| | WBS Number | Level 0 | Level 1 | Level 2 | Level 3 |
| | | 1 | Kitchen Renovation |
| | | 1.1 | Planning and Design |
| | | 1.1.2 | | Research Design Styles |
| | | 1.1.3 | | Develop Preliminary Design |
| | | 1.1.4 | | Secure Funding Source |
| | | 2 | Contractors | Select Subcontractors |
| | | 2.1 | | | Research and Interview Subcontractors |
| | | 2.2.1 | | | Aquire Subcontractors |
| | | 3 | Design | Design Package |
| | | 3.1.1 | | | Demolition Plan |
| | | 3.1.2 | | | Architectural and MEP (Mechanical,Electrical, Plumbing) |
| | | 3.1.3 | | | Cabinetry |
| | | 3.1.4 | | | Appliances |
| | | 3.1.5 | | | Countertops |
| | | 3.1.6 | | | Flooring |
| | | 3.1.7 | | | Electrical |
| | | 3.1.8 | | | Lighting |
| | | 3.1.9 | | | Painting |
| | | 4 | Permits |
| | | 4.1.1 | | Approval | Review and approval of all shop drawings |
| | | 4.1.2 |
| | | 4.1.3 | | Inspection | Book City Inspection (Roughed In) |
| | | 4.1.4 | | | Book City Inspection (Finished Product) |
| | | 4.1.5 | | | Perform City Inspection (Roughed In) |
| | | 4.1.6 | | | Perform City Inspection (Finished Product) |
| | | 4.1.7 | | Cordination | Coordinate subcontractor work |
| | | 5 | Demolition |
| | | 5.1.1 | | Demolition Plan | Site visit |
| | | 5.1.2 | | | Create demolition plan |
| | | 5.1.3 | | | Secure demolition equipment |
| | | 5.1.4 | | | Secure waste container |
| | | 5.1.5 | | | Hire demolition team |
| | | 5.1.6 | | | Structural preperation |
| | | 5.1.7 | | | Clean and prepare site for construction |
| | | 5.1.8 | | | Turn off utilities |
| | | 5.1.9 | | | Pack and secure existing kitchen for reuse |
| | | 5.1.10 | | | Complete demolition |
| | | 6 | Construction |
| | | 6.1.1 | | Procurement of Materials | Estimate quantities |
| | | 6.1.2 | | | Quotes for all subcontractors |
| | | 6.1.3 | | | Issue contract for electrical |
| | | 6.1.4 | | | Issue contract for plumbing |
| | | 6.1.5 | | | Issue contract for mechanical |
| | | 6.1.6 | | | Issue contract for Painting |
| | | 6.1.7 | | | Issue contract for cabinets & counters |
| | | 6.1.8 | | | Issue contract for Kitchen Appliances |
| | | 6.1.9 | | | Issue contract for flooring |
| | | 7 | Mechanical |
| | | 7.1.1 | | | Rough in |
| | | 7.1.2 | | | Install |
| | | 7.1.3 | | | Test |
| | | 8 | Plumbing |
| | | 8.1.1 | | | Rough in |
| | | 8.1.2 | | | Install |
| | | 8.1.3 | | | Test |
| | | 9 | Paint |
| | | 9.1.1 | | | Prime |
| | | 9.1.2 | | | Paint ceiling |
| | | 9.1.3 | | | Paint walls |
| | | 9.1.4 | | | Finish trim |
| | | 10 | Cabinetry & Counters |
| | | 10.1.1 | | | Installation |
| | | 11 | Flooring |
| | | 11.1.1 | | | Installation |
| | | 12 | Appliances |
| | | 12.1.1 | | Installation of Appliances | Refrigerator |
| | | 12.1.2 | | | Dishwasher |
| | | 12.1.3 | | | Microwave |
| | | 12.1.4 | | | Oven |
| | | 13 | Clean Up |
| | | 13.1.1 | | | Remove unused material |
| | | 13.1.2 | | | Remove trash |
| | | 14 | Turnover |
| | | 14.1.1 | | | Sign off on procurement |
| | | 14.1.2 | | | Sign off from customers |