method. It

is normally a steel wheel roller with an auxiliary device to

provide vibration to the roller.

 Pneumatic tired rollers, impart a kneading action as well

as vertical pressure on the soil being compacted. They

are good for sands, gravels, or those materials in

combination with some cohesive material.

12

3/2/2021

7

13

New site grades and rough grading

Cutting and filling to reshape the grade

 Cross Section Method

 For building sites and parking areas

 Dividing the site into a grid and determining the cut or fill for each of the grids

 Average End Area

 For long narrow tracts such as roads

The site is divided into stations

14

3/2/2021

8

15

Labeling Convention

16

3/2/2021

9

17

Fill Volume (Grid 13)

18

Cut Volume (Grid 40)

3/2/2021

10

19

Cut and Fill (Grid 10)

20

3/2/2021

11

21

22

New site grades and rough grading

Cutting and filling to reshape the grade

 Average End Area

 For long narrow tracts such as roads.

 The site is divided into stations;

 a profile at each station line is drawn;

 the cut or fill area of two adjacent profiles is averaged and multiplied by the distance between the two stations.

3/2/2021

12

23

Road Site Plan

24

3/2/2021

13

25

Cut Area Calculation

26

Topsoil Removal

 Unit (cubic yard)

 Depth

 Stockpile location

 Clearance  buildings: 5'

 walks, roadways, and parking areas: 1' to 2'

 Equipment: a bulldozer or a front-end loader

3/2/2021

14

27

General Excavation

 Removal of all types of soil that can be handled in fairly large quantities using power equipment (basement, cut for a highway, ..)

 Add 1' on all sides of the footing to allow workers to install and remove forms

 Allow for the sloping of the banks (angle of repose)

What must be done with the excess excavation?

28

3/2/2021

15

29

Typical Excavation

30

Special Excavation

 Portions of the work that require hand excavation or special equipment other than general excavation (footing holes, small trenches)

3/2/2021

16

31

Backfilling

 Volume of excavation minus volume of the building within the area of excavation.

 Tamping or compaction is required

 Soil shrinkage must be considered

32

Backfill Section

3/2/2021

17

33

Excess and Borrow

 If volume of cut > volume of fill, excess materials must be disposed of

 If volume of fill > volume of cut, shortage materials must be borrowed

 Topsoil is not included in this comparison.

 Consider soil swell for excess materials

 Determine the distance excess materials must be hauled away

 Consider shrinkage for borrowed materials

BCN 5618 34

3/2/2021

18

BCN 5618 35

BCN 5618 36

3/2/2021

19

37

Division 32 – Exterior

Improvements

Base Course

Flexible Paving

Rigid Paving

Landscaping

38

Spreading Topsoil, Finish

Grade

 Stockpiled topsoil is usually placed over the rough grade to make it a finish grade. If the volume is not sufficient, it will have to be purchased.

3/2/2021

20

39

Asphalt Paving

 Unit (SY or Ton)

 Determine the surface area to be paved (SF)

 Determine the compacted thickness of each course and type of materials required (inches)

 Use the following table to find the tonnage of asphalt, granular materials, and subgrade materials.

40

3/2/2021

21

41

Landscaping

 Seeding and fertilizing (type, no. of # per square, area to be covered)

 Sodding (type, area to be filled)

 Trees and shrubs (number, size, and species)

 Maintenance of landscaping and guarantee period