19CHAPTER NINETEEN Project Reviews
Subbu Murthy
T HE PURPOSE OF PROJECT reviews depends on the project life cycle (see
Figure 19.1). Understanding the purpose of a review is as important as the
review itself. In the early stages of the project, reviews are typically held to
assess the project impact across the portfolio of other projects, evaluate alternatives,
and make decisions to continue the project or abandon them.
In the planning stages, reviews are held to assess the project costs, schedule, and
risks. They are also held to establish the high-level scope and interfaces with other
projects and to evaluate resource allocations. The reviews in the early stage and the
planning phase play a key role in prioritizing and sequencing the project.
In the execution stage, reviews are focused on understanding the project specifica-
tions (requirements, design, etc.), assessing the progress of the project, and assessing
project quality.
Postimplementation reviews are also crucial as they serve to assess overall
performance and review the key lessons learned. They also help understand the true
causes of variance. In a majority of IT projects, poor specifications and scope creep are
the two strong determinants of cost and schedule variances.
Project reviews share four characteristics: (1) They are measurable, (2) they have
specific goals, (3) they deliver direct or indirect benefits to customers or stakeholders,
and (4) they are triggered by a specific milestone or a preestablished schedule.
187
C o p y r i g h t 2 0 1 1 . W i l e y .
A l l r i g h t s r e s e r v e d . M a y n o t b e r e p r o d u c e d i n a n y f o r m w i t h o u t p e r m i s s i o n f r o m t h e p u b l i s h e r , e x c e p t f a i r u s e s p e r m i t t e d u n d e r U . S . o r a p p l i c a b l e c o p y r i g h t l a w .
EBSCO Publishing : eBook Collection (EBSCOhost) - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY AN: 391434 ; Lane, Dean.; The Chief Information Officer's Body of Knowledge : People, Process, and Technology Account: strayer.main.eds-live
C19 07/14/2011 11:18:53 Page 188
CONCEPTS
Every review must have a purpose, and the purpose must be aligned to the specific
project needs. In addition to identifying the purpose of the review, some of the
fundamental aspects of a project review to consider are the frequency of the review
(weekly versus monthly or quarterly), granularity (detailed versus high level), and
whether reviews are scheduled (weekly, monthly, quarterly) or event driven (such as
completion of a project milestone). The audience for the project review depends on the
purpose of the review. Management, technical architects, developers, quality assurance
personnel, users, finance, and other functions may have to be involved, depending on
the type of review.
While the frequency of review and granularity of reviews depends on the type of
project and the maturity of the team working on the project, it is helpful to recognize
that projects that are unstructured (not very well defined) and more critical to the
enterprise will require more scrutiny. Weekly meetings as opposed to monthly reviews
may be required. The flip side of the equation is the cost entailed in organizing and
conducting the reviews.
It is a very common myth that project reviews always require face-to-face meetings
and are formal. Informal reviews, online project dashboards, and other communication
mechanisms are also part of the project review process and very critical to ensuring
overall success of the project. Formal project reviews are generally planned as milestone
events, but reviews for very complex projects can have mini–life cycles of their own. This
is true for reviews where a critical decision, such as deployment readiness, has to be
assessed. The phrase ‘‘review phase’’ is quite common when reviews are complex and
time consuming.
In addition to compliance with project requirements, the review focus is a
combination of assessing the costs, schedule, quality, and risk of a project. Project
risk can be defined in terms of criticality, degree of clarity in the specifications, and costs.
Projects that are critical, lack clarity of specifications, and are costly to implement are
high-risk projects. In contrast, projects that are not mission critical, cost less, and are
well specified tend to have the least risk.
In general, smaller, mission-critical projects have a schedule focus (see Figure 19.2);
that is, the review focuses on schedule variance since the costs are relatively low and the
schedule of when the projects get completed assumes more importance. However, for
Early Stage Planning Execution Post- implementation
• Assess Impact • Evaluate Alternatives • Make Go/No- Go Decisions
• Assess Cost, Schedule, Risk • Review Resource Allocations • Review Scope
• Review Design • Review Progress • Assess Quality
• Assess Performance • Lessons Learned
FIGURE 19.1 Project Life Cycle
188 & Process
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 189
larger, less mission-critical projects, in addition to schedule reviews, cost variance
reviews are also important. For smaller but mission-critical projects, reviews tend to
focus more on mitigating risk; for mission-critical large projects, the review focus is on all
of the four attributes mentioned.
TYPES OF PROJECT REVIEWS
Some of the common project reviews include:
& Project go/no-go review. The purpose of this review is to assess the project need;
the desired benefits; the fit within the project portfolio with reference to costs,
schedule, and risks; and, most important, how the project aligns to business needs.
The desired outcome is a go/no-decision and project prioritization within the
portfolio of projects. In reality, decisions are not made in one review meeting,
and different levels of granularity of project scope may need to be reviewed,
depending on the audience. For example, finance may be more concerned about
return on investment (cost and tangible benefits) whereas users may be more
concerned about features and prioritization. & Plan review. The purpose of this review is to review the project plan. (Note: For
very small projects that are better treated as tasks, the project plan and review
process may be less formal.) For most projects, the master plan for a project is
usually formally documented in a project plan. The key goals of this review are to
ensure that: & Project governance provides adequate visibility and is in compliance with IT
governance practices.
Schedule Focus
Cost and Schedule
Focus
Cost, Schedule, Risk, and
Quality Focus
Risk and Quality Focus
Small Projects
Large Projects
Less Mission Critical
More Mission Critical
FIGURE 19.2 Review Focus
Project Reviews & 189
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 190
& The project addresses the critical business, user, and technical requirements. & The project vision is understood and shared by all team members. & Project costs, schedules, and resources are realistic. & Project success criteria are clearly established. & Interfaces with other projects and external and internal entities are clearly
identified. & Project quality assurance and reviews are well planned. & Project risks are appropriately identified, and mitigation strategies are proposed. & Project organization has experience in delivering projects.
Note examples of what to look out for to determine if you are going in the right
or wrong direction. & Progress reviews. The purpose of the progress reviews is to review the status of
the project. These reviews address not only the progress to date but the plan for the
remainder of the project and any necessary adjustments. The key goals of this
review are to ensure that: & Project progress (costs, schedules, and resource utilization) is per the plan.
Variance in terms of costs and schedule are tracked. If variances exceed
established thresholds, replanning may be required. It should be noted that
extensive replanning is tantamount to canceling the existing project and
initiating a new one. & Project success criteria are met. An absolute measure is nearly impossible to
achieve. Criteria such as on a scale of 1 to 5 help provide a degree of success of
the project. & Interfaces with other projects and external and internal entities are assessed. & Project technical progress is as per the plan.
Progress reviews address the technical aspects at a milestone level. Some of the
more common progress reviews include preliminary design review, test readiness
review, and deployment review.
The preliminary design review is a key review in the early stages for reviewing
implications to the project scope, schedule, and costs, based on design alternatives
that meet requirements.
The test readiness review assesses the completion of the development and the
readiness to proceed with the testing. One of the key considerations is the quality of
the test plans and the adequacy of both technical resources and users available for
testing.
Deployment reviews help determine whether the developed and tested product
(or service) is ready for use.
The goal of progress reviews is to ensure that mistakes are caught early in the
project life cycle. While there is general agreement that mistakes detected earlier in
the project life cycle are far less expensive than those detected in the later stages of
the project life cycle, there is no uniform data to quantify the costs. Generally it is an
order of magnitude more expensive to correct a mistake during testing as opposed to
detecting it during early stages of the design and a further order of magnitude more
expensive to address postdeployment (see Figure 19.3).
190 & Process
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 191
& Detailed technical reviews. The purpose of these reviews is to ensure com-
pleteness, accuracy, appropriateness, and overall quality of the project. The
reviews depend on the type of project and are typically staged to match the
project life cycle. Software projects, for example, typically include requirements
reviews, design reviews, development (code) reviews, and test reviews. The
quality of the delivered project depends heavily on the quality of the technical
reviews. While the technical collaterals and checklists depend on the nature of
the review (e.g., test reviews should include a mapping to the requirements
specification to ensure that all requirements are tested), they all have a few
common characteristics: & Informal technical reviews should be held frequently to ensure that errors,
omissions, and other issues are caught early in the project life cycle. & In general, detailed technical reviews should not be combined with project
progress reviews. Although cost and schedule considerations are important, the
primary purpose of technical reviews is to ensure overall system quality. & In addition to development teams, users and members of the quality staff are
actively involved in the technical reviews to ensure that the project implemen-
tation meets the stakeholder expectations. & Project sunset review (aka postmortem review). The purpose of this review is
to capture project successes, difficulties, and resulting lessons learned and com-
municate these to the project team and relevant management peers. A common
myth is that project sunset reviews are needed only for projects that were not
deemed successful. These reviews provide very valuable insights and evidential data
to improve existing processes, metrics, and often serve as a baseline for future
projects. Project sunset reviews for successful projects are valuable in that they
reinforce what worked and best practices. Such reviews are arguably more valu-
able for failed projects in that they show what did not work so as to avoid
making similar mistakes in the future. In either case, such reviews provide an
excellent opportunity to reflect and learn.
1X
10X
Preliminary Design Review
Test Readiness Review
Postdeployment
100X
FIGURE 19.3 Cost of Mistakes/Defects
Project Reviews & 191
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 192
PROJECT REVIEW PROCESS
In the past, reviews were almost always conducted face-to-face. Recent advances
in technology have facilitated Web meetings, with tools such as WebEx and
GoToMeeting enabling geographically dispersed teams to collaborate as if they
were sitting next to one another. A few institutions also use social networks to
facilitate project reviews where some of the participants provide ‘‘informal’’ feedback,
such as wikis and tweets. While face-to-face meetings are more common, these newer
forms of collaborating are gaining momentum. Independent of the review modality,
formal project reviews have a mini–life cycle of their own and should be treated in the
context of the project.
The three key stages are preparation, meeting/review, and postmeeting follow-up:
1. The preparation stage is crucial to ensure success of the review. Careful prepara-
tion results in maximum benefits from the review. The review collaterals, review
checklists, audience, review agenda, schedule, and location are critical to a success-
ful review. Typically the review collaterals are sent ahead of time to the reviewers
with instructions and road maps for reviewing. This method is particularly useful
when reviewing large documents. When preparing for the review, the aim is to
ensure that the review goals are met with buy-in from all participants. Review-
meeting planning checklists help facilitate the reviewing planning process. While
checklists and preestablished templates facilitate reviews, they should always be
viewed in the context of the project.
2. Each review should have a review coordinator who conducts the meeting. Also
consider designating a note taker and timekeeper. The assigned note taker is
responsible for taking meeting notes. The note taker records action items that are
then reported in the meeting minutes and any follow-on reviews. The review
coordinator is responsible for leading the meeting, setting the agenda, and creating
the role rotation. On occasion, the review coordinator may be assisted by a
timekeeper to ensure adherence to the meeting agenda. The review agenda may
be modified by the review coordinator as warranted. The note taker will ensure that
all comments and new and open issues are recorded as part of the meeting minutes.
3. During the review or postreview, the action items are reviewed and assigned to
responsible individuals. Any issues/concerns raised during the review are discussed
and adjudicated. Accepted issues will have a corrective action plan and rejected
issues are documented with the appropriate rationale for rejection. All these items
become part of the meeting minutes, which are sent to the reviewers and other
stakeholders as appropriate.
SUMMARY
Project reviews are an essential component of project management. They should
be planned taking into account the nature of the project, culture of the enterprise,
192 & Process
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 193
and project stage. Reviews should be planned to help assess project progress,
technology, and other key variables to ensure that the project is proceeding as
planned. However, care should be taken to ensure that the review process does not
become onerous and dilute the overall purpose of the project. To be successful, all
reviews must be planned, conducted according to preestablished agenda, and have
a follow-up to ensure that they have achieved the desired outcome.
Project Reviews & 193
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use
C19 07/14/2011 11:18:54 Page 194
EBSCOhost - printed on 5/3/2020 12:29 PM via STRAYER UNIVERSITY. All use subject to https://www.ebsco.com/terms-of-use