Project Performance Measurement & Closure

profileTW7809
Larson8e_CH13_PowerPoint_Accessible.pptx

Chapter Thirteen

Progress and Performance Measurement and Evaluation

© 2021 McGraw Hill. All rights reserved. Authorized only for instructor use in the classroom.

No reproduction or further distribution permitted without the prior written consent of McGraw Hill.

Because learning changes everything.®

Where We Are Now

© McGraw Hill

‹#›

2

Learning Objectives

13-1 Identify the four steps for controlling a project.

13-2 Utilize a tracking Gantt to monitor time performance.

13-3 Understand and appreciate the significance of earned value management.

13-4 Calculate and interpret cost and schedule variance.

13-5 Calculate and interpret performance and percent indexes.

13-6 Forecast final project cost.

13-7 Identify and manage scope creep.

© McGraw Hill

‹#›

Chapter Outline

13.1 Structure of a Project Monitoring Information System

13.2 The Project Control Process

13.3 Monitoring Time Performance

13.4 Earned Value Management (EVM)

13.5 Developing a Status Report: A Hypothetical Example

13.6 Indexes to Monitor Progress

13.7 Forecasting Final Project Cost

13.8 Other Control Issues

© McGraw Hill

‹#›

13.1 Structure of a Project Monitoring Information System

A project monitoring system involves

Determining what data to collect

Determining how, when, and who will collect the data

Analysis of the data

Reporting current progress

© McGraw Hill

‹#›

What Data Are Collected?

The data need to answer questions such as

What is the current status of the project in terms of schedule and cost?

How much will it cost to complete the project?

When will the project be completed?

Are there potential problems that need to be addressed now?

What, who, and where are the causes for cost or schedule overruns?

If there is a cost overrun midway in the project, can we forecast the overrun at completion?

© McGraw Hill

‹#›

Collecting Data and Analysis

Will the data be collected by the project team, contractor, independent cost engineers, project manager?

Will the data be derived electronically from some form of surrogate data?

Should the reporting period be one hour, one day, one week, or what?

Is there a central repository for the data collected and is someone responsible for its dissemination?

© McGraw Hill

‹#›

Reports and Reporting

Who gets the progress reports?

How will the reports be transmitted?

When will the reports be distributed?

A common topic format for progress reports

Progress since last report

Current status of project: 1) schedule, 2) cost, 3) scope

Cumulative trends

Problems and issues since last report:

Actions and resolutions of earlier problems

New variances and problems identified

Corrective action planned

© McGraw Hill

‹#›

13.2 The Project Control Process

Control

Is the process of comparing actual performance against plan to identify deviations, evaluate possible alternative courses of actions, and take appropriate corrective action.

Project control steps for measuring and evaluating project performance

Setting a baseline plan

Measuring progress and performance

Comparing plan against actual

Taking action

© McGraw Hill

‹#›

13.3 Monitoring Time Performance

Typical tools used for communicating project schedule status

Gantt chart (bar chart) is the most favored, used, and understandable. It is commonly referred to as a tracking Gantt chart.

Control chart is used to plot the difference between the scheduled and actual times on the critical path at a given point on the project.

Milestone schedules are often used to keep more distal stakeholders informed on the progress of a project.

Milestones are significant project events that mark major accomplishments.

© McGraw Hill

‹#›

Baseline and Tracking Gantt Charts

© McGraw Hill

‹#›

Project Schedule Control Chart

© McGraw Hill

‹#›

13.4 Earned Value Management (EVM)

Earned Value Management

Is a methodology that combines scope, schedule, and resource measurement to assess project performance and progress.

Was pioneered by the U.S. Department of Defense (DoD) in the 1960s.

Uses several acronyms and equations for analysis.

Uses data developed from the work breakdown structure, project network, and schedule.

Starts with the time-phased costs that provide the project budget baseline, which is called the planned budgeted value of the work scheduled (PV). Then comparisons can be made with actual and planned schedule and costs.

© McGraw Hill

‹#›

Glossary of Terms

EV Earned value for a task is the budgeted value of the work accomplished. Work accomplished is often measured in terms of percentages (for example, 25% complete) in which case, EV is simply percent complete times its original budget. [The older acronym for this value was BCWP— budgeted cost of the work performed.]
PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled].
AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work [ACWP—actual cost of the work performed].
CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV − AC.
SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV − PV.
BAC Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.
EAC Estimated cost at completion
ETC Estimated cost to complete remaining work
VAC Cost variance at completion. VAC indicates expected actual over- or underrun cost at completion.

TABLE 13.1

© McGraw Hill

‹#›

Developing an Integrated Cost/Schedule System

Define the work using a WBS.

Scope

Work package

Deliverables

Organization units

Resources

Budgets for each work package

Develop work and resource schedule.

Schedule resources to activities

Time-phase work packages into a network

Develop a time-phased budget using work packages included in an activity called the planned budgeted cost of the work scheduled (PV).

At the work package level, collect the actual costs for the work performed called the actual cost of the work completed (AC). Multiple percent complete with the original budget amount to be earned value (EV).

Compute the schedule variance (SV = EV − PV) and cost variance (CV = EV − AC).

© McGraw Hill

‹#›

Project Management Information System Overview

© McGraw Hill

‹#›

Development of Project Baseline

Purposes of a Baseline (PV)

To measure and report progress

To estimate cash flow

Rules in Assigning Costs to the Baseline

Costs are placed (time-phased) in the baseline exactly as managers expected them to be “earned.”

Percent complete is the workhorse most commonly used. Someone familiar with each task estimates what percent of the task has been completed or how much of the task remains.

What Costs Are Included in Baselines?

Baseline is the sum of the cost accounts and each cost account is the sum of the work packages in the cost account.

Three direct costs are typically included in baselines—labor, equipment, and materials.

© McGraw Hill

‹#›

Methods of Variance Analysis

Comparing earned value with

The expected schedule value

The actual costs

Assessing current status of a project requires three data elements

Planned cost of the work scheduled (PV)

Budgeted cost of the work completed (EV)

Actual cost of the work completed (AC)

Computing schedule variance (SV) and cost variance (CV)

A positive variance indicates a desirable condition, while a negative variance suggests problems or changes that have taken place.

© McGraw Hill

‹#›

Variances

Cost variance (CV) = EV − AC

Tells us if the work accomplished costs more or less than was planned at any point over the life of the project.

Schedule variance (SV) = EV − PV

Presents an overall assessment of all work packages in the project scheduled to date.

Contains no critical path information.

Measures progress in dollars rather than time units.

Variance at completion (VAC) = BAC − EAC

Suggests whether the costs at completion of the project will differ from what was planned.

© McGraw Hill

‹#›

Cost/Schedule Graph

© McGraw Hill

‹#›

Earned Value Review Exercise

© McGraw Hill

‹#›

13.5 Developing a Status Report: A Hypothetical Example

Assumptions

Each cost account has only one work package, and each cost account will be represented as an activity on the network.

The project network early start times will serve as the basis for assigning the baseline values.

From the moment work on an activity task begins, some actual costs will be incurred each period until the activity is completed.

© McGraw Hill

‹#›

Work Breakdown Structure with Cost Accounts

© McGraw Hill

‹#›

Digital Camera Prototype Project Baseline Gantt Chart

© McGraw Hill

‹#›

Digital Camera Prototype Project Baseline Budget ($000)

© McGraw Hill

‹#›

Digital Camera Prototype Status Reports: Periods 1–3

Cost Variance CV = EV − AC
Schedule Variance SV = EV − PV
Status Report: Ending Period 1
Task %Complete EV AC PV CV SV
A 50% 10 10 10 0 0
Cumulative Totals 10 10 10 0 0
Status Report: Ending Period 2
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
Cumulative Totals 20 30 20 −10 0
Status Report: Ending Period 3
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
B 33% 5 10 5 −5 0
C 20% 20 30 20 −10 0
D 60% 21 20 15 +1 +6
Cumulative Totals 66 90 60 −24 +6

TABLE 13.2

© McGraw Hill

‹#›

Digital Camera Prototype Status Reports: Periods 4–5

Status Report: Ending Period 4
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
B Finished 15 20 15 −5 0
C 50% 50 70 50 −20 0
D 80% 28 30 25 −2 +3
Cumulative Totals 113 150 110 −37 +3
Status Report: Ending Period 5
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
B Finished 15 20 15 −5 0
C 60% 60 100 80 −40 −20
D 80% 28 50 35 −22 −7
Cumulative Totals 123 200 150 −77 −27

TABLE 13.2 (Continued)

© McGraw Hill

‹#›

Digital Camera Prototype Status Reports: Periods 6–7

Status Report: Ending Period 6
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
B Finished 15 20 15 −5 0
C 80% 80 110 100 −30 −20
D Finished 35 60 35 −25 0
Cumulative Totals 150 220 170 −70 −20
Status Report: Ending Period 7
Task %Complete EV AC PV CV SV
A Finished 20 30 20 −10 0
B Finished 15 20 15 −5 0
C 90% 90 120 100 −30 −10
D Finished 35 60 35 −25 0
E 0% 0 0 30 0 −30
F 0% 0 0 0 0 0
Cumulative Totals 160 230 200 −70 −40

TABLE 13.2 (Continued)

© McGraw Hill

‹#›

Digital Camera Prototype Summary Graph ($000)

© McGraw Hill

‹#›

Digital Camera Project-Tracking Gantt Chart Showing Status—through Period 7

© McGraw Hill

‹#›

Project Rollup End Period 7 ($000)

© McGraw Hill

‹#›

13.6 Indexes to Monitor Progress

Performance Indexes

Cost performance index (CPI) = EV/AC

Measures cost efficiency of the work accomplished to date

Scheduling performance index (SPI) = EV/PV

Measures scheduling efficiency to date

Project Percent Complete Indexes

Percent complete index budgeted costs (PCIB) = EV/BAC

Percent complete index actual costs (PCIC) = AC/EAC

Management reserve index (MRI) = CV/MR

Is popular in the construction industry

Reflects the amount of management reserves that has been absorbed by cost overruns.

© McGraw Hill

‹#›

Interpretation of Indexes

Index Cost (CPI) Schedule (SPI)
>1.00 Under cost Ahead of schedule
=1.00 On cost On schedule
<1.00 Over cost Behind schedule

TABLE 13.3

© McGraw Hill

‹#›

Indexes Periods 1–7

© McGraw Hill

‹#›

Additional Earned Value Rules

Rules applied to short-duration activities and/or small-cost activities

0/100 rule

Assumes 100% of the budget is earned when the work package is completed.

50/50 rule

Allows 50% of the value of the work package budget to be earned when it is started and 50% to be earned when the package is completed.

Rule used gates before the total budgeted value of an activity can be claimed

Percent complete with weighted monitoring gates

Uses subjective estimated percent complete in combination with hard, tangible monitoring points.

© McGraw Hill

‹#›

13.7 Forecasting Final Project Cost

Two methods used to revise estimates of future project costs

Revised estimated cost at completion (EACre)

Allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate.

Forecasted total cost at completion (EACf)

Uses the actual costs to date plus an efficiency index (CPI=EV/AC) applied to the remaining project work.

© McGraw Hill

‹#›

Forecasting Models: EACre and EACf

Revised estimated cost at completion (EACre) = AC + ETCre

where AC = cumulative actual cost of work completed to date

ETCre = revised estimated cost to complete remaining work

Forecasted total cost at completion (EACf) = ETC + AC

where ETC = estimated cost to complete remaining work

AC = cumulative actual cost of work completed to date

CPI = cumulative cost index to date

BAC = total budget of the baseline

EV = cumulative budgeted cost of work completed to date

© McGraw Hill

‹#›

Another Forecasting Index

To Complete Performance

Used as a supplement to the estimate at completion (EACf) computation.

Measures the amount of value each remaining dollar in the budget must earn to stay within the budget.

A ratio less than 1.00 indicates an ability to complete the project without using all of the remaining budget.

© McGraw Hill

‹#›

Monthly Status Report

Project: Red Octopus (#72) Project manager: Xavier Hart
Project priority now: 4
Status as of: April 1
Earned value figures:
PV EV AC SV CV BAC
588,240 566,064 596,800 −22,176 −30,736 1,051,200
EAC VAC EACf CPI PCIB PCIC
1,090,640 −39,440 1,107,469 .95 .538 .547

Project description: A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter.

Status summary: The project is approximately 25 days behind schedule and $30,736 over budget.

Explanations: The schedule variance has moved from noncritical activities to those on the critical path. Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule. This delay is traced to the loss of the second design team, which made it impossible to start utilities documentation on 2/27 as planned. The cost variance to date is largely due to a design change that cost $21,000.

Major changes since last report: The major change was loss of one design team to the project.

Total cost of approved design changes: $21,000. Most of this amount is attributed to the improved design of the serial I/O drivers.

Projected cost at completion: EACf is estimated to be $1,107,469. This represents an overrun of $56,269, given a CPI of .95.

Forecasted completion date: October 23

Risk watch: Five team members were stricken with flu.

EXHIBIT 13.1

© McGraw Hill

‹#›

13.8 Other Control Issues

Technical performance measurement is as important as measuring schedule and cost performance.

Scope creep causes problems because the “minor refinements” eventually build to be major scope changes.

Baseline changes should be allowed only if it is clear that the project will fail without the change, the project will be improved significantly with the change, or the customer wants it and will pay for it.

Data acquisition is time consuming and costly.

© McGraw Hill

‹#›

Scope Changes to a Baseline

© McGraw Hill

‹#›

Conference Center WiFi Project Communication Plan

What Information? When? Mode? Responsible? Recipient?
Milestone report Bimonthly E-mail Project office Senior management
Time/cost report Weekly E-mail Project office Staff and customer
Risk report Weekly E-mail Project office Staff and customer
Issues Weekly E-mail Anyone Staff and customer
Team meeting times Weekly Meeting Project manager Staff and customer
Outsourcing performance Bimonthly Meeting Project manager Project office, staff, and customer
Change requests Anytime Document Project manager, customer, design Project office, staff, and customer
Stage gate decisions Monthly Meeting Project office Senior management

FIGURE 13.14

© McGraw Hill

‹#›

Key Terms

Control chart

Cost performance index (CPI)

Cost variance (CV)

Earned value (EV)

Earned value management (EVM)

Forecasted total cost at completion (EACf)

Management reserve index (MRI)

Percent complete index actual costs (PCIC)

Percent complete index budgeted costs (PCIB)

Revised estimated cost at completion (EACre)

Schedule variance (SV)

Scheduling performance index (SPI)

Scope creep

To complete performance index (TCPI)

Tracking Gantt

Variance at completion (VAC)

© McGraw Hill

‹#›

End of Main Content

© 2021 McGraw Hill. All rights reserved. Authorized only for instructor use in the classroom.

No reproduction or further distribution permitted without the prior written consent of McGraw Hill.

Because learning changes everything.®

www.mheducation.com

Accessibility Content: Text Alternatives for Images

© McGraw Hill

‹#›

Baseline and Tracking Gantt Charts - Text Alternative

Return to parent-slide containing images.

The Baseline Gantt Chart gives the following baseline durations for several activities: Activity A: Periods 1-2 Activity B: Periods 3-5 Activity C: Periods 3-6 (plus slack for Period 7) Activity D: Periods 6-8 Activity E: Period 7 (plus slack for Period 8) Activity F: Periods 9-12 The Tracking Gantt Chart Showings Status—through Period 6 (Today) Activity A: Baseline duration—Periods 1-2; Actual completed—Periods 1-2 Activity B: Baseline duration—Periods 3-5; Actual completed—Periods 3-5 Activity C: Baseline duration—Periods 3-6 ; Actual completed—Periods 3-5; Slack—Period 7 Activity D: Baseline duration—Periods 6-8; Actual completed—Period 6; Remaining duration—Periods 7-9 Activity E: Actual completed—Period 6; Baseline duration—Period 7; Remaining duration—Period 7; Slack—Period 8 Activity F: Baseline duration—Periods 9-12; Remaining duration—Periods 10-13

Return to parent-slide containing images.

© McGraw Hill

‹#›

Project Schedule Control Chart - Text Alternative

Return to parent-slide containing images.

A graph plots Reporting period to Time periods. A line (labeled “Today”) extends up from Reporting period 6 on the horizontal axis, parallel to the vertical axis. A dashed line extends out from Time period 0 on the vertical axis, parallel to the horizontal axis. The area on the graph above this dashed line represents “Ahead of schedule”; the area below the dashed line represents “Behind schedule.”

A line on the graph connects data points (0,0), (1,-2), (2,-1), (3,-4), (4,0), (5,2), and (6,3).

Return to parent-slide containing images.

© McGraw Hill

‹#›

Project Management Information System Overview - Text Alternative

Return to parent-slide containing images.

The Database is derived from the Scope Deliverables WBS and Organization OBS. The Database consists of the following components:

Work packages

Time

Resources

Labor

Materials

Support effort

Budgets

Responsibilities

Performance standards

The next step is to plan and schedule a baseline, after which Control data (Time, cost, and specifications by Deliverables and Organization) can be generated.

Return to parent-slide containing images.

© McGraw Hill

‹#›

Cost/Schedule Graph - Text Alternative

Return to parent-slide containing images.

The graph plots Project duration to Cost/Percentages.

A “Today” label marks the report date (time period 25) of where the project has been and where it is going. Three lines are shown on the graph. The top line represents the actual costs (AC) incurred for the project work to date. The middle line is the baseline (PV) and ends at the scheduled project duration (45). The bottom line is the budgeted value of the work actually completed to date (EV) or the earned value. The dotted line extending the actual costs from the report date to the new estimated completion date represents revised estimates of expected actual costs.

At the end of period 25, 75 percent of the work was scheduled to be accomplished. At the end of period 25, the value of the work accomplished is 50 percent. The actual cost of the work completed to date is $340, or 85 percent of the total project budget.

Return to parent-slide containing images.

© McGraw Hill

‹#›

Earned Value Review Exercise - Text Alternative

Return to parent-slide containing images.

Four simple cost/schedule graphs plot Time to Cost. Each graph shows lines AC, PV, and EV; in each graph, the time period is at the mid-point of the project, represented by a straight line extending up from the Time axis and running parallel to the vertical axis.

Graph 1:

Top line is AC, curving up gently from (0,0) on the graph and running up rather high on the vertical axis; it stops at the mid-point on the horizontal axis.

Middle line is PV, which runs almost parallel to AC; by the end of the project, it extends to the very top of the vertical axis.

Bottom line is EV, a gentle convex curve extending from (0,0) on the graph to about one-third of the way up the vertical axis; it stops at the mid-point on the horizontal axis.

SV = negative

CV = negative

Graph 2:

Top line is EV, curving up from (0,0) on the graph and running a bit more than halfway up the vertical axis; it stops at the mid-point on the horizontal axis.

Middle line is AC, a gentle convex curve extending from (0,0) on the graph to a bit less than half of the way up the vertical axis; it stops at the mid-point on the horizontal axis.

Bottom line is PV, which has reached about one-quarter of the way up the vertical axis by the mid-point of the project, but which extends to the top of the vertical axis by the end of the project.

SV = positive

CV = positive

Graph 3:

Top line is AC, which makes a concave curve from (0,0) on the graph to about three-quarters of the way up the vertical axis; it stops at the mid-point on the horizontal axis.

Middle line is EV, a much flatter concave curve that extends to a bit less than half of the way up the vertical axis; it stops at the mid-point on the horizontal axis.

Bottom line is PV, which is far below the other two lines by the mid-point of the project, but which curves up in a gentle “S” shape to extend to the top of the vertical axis by the end of the project.

SV = positive

CV = negative

Graph 4:

Top line is PV, which slopes up gently from (0,0) on the graph to the top of the vertical axis by the end of the project.

Middle line is EV, which extends up from (0,0) on the graph at almost a 45-degree angle to about halfway up the vertical axis by the mid-point of the project.

Bottom line is AC, which is an almost straight line extending from (0,0) to about one-quarter up the vertical axis by the mid-point of the project.

SV = negative

CV = positive

Return to parent-slide containing images.

© McGraw Hill

‹#›

Work Breakdown Structure with Cost Accounts - Text Alternative

Return to parent-slide containing images.

  Digital Camera Prototype Design/Build Project $320 (000)
  Design Specifications $20 Shell & Power $15 Memory/Software $100 Zoom System $35 Assemble $120 Test $30
Design $20 CA 1-1 $20          
Shell $15   CA 2-2 $15        
Storage $100     CA 3-3 $100      
Zoom $35       CA 4-4 $35    
Assembly $150         CA 5-5 $120 CA 6-5 $30
OBS: $320            

Return to parent-slide containing images.

© McGraw Hill

‹#›

Digital Camera Prototype Project Baseline Gantt Chart - Text Alternative

Return to parent-slide containing images.

The Baseline Gantt Chart gives the following baseline durations for several activities:

Activity A (Design Spec’s): Periods 1-2

Activity B (Shell & Power): Periods 3-4 (plus slack for Periods 5-6)

Activity C (Memory/Software): Periods 3-6

Activity D (Zoom System): Periods 3-5 (plus slack for Period 6)

Activity E (Assemble): Periods 7-9

Activity F (Test): Periods 10-11

Return to parent-slide containing images.

© McGraw Hill

‹#›

Digital Camera Prototype Project Baseline Budget ($000) - Text Alternative

Return to parent-slide containing images.

Schedule information Baseline budget needs
Time period 0 1 2 3 4 5 6 7 8 9 10 11
ACT/WP DUR ES LF SL Total PV
A           10 10                  
B               5 10              
C               20 30 30 20          
D               15 10 10            
E                       30 40 50    
F                             10 20
Total PV by period 10 10 40 50 40 20 30 40 50 10 20
Cumulative PV by period 10 20 60 110 150 170 200 240 290 300 320

Return to parent-slide containing images.

© McGraw Hill

‹#›

Digital Camera Prototype Summary Graph ($000) - Text Alternative

Return to parent-slide containing images.

The graph plots Time periods to Dollars. “Today” is time period 7. Three lines are shown on the graph: AC, PV, and EV.

As of today, data points for line AC are: (7,230)

As of today, data points for line PV are: (7,200). Additional data points for PV are (8,240), (9,290), (10,300), (11,320).

As of today, data points for line EV are: (7,160)

SV = -40 (the difference between today’s EV and PV)

CV = -70 (the difference between today’s EV and AC)

Return to parent-slide containing images.

© McGraw Hill

‹#›

Digital Camera Project-Tracking Gantt Chart Showing Status—through Period 7 - Text Alternative

Return to parent-slide containing images.

The Gantt chart gives the following durations for several activities:

Activity A (Design Spec’s): Baseline duration—Periods 1-2; Actual completed—Periods 1-2

Activity B (Shell & Power): Baseline duration—Periods 3-4; Actual completed—Periods 3-5; Slack—Periods 6-8

Activity C (Memory/Software): Baseline duration—Periods 3-6; Actual completed—Periods 3-7; Remaining duration—Period 8

Activity D (Zoom System): Baseline duration—Periods 3-5; Actual completed—Periods 3-6; Slack—Periods 7-8

Activity E (Assemble): Baseline duration—Periods 7-9; Remaining duration—Periods 8-10

Activity F (Test): Baseline duration—Periods 10-11; Remaining duration—Periods 12-13

“Today” is period 7.

Return to parent-slide containing images.

© McGraw Hill