Risk Management

profileVignesh Sivadass
Lecture2M22.pptx

MANG 6143 Project Risk Management Mario Brito

Lecture outline

The other 3 frameworks

Minimum clarity approach

Tools

Recommended Reading

(Chapman and Ward, 2011), chapter 2

(Chapman, 2019), chapter 3

(Chapman, 2019), chapter 7

2

In the previous lecture we have talked about the first important framework of the EP.

In this lecture we are going to cover the other 3 frameworks. And we are going to talk about tools.

2

Key project definition questions – the seven Ws

1. who who are the parties involved? parties
2. why what do the parties want to achieve? motives
3. what what is the deliverable product the parties are interested in? design
4. whichway how will all relevant plans in each lifecycle stage deliver what is needed? plans for: relationships and contracts, business case purposes, operations, activities
5. wherewithal what key resources are required to achieve execution of these plans? resource plans for: operations, activities
6. when when do all relevant events have to take place? integration of all plan-based timetables
7. where where will the project take place? (in location and all other context terms) context

For different lifecycle stages, planners will change the levels of management plans among corporate, operation and project. In the various stages in a different time, planners should focus on different factors. The EP approach uses the 7Ws framework to inject clarity in the each stage.

Go through the list.

In the E&D stage the emphasis should be on the who, why and what.

3

Key project definition questions – the seven Ws

what

the design of

the product

of the project

who

all project parties

ultimately involved

plans for

relationships

and contracts

plans for

operations

why

project motives:

profit and

other motives

plans for

business case

purposes

wherewithal

resource

plans for

activities

when

integration of all

plan-based

timetables

whichway

plans for

activities

resource

plans for

operations

where - the location of the

project and all the relevant

wider context issues

The role of the goals-plan relationship framework

Plans for activities have obvious duration and cost implications.

Resource plans for activities also have cost and duration effects.

Plans for operations have further duration and cost effects.

Resource plans for operations are also relevant.

Plans for relationships and contracts are crucial.

Integration of all plan-based timetables clearly matters.

The design of the product of the process is fundamental.

All the motives for being involved in the project matter.

All the parties involved with relevant plans have relevant motives.

Plans for business case purposes should reflect all the above.

The third level of planning the framework of project risk management is using goals-plans relationship framework. In the E&D stage of the EP this framework links the overall goal of the corporate with the relevant plans in projects. This includes the plans and resources plans for activities and operations with visible durations and cost effects. The plans also involve maintaining relationships and contracts.

5

Our estimation-efficiency spectrum exploration agenda

The minimum clarity to maximum clarity spectrum concept.

The clarity efficiency concept.

The risk efficiency concept.

The opportunity efficiency concept.

‘Best practice’ in these terms.

Clarifying degrees of ‘bad practice’ and ‘common practice’.

Using an initial focus on a ‘primary attribute’.

Multiple attribute trade-offs as integrated concerns.

The need for a process to achieve ‘best practice’.

Before I introduce the next framework lets explore the concepts of efficiency in more detail.

6

Minimum clarity estimation: a simple MoD example

0

probability

(density)

0 2 10 18 20

outcome value in weeks

probability

density

format

0 2 10 18 20

outcome value in weeks

0

1.0

cumulative

probability

0.5

the median (P50)

is equal to the

expected value

and both are

10 weeks

cumulative

probability

format

0.05

0.9

0.1

The approximation involved: a density portrayal

Interval estimates and the ABCs of targets

Using a P10 estimate as a default aspirational target, and alternatives.

Using a P90 estimate as a default commitment target, and alternatives.

Expected values as balanced targets, and alternatives.

Provisions defined by balanced targets less aspirational targets.

Contingencies defined by commitment targets less balanced targets.

Range estimates as the default choice, and point estimate alternatives.

Expected values as an opportunity/risk datum, and alternatives.

Clarifying relationships between opportunity, risk and uncertainty.

Clarifying relationships between plans and outcomes.

A basic probability-impact grid (PIG)

Probability

high

low

low medium high

medium

Impact

p1

p2

p0 = 0

p3 = 1

i0 = 0 i1 i2 i3

r2 r3 r4

r1 r2 r3

r3 r4 r5

Sensitivity diagrams: a high clarity BP example

Sensitivity diagrams: Highways Agency example

Clarity efficiency: ‘efficient frontier’ portrayal

Risk efficient options: ‘efficient frontier’ portrayal

Decision diagrams: one risk efficient choice example

Decision diagrams: two risk efficient choices example

An extract from Sally’s BCS cost estimate and contract

Item description Target minimum Target maximum Target mid-point
Remove old floor covering and prepare the floor surface Lay new flooring Provision for clean-up and other time 4 8 2 12 12 6 8 10 4
Total hours Total cost 14 £ 420 30 £ 900 22 £ 660
Estimated value contract option basis is £ 660 + 10% = £ 726

This is a Chapman and Ward (2011) example used to illustrate very simple modest clarity approaches.

Read the flooring example in Chapman and Ward (2011), chapter 2

Approximate ‘macro-phase’ alignments for three processes

Association for Project Management (APM): Project Risk Analysis and Management (PRAM) Guide (APM, 2004) Institution of Civil Engineers (ICE) and the Institute and Faculty of Actuaries (IFoA): Risk Analysis and Management for Projects (RAMP) (ICE and IFoA, 2005) Project Management Institute (PMI): A Guide to the Project Management Body of Knowledge (PMI, 2009)
Initiate: define the project Initiate: focus the risk management process Organise and define RAMP through the investment lifecycle Plan and initiate risk review Plan risk management
Identify Identify risks Identify risks
Assess: structure ownership estimate evaluate Evaluate risks Perform qualitative risk analysis Perform quantitative risk analysis
Plan risk event responses Plan project risk responses Respond to risks Assess residual risks Plan responses to residual risks Plan risk responses
Implement responses Communicate strategy and plans Implement strategy and plans Control risks Monitor and control risks

Flowchart for the basic SPP

identify all relevant sources,

responses & conditions

structure

all uncertainty

clarify

ownership

quantify

some uncertainty

evaluate

all the relevant implications

to the

appropriate

gateway

stage

capability-culture

assets

capability-culture

liabilities

create & enhance plans

for all relevant concerns

from

project

initiation or a

gateway

stage

select & focus the process

for appropriate clarity

capture the context

with appropriate clarity

shape base plans using

models of some key issues

A bar chart for the first pass of the SPP

ownership

quantify

evaluate

intense effort

on-going effort

no effort or intermittent effort

key:

structure

phase

create & enhance

select & focus

start of the

process

end of the first

complete cycle

capture

identify

shape base plans

Flowchart for the universal process (UP) which underlies the basic SPP

select & focus the process

for appropriate clarity

create & enhance the plans

for all relevant concerns

shape the plans

using models of key issues

test the plans

to ensure robustness

interpret the plans

to exploit creativity

implement the plans

as and when appropriate

a trigger

in some

other

process

return

to an

appropriate

process

capability-culture

assets

capability-culture

liabilities

capture the context

with appropriate clarity

A brief overview of the development of this process, elaborated in Enlightened Planning (Chapman, 2019) chapter 2.

Recommended reading

(Chapman and Ward, 2011), chapter 2

(Chapman, 2019), chapter 3

(Chapman, 2019), chapter 7

22