Labor and Equipment
Lecture 5
2
Labor Estimating labor involves determining
how long it will take to do the work involved
what labor types will be required, and at what pay rates.
The unit of time for estimating labor is the hour.
Labor hour
One worker for one hour
3/2/2021
2
3
Factors Affecting Labor Estimate -1
Wage Increase
For large projects that take years to build allowances must be made for pay increase
Availability and Productivity of trained workers
When there is a lot of work available and workers are scarce, labor costs will most likely go up
BCN 5618 4
3/2/2021
3
5
Factors Affecting Labor Estimate - 2 Climatic Conditions- Any weather extremes
will slow down work and may require additional precautions
Too hot, cold, snow, windy
Working Conditions
Restricted/little working space, limited storage space, and difficult delivery situations affect productivity
Actual amount of work time per hour
Overtime
Others (cleanup time, breaks)
6
Breakdown of a Typical Craftworker’s Hour
Waiting 29%
Traveling 13%
Instructions 8%
Tools & materials 7%
Late starts/early quits 6%
Personal breaks 5%
Direct work 32%
3/2/2021
4
BCN 5618 7
8
Best Source
The best source for the estimator to determine labor productivity is to check the company’s past project records and then consult with the general superintendent
3/2/2021
5
Unions
May set:
Wage rates
Wage premiums for shift work, holidays, weekends, and overtime
Fringe benefits including pension, health insurance, vacation, holidays, and sick leave
Unions
May set:
Shift times, lunch breaks, and breaks
Working conditions
Travel and subsistence allowances
Hiring procedures
Rejecting workers
Preference in rehiring past employee
3/2/2021
6
Unions
May set:
Use of union personnel from other neighboring unions
Requiring all labor to be union members and subcontractors to use union labor
Procedures for dispute resolution
12
Closed or Union Shop vs Open Shop
Closed Shop
Employer will not hire any non union member
Union Shop
Employer can hire nonunion workers, but they must join the union
Open Shop
Employer can hire any individual qualified to perform the job
Less restrictive than union
3/2/2021
7
13
Union vs non-union Average productivity for a union worker is lower
than that of equally qualified nonunion worker, because of work rule, lost time due to labor disputes, nonworking job stewards, and paid break periods.
Associated General Contractors of America (AGC) and National Constructors Association (NCA) represent contractors in negotiation with local unions. Associated Builders and Contractors (ABC) represents open shop contractors.
Fair Labor Standards Act
Requires employees must be paid
at least the Federal minimum wage
$7.25 as 2019 (current dispute to $15: yr 2020)
one and a half times the regular pay for hour worked in excess of 40 hours per work week
3/2/2021
8
Fair Labor Standards Act
Employees exempt from minimum wage and overtime:
Executive
Administrative
Professional
Outside sales employees
16
Pricing Labor
Quantity of work
Labor Cost = ---------------------- x Cost per hour
Productivity
Cost per hour = Base hourly cost + Payroll burden
Base Hourly Cost:
Union Scale (union contractors/contracts)
Nonunion Scale (open shop)
Prevailing Wages in the Area (federal projects)
3/2/2021
9
BCN 5618 17
Published Productivity Rates
Figure 7.1
From Means Building Construction Cost Data 2020. Copyright RSMeans, Kingston, MA 781-585-7880; All rights reserved.
3/2/2021
10
19
Payroll Burden Items - 1
Fringe Benefits
vacation pay, employer paid health and welfare costs, pension costs, and training.
Workers’ Compensation Insurance
Fixed Overhead-
Federal and State Unemployment Costs
Social Security Taxes (FICA)
20
Payroll Burden Items - 2
Special Costs:
Overtime Premium Pay
Transportation (mileage or transportation)
Travel Time
Shortened Shift Time (6 am to 1 pm and 1 pm to 8 pm)
Area Premium Pay (unfavorable working conditions)
3/2/2021
11
BCN 5618 21
“Bona Fide” Fringe Benefits
Excludes:
Use of a vehicle
Thanksgiving turkey
Christmas bonus
Workers’ compensation insurance
Unemployment compensation
Social security and Medicare contributions
3/2/2021
12
Burdened Hourly Wage Rate
Burdened wage rate = Wages + Benefits Billable hours
Billable hours exclude:
Vacation
Holidays
Sick leave
Other unbillable time
Pricing Labor
Labor cost = Adjusted labor hours x Weighted average burdened wage rate
3/2/2021
13
Standard Crews
Figure 7.3
From Means Building Construction Cost Data 2020. Copyright RSMeans, Kingston, MA 781-585-7880; All rights reserved.
Equipment
3/2/2021
14
27
Equipment
Site clearing, development of access,
shaping of the site, foundation excavation,
and hoisting and handling materials all
involve the use of a large number of highly
efficient and versatile equipment
The proper selection of these equipment and
the length of time they will have to be used
are an essential part of the estimator’s work
Equipment Costs
Operating costs
Fuel
Lubrication
Filters
Tires
Repairs
Ownership costs
Depreciation
Interest
Insurance
Taxes
Storage
3/2/2021
15
Depreciation & Interest
Cost = P(1+i)ni Fi
(1+i)n - 1 (1+i)n - 1
where:
P = Purchase price
F = Salvage value
i = Interest rate
n = Useful life
Insurance, Taxes, and Storage
Cost = Annual cost / Hours per year
Based upon current bills or historical costs
3/2/2021
16
Fuel Cost
Fuel cost = hp rating × Power utilization × Use factor × Consumption rate × Fuel cost
Consumption rate:
Diesel 0.04-0.06 gallons per hp per hour
Gas 0.06-0.07 gallons per hp per hour
Lubrication & Filters
Oil
Labor
Filters
3/2/2021
17
Tires
Depreciation = Cost / Useful life
Repair
Typically 15% of depreciation
Repairs
Percentage of equipment cost spread over useful life
3/2/2021
18
35
Equipment - 2
The construction equipment used on a
project may be owned, leased, or rented
by a contractor.
The cost of contractor-provided
equipment to a project must be passed
on to the client in the form of equipment
charges that are included within a bid.
36
EQUIPMENT LEASING
A lease normally involves a long period of time, usually approximating the economic life.
With a lease, the depreciation and interest components are replaced completely by the lease payments. Other fixed costs (taxes, licenses, permits, insurance, parking and storage) still remain. Operating costs are also lessee's responsibility and will be handled the same as for owned equipment.
3/2/2021
19
37
EQUIPMENT RENTAL
Rental is the ideal option for short-term equipment need. The rates per unit time are higher than for leasing.
Under most rental agreements, all fixed costs are included within the rental fee.
Maintenance and repair normally are rental agency responsibilities, as would be tires.
Fuel, oil and lubrication costs generally will be the only operating costs (other than the operator himself) to be paid by the renter.
38
Buy, Lease, or Rent
Availability of cash for down payment or outright purchase
current interest rates on loans or installment purchase plans
current rental and lease rates
income tax benefits
expected usage of the equipment
the expected life of the equipment
3/2/2021
20
39
Ownership
Ownership of the equipment can be an
economic drain if the equipment is
underutilized, becomes obsolescent, or
is subject to frequent breakdown as so
often happens when kept too long.
Leasing versus Buying
Benefits:
Flexibility
Reduces risk
Easier than financing
Disadvantages
More costly
No ownership
3/2/2021
21
Leasing versus Buying
Should be based upon cost
Used for long-term equipment needs
Renting versus Buying
Should be based upon cost
Should be rented when needed for a short time
3/2/2021
22
Mobilization
Cost to:
Transportation to and from jobsite
Setup
44
Selecting Equipment
Volume of work to be performed. The size of the job will influence both individual size and numbers of production units.
Job conditions. Each equipment best suited for certain job conditions.
Current Inventory of Equipment. The contractor will attempt to use any available owned or on-hand leased equipment.
Project Schedule. Required job completion date may force use of larger numbers of sizes of equipment.
3/2/2021
23
45
46
3/2/2021
24
47
Loaders
Used for earthmoving and loading.
Can be used as integrated tool carriers.
Available in many sizes and configurations.
“Easily” maintained
Operator “friendly”
48
3/2/2021
25
49
Backhoe Loaders
Very common piece of equipment
Many subcontractors own/lease
Very versatile
Easily transported
“Low” maintenance costs
Operator “friendly”
Easily rented
50
Other Equipment
Dump trucks
Various hauling operations.
Compactors
to consolidates soils in fills, road bases, etc.
Excavator
Used primarily for digging but can be used for demolition with attachments.
Motor grader
Shaping of subgrades, shoulders, ditches, and backslopes;
maintenance of construction roads.
3/2/2021
26
51
52
3/2/2021
27
53
Cranes
Cranes have been one of the most important and widely used pieces of erection equipment since they were first invented.
Every construction job should be looked at on an individual basis before a crane is selected. All variables should be considered.
54
Mobile Cranes
Can travel freely throughout the job site and on the highway.
Do not have to follow a pre- determined path.
3/2/2021
28
55
Mobile Cranes
They are best suited for rural areas, where movement is necessary.
Not well suited for city construction because they have to step back to lift loads over the top of buildings. Usually there is no room for this in a dense city environment.
56
Latticed Boom Cranes
Have high production rates, easy operation, and have a large range of potential uses to the owner
Typically used to:
load sand and gravel at concrete batching plants
load and unload ships
demolish buildings
Usually mounted to truck or crawler base
3/2/2021
29
57
Lattic
58
Telescoping Cantilevered Boom Cranes
3/2/2021
30
59
Telescoping Cantilevered Boom Cranes
Commonly referred to as cherry pickers, zoom booms, or hydraulic cranes.
Can be mounted on any type of carrier or base.
Made of several sections that fit into one another
Virtually no erection and dismantling is needed, saving labor costs.
60
Tower Cranes
3/2/2021
31
61
Tower Cranes
Are best suited for city construction
Work well in confined spaces and have virtually no height limit in the buildings that they can build.
Can operate in higher wind conditions than mobile cranes.
62
Crane Related Accidents
Accidents on construction sites that are related to crane and rigging equipment:
electrocution
overturning
overloading
falls
dropping loads
Most of these accidents are preventable with a proper safety program and training.
3/2/2021
32
63
Equipment Productivity
Factors affecting rate of production of a
piece of equipment:
site conditions
the nature of material being processed
the condition of equipment
operator ability.
64
Determining Productivity
Equipment productivity can be measured in two ways:
On-site: It is measured over a sufficient period to establish
reasonably accurate figures.
Off-site: It is estimated based on productivity data that has
been generated from past company experience or which has
been made available from manufacturer. Manufacturer's
productivity rates are based on ideal conditions. Such rates
should be multiplied by a numerical efficiency factor.