Continue your project development

1. Identify the warm-up period based on the current setting.

2. Now since a disruption occurred in ABC’s upstream suppliers, the arrival of P1 and P3 are not as reliable as before and their inter-arrival times are following, N~(24,4) and N~(18,3), two normal distributions, respectively. Please choose the proper time window and use Welch’s moving average method to determine the new warm-up period. Also, if the use of oven costs us £10 per minute, then how much is the total cost after 1000 minutes?