D4WareHouseMove

Tasks on the critical path

Task

Book location for meeting

Invite Prepare Presentation

Develop Charter/Scope

Develop WBS

Develop Project Plan

Develop Communication Plan

Set schedule for stakeholder

Meet with Framing/Drywall

Meet with Electrical

Meet with Plumbing

Meet with Finish Work

Meet with Student Workers

Obtain Building Permits

Workbenches – Order Supplies

Workbenches – Build

Workbenches-Quality Inspection

Workbenches-Project Sign-Off

Pack non-production equipment

Project Sign-off

Move production equipment

Move non-production equipment

Project Sign-off

Review Contract Work

Release Contractors

Final Report

Archive Documentation

Lessons Learned

Risk Table

1 Permits are not received per the schedule

  This will increase the project timeline because the construction cannot start without obtaining the permit. This is also on the critical path meaning that it is very important and can stall the progress of the project

2 Finish work contractors walk off the job half way

  Other contractors could be brought in to finish the work and it will not stall the project and will not affect the time schedule

3 Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled

  This will affect the resource and dry wall schedule by at most 15 days. This will not be critical.

4 Work benches are poor quality and 1/3 will have to be rebuilt

This will not affect the project at all. The workbenches can be rebuilt as the project progresses.