8 Questions (cost & estimating 2)
2/15/2021
1
CSMT 442
Contracts, Bonds, Insurance, and Specifications
Lecture 2
Construction contract
A written binding agreement between two or more people in a construction venture
Elements of a valid contract
Must be in legal language and include: the date of agreement
the parties involved and their addresses
the name of the project and its location
the name and address of A/E
a list of contract documents to be attached (Specifications, drawings,..)
2
2/15/2021
2
Contract Documents
1. Agreement
2. Project Manual
3. Drawings
3
Agreement Provisions
Scope of work
Time of completion
Start time
Completion time
Calendar days
Date
Liquidated damages
Damages whose amount the contractual parties designate in the contract for the owner or injured party to collect as compensation of a breach (e.g., poor work or late completion).
2/15/2021
3
Agreement Provisions Contract sum
Progress payments
Due date
Retainage
A portion agreed upon in each payment application or contract price (usually 5- 10%) that is withheld until the work is substantially complete to assure that contractor or subcontractor will satisfy its obligations and complete a construction project as laid out in the contract.
Agreement Provisions
Schedule of values
Price for specific items
Work in place and stored materials
How is work completed calculated?
Does the owner pay for stored materials?
2/15/2021
4
Agreement Provisions
Acceptance and final payment
Final inspection
Certification of completion
Acceptance of the work
Contract System
Single contract
Owner contracts with prime contractor
Prime contractor hires subcontractors
A general contractor (GC) is responsible for all of the work required for the completion of a project.
2/15/2021
5
Contract System
Separate contracts
The owner signs separate agreements for the construction of various portions of a project.
Owner contracts separately for:
General construction
Plumbing
Heating, ventilating, and air-conditioning
Electrical
Specialties
Etc.
10
2/15/2021
6
11
Types of Agreements
Lump sum (stipulated sum, fixed price)
The contractor reviews the contract documents and specifies a fixed price (direct costs, indirect costs, overhead, and profit) to finish the project.
Single price for entire job
Unit-price agreement
A price is given for each unit of work
Paid based on actual quantity of work
2/15/2021
7
13
Types of Agreements
Cost-plus-fee
It is often used when speed (construction must begin before the drawings and spec. are completed) and high quality have a higher priority than the desire for the lowest possible price.
Paid for actual construction cost
Plus a fee:
Percentage fee
Fixed fee
Fixed fee with bonus and penalty
2/15/2021
8
Bonds
Bonds are written documents that describe the conditions and obligations relating to the agreement. Under the terms of the bond, the owner is compensated for actual damages sustained from any default of the contractor.
Surety
Guarantees payment on another party’s obligations
Bonding limits based upon
Experience
Work in progress
Bonds
Bid Bond If the contract is awarded to a bidder, the contractor
should enter a contract. If they fail to do so, the bidder must pay the owner the difference between his/her bid and the next lowest bid that the owner accepts and enters into a contract with. If this bidder does not pay the owner, the surety issuing the bond will pay the owner up to the amount of the bid bond. Then the surety will seek repayment of this amount from the bidder who failed to enter into the contract.
The issuance of a bid bond does not prevent the bidder from withdrawing their bid before acceptance.
2/15/2021
9
Bonds
Bid Bond Ensures that if a contractor is awarded the bid
within the time specified, the contractor will enter into the contract and provide all other specified bonds.
Are usually provided by the contractor’s surety free or for a small amount service charge of from $25 to $100.
Are usually between 5 to 10% of the bid price
Submitted with bid
Guarantees the contractor can bond the project
Bid shopping and bid rigging
Bid Shopping/peddling
The act of getting a bid price from one vendor and/or subcontractor and sharing the number with another interested subcontractor or vendor in order to get a lower price from this second subcontractor or vendor.
In general bid shopping (bid peddling) is considered by most in the construction industry to be unethical.
Bid Rigging or Bid Collusion
Describes the actions of bidders who get together to control the distribution of work among themselves by sharing their pricing and choosing among themselves who will bid the lowest number.
This action is not only unethical but by federal and state laws is considered illegal.
2/15/2021
10
Bid depositories
Bid depositories are usually established by associations of contractors, subcontractors and suppliers.
It is a place where subcontractor bids are deposited by bidding subcontractors, according to a set of rules established by the depository founders, for registration and subsequent transmittal to specific bidding general contractors according to a timetable for each project related to the time and date for the latest submission of general contractor bids to the owner.
Bid depositories
The purpose of bid depositories are:
Ensure that sub-bids are deposited by a specified time and date to allow bidding general contractors time to review, analyze and select sub-bids prior to submission of the general bids.
To ensure that all sub-bids are registered and recorded by officials of the depository in the names of the sub-bidders and of the general bidders to who sub-bids will be sent.
Reduce bid shopping (bid peddling)
2/15/2021
11
Bonds
Performance bonds
Guarantees that the contractor will perform all the work in accordance with the contract documents
Most commonly these bonds must be made out in the amount of 100% of the contract price.
The rates vary according to the classification of work being bid on (0.6-2.5%)
Includes warranty period
Bonds
Labor and material bond (payment bond)
Guarantees contractor will pay for:
Labor
Materials used or supplied to the project
2/15/2021
12
Bonds
Subcontractor bonds
Labor and materials bond provided by subcontractor to general contractor
Reduces general contractor’s risk
Preserves general contractor’s bonding capacity
Insurance
The contractor must provide the insurance required by the contract. The insurances normally required by the contracts are: Workmen's/women’s Compensation
Motor Vehicle
Builder's Risk Fire Insurance
24
2/15/2021
13
Insurance
Other insurances usually carried by the contractor:
Health Insurance
Life Insurance
Business Interruption
25
Project Manual or Specification
2/15/2021
14
Project Manual
Accompanies drawings (plans)
Often referred to as specifications
Project manual refers to the written document(s) that accompany the plans
Specification refers to the technical specifications
Part of project manual
CSI
Construction Specifications Institute
Sets standard format for:
Project specification
2012 MasterFormatTM
50 divisions (0 to 49)
2/15/2021
15
Contents of Project Manual
Invitation to bid (Advertisement for bids)
Publicly advertized:
Newspapers
Trade journals
Dodge Reports
Engineering New Record (ENR)
Internet
Contents of Project Manual
Invitation to bid (Advertisement for bids)
Describes:
Location, extent, and nature of work
Bid date and time
Where to obtain documents
Bond requirements
Start and completion dates
2/15/2021
16
Contents of Project Manual
Instruction to bidders (Information for bidders)
Procedures that must be followed by all bidders
How to submit a proposal (bid)
Commencement and completion dates
Bidders responsibilities (i.e. site visit required)
Award or rejection of bid
INVITATION TO BID
Notice is hereby given that bids will be received by Centex Rooney Construction Co., Inc.
(Lic. No. CG C10034) at 2:00 p.m. on Tuesday, November 13, 2001 at Centex Rooney’s
Jacksonville office at 4651 Salisbury Road, Suite 193, Jacksonville, Florida 32256, Ph.
(904) 281-0120, Fax (904) 281-0747. The bids are for Site and Site Utilities Construction
Documents Package for the University of Florida’s Project BR-191, M.E. Rinker, Sr. Hall,
located in Gainesville, Florida. Refer to the “Instructions To Bidders” and the Project
Manual for additional information on the Bidding Process. The following Contract
Documents will be available on Monday, October 29, 2001 at Centex Rooney’s
Jacksonville office at 4651 Salisbury Road, Suite 193, Jacksonville, Florida, Ph. (904) 281-
0120, Fax (904) 281-0747 :
No. Bid Package Description
1 Demolition/Earthwork/Site Utilities/Paving
2 Site Mechanical
3 Site Electrical
All work shall be in strict accordance with the Contract Documents. Drawings,
Specifications, Instructions to Bidders, and other Contract Documents may be reviewed at
Centex Rooney’s Jacksonville office.
A Pre-Bid Conference will be held at the time and location indicated in the Instructions to
Bidders. 32
2/15/2021
17
Contents of Project Manual
Bid (proposal) forms
Standard form that must be submitted by all bidders
Includes:
Price
Last date the proposal may be accepted
Addenda received
Bid security
34
2/15/2021
18
35
Contents of Project Manual
Form of owner/contractor agreement
Contract between owner and contractor
May be:
Standard AIA contract
Company form
Government agency form
2/15/2021
19
37
Contents of Project Manual
General conditions
Clearly spell out the rights and responsibilities of all parties.
Conditions that apply to all aspects of the project
May be:
Standard AIA general conditions
Company document
Government agency document
2/15/2021
20
39
Contents of Project Manual
Supplementary general conditions
Geared to the specific project
Modifies the general conditions
2/15/2021
21
Contents of Project Manual
Specifications (technical specifications)
Describes the required materials and equipment , construction systems, and their fabrication, quality, workmanship, and/or installation details.
Often follows MasterFormatTM
Division 1 - General Requirements
Division 2 – Existing Conditions
Division 3 - Concrete
Contents of Project Manual
Alternates
Request prices for alternate methods or materials of construction.
To allow an owner a choice of what to spend money on.
Add or deduct pricing for:
Alternate methods of construction
Alternate materials
Can be awarded based upon any combination of:
Base bid and
Alternatives
2/15/2021
22
43
Contents of Project Manual
Addenda
Modifies the contract documents after they have been released and prior to the bid
Important to make sure that:
You have seen all the addenda
Your subcontractors and suppliers have seen all of the addenda (addendum)
2/15/2021
23
45
Errors in the Specifications
Errors should be brought to the attention of the architect or engineer
Requests for clarifications of the specifications should be submitted to the architect or engineer so that the clarification can be sent to all bidders
2/15/2021
24
Contract Drawings
Civil
Landscaping
Architectural
Structural
Mechanical, electrical, plumbing, fire protection
47