Procurement and Supply Chain Management
1
Module KB7035
Module Title Procurement and Supply Chain Management
Procurement and supply Chain Management Report
Name Dara Easwar Karthik
ID W19042969
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
2
Executive summary
This report presents information necessary to ensure efficient governance of the procurement
process in the $55 million construction of an autonomous but state-funded school in York, which
is being undertaken by a York-based parent-led educational group. In achieving this, the report
has developed a procurement plan that can be used in the project based on the characteristics
of the project and the needs of the client. Consequently, the report established Management
Procurement as the appropriate procurement arrangement suitable in this project as per the
client requirements, including the need for early delivery of the project and constant involvement
in the client in the project. Following this, the Management Contract under JCT is found to be
the most suitable standard form of contract that should be used in this project and the Two-
stage tendering strategy as most appropriate to achieve the most economically advantageous
tender. Since Management Contract requires the client to appoint a Management contractor, the
Prime cost plus management fee is found to be the most applicable mechanism for pricing in
this project. However, the report establishes that contractors, especially subcontractors and
suppliers could see financial challenges under COVID-19 situation under this form of contract
since the client cannot direct the contractors on what to do with the money they pay them.
Owing to this, the reportrecommends that contractors, suppliers and subcontractors be
encouraged to take advantage of the available funding opportunities by the government and that
the main contractor is encouraged to pay their subcontractors and suppliers on time to keep
them afloat.
3
Contents
1.0 Introduction 4
2.0 Detailed procurement plan 5
2.1 Client's organizational characteristics and the client needs 5
2.2 Project characteristics 6
2.3 Most suitable procurement arrangement 7
2.4 Most suitable main standard form of contract 9
2.5 Most suitable tendering strategy 9
2.6 Mechanism for pricing and agreeing on the price for the project 10
3.0 Current situations 11
3.1 Impacts of COVID-19 on the client's procurement strategy 11
3.2 How to manage the COVID-19 issues to enable project success, business
benefits and overall ethical operations 13
Conclusion 13
References 15
Appendixes 18
Appendix 1: Selection of the most appropriate Management Contracting option in the Project 18
Appendix 2: Category groups planning in Procurement and supply chain process 19
4
1.0 Introduction
The construction industry is one of the crucial industry for many countries, often contributing
about 7-10% of the Gross Domestic Product (Eriksson and Westerberg, 2009). However, many
projects tend to fail because of lack of proper procurement procedures and practices (Mabveka,
2018), which makes the procurement process very crucial for any given construction
project.Kafile (2018) and Tiwari et al. (2018) identified increment of project complications, ever-
changing customer's needs and expectations, vulnerability, absence of team integration and the
separation of outline plan from the construction as some of the procurement issues that
construction industry face. To address some of these issues and ensure efficient governance in
projects within the context of the construction industry, a systemic and holistic approach to
procurement procedures is very important (Eriksson and Westerberg, 2009).
Based on this background, this report seeks to present information necessary to ensure efficient
governance of the procurement process in the $55 million construction of an autonomous but
state-funded school in York, which is being undertaken by a York-based parent-led educational
group. The project involves the construction of 14 Classrooms, staff accommodation, laboratory
facilities, VR 3D printing and digital spaces, canteen and dining facilities as well as outdoor
learning and play area. This report is very important in this project because the leading
management team appointed by the parent-led educational promoters as a caretaker board of
trustee do not have wide knowledge and experience in the construction project despite being
involved in making a very important operational decision in the proposed construction of the
above school facilities. As such, this report presents information that will help the Board of
trustee in making appropriate decisions about the procurement processes in the project,
including information relating to how the current situations in the construction industry, such as
COVID-19 could be managed to ensure the project is delivered in the most efficient way
possible.
5
2.0 Detailed procurement plan
2.1 Client's organizational characteristics and the client needs
Understanding the clients' organizational characteristics is a very crucial aspect in the
procurement process since clients are not a homogenous organized group of individuals or
organization and therefore different clients may have different needs and expectations that have
to be considered in the selection of procurement methods so that these individual needs and
expectations can be met (Masterman and Gameson, 1994). Mortledge et al. (2006) note that
this important because of the client's desired level of involvement in project and culture as well
as experience and knowledge influence the choice of procurement method. Thus, the client's
organizational characteristics are very paramount. In this project, the client characteristics can
be summarized as follows, which is based on a framework suggested by Ng et al. (2002);
Characteristics Description
Speed The client wants a speedy procurement process due to the desire that the
project must be completed as soon as possible, not later than May 2022
to enable the smooth opening of the school in September 2022.
Cost certainty The client has already secured a GBP55 million funds for the project.
However, the amount is non-negotiable budget, hence cost certainty is
very important for the client. The project has to be completed within the
budget.
Time certainty The client wants a timely completion of the project since any delay is not
acceptable because it will affect the reputation of the school and delay the
smooth opening of the school in September 2022.
Flexibility Flexibility in the project requirements is not a priority for the client since
new changes will result in additional funding, which is not available for the
client due to a fixed budget. However, the contractor has to ensure the
6
project meets client design specifications and requirements.
Responsibility The client wants to be involved in the project and be informed about the
project over its lifecycle.
Complexity The design theme of the school has to be a natural-looking building with
the outside environment linking with the interior, taking into account the
several external access points and distinct outdoor learning and play
areas. Most importantly, the client requires the school plan to take into
account PV and other sustainable technologies, hence a bit more
complex.
Quality level The client demands first-class facilities that reflect the ambition of the
school as a modern provider of digital and health technology education.
Risk allocation The client wants to be aware of risks and uncertainties in the project
during the procuring process and how this impact the project success.
Price
competition
The client is concerned about value for money and therefore a price
competition in the award of the contract is important as this will allow the
client to compare different tenders and evaluate the one that is most
economically advantageous.
2.2 Project characteristics
According to Love et al. (2009), project characteristics in the construction industry is paramount
in the selection of procurement methods and is concerned with the size, complexity, location
and uniqueness of the project since these can have a significant impact on the project across
key aspects such as the time, cost and risk involved in the project. Most importantly, Love et al.
(2009) developed a framework upon which project characteristics in the construction industry
can be formulated, which is used in this report to establish the project characteristics as follows;
7
Project title UTC autonomous and
state-funded school.
Project start date January 2021
Project value GBP55 million Project completion date May 2022
Contractor Not yet specified Opening of the project to
the public
September 2022
Project location York, in the UK. Project duration 70 weeks
Key project objectives:
To develop first-class school facilities to offer Digital technologies and Health sciences
skills to about 430 pupils.
To complete the project within the budget of GBP55 million.
To complete the project within a period of 70 weeks to May 2022 to allow smooth
opening of the school in September 2022 and avoid the tarnishing reputation of the
school experienced by similar schools in the past where delays were forcing them to
postpone opening by one academic year or temporary accommodation.
To maximize value for money at every stage of the project lifecycle.
Project constraints:
A non-negotiable budget of GBP55 million
A fixed project schedule of 70 weeks
2.3 Most suitable procurement arrangement
According to Love et al. (2009), three common procurement arrangement methods can be
employed in the construction industry: Design and Manage, Management Procurement, and the
Traditional Lump-sum procurement arrangement options. Considering the needs of the client in
this project and the characteristics of the projects as discussed above, the most appropriate
procurement arrangement will be Management Procurement. According to Love et al. (2009),
8
this procurement is most appropriate to a company when there is need for an early start and
early completion of the project, the client and his advisers have insufficient management
resources, the project is organizationally complex thereby demanding multiplicity of consultant
and contractor organizations, and when maximum price competition is necessary for the work to
be carried out in the most economically advantageous way possible, which to be captured in the
client and project characteristics mentioned above. Under the Management Procurement
arrangement, there two options that will be available to the client: Management Contracting, and
Construction Management form of contracts. In selecting the most appropriate option among
these two, the client characteristics are considered using a scale of 1 to 5, where 1 is the least
important criteria and 5 is the highest criteria. The results are as summarized in Appendix 1 of
this report.
The results show that the most appropriate Management Procurement option that fits with client
requirements is the Management Contract (MC) option, with a score of 185 points compared to
Construction Management (CM) option, which has a score of 152 points. According to Love et
al. (2009), under the Management Contracting, the client will be required to appoint both an
independent professional team and management contractor who will be involved in the pre-
construction stages to provide the client with professional advice on the pre-construction
activities since the client has insufficient knowledge in construction project procurements and
management activities. During the construction period, they will take responsibility in ensuring
the project activities are executed as per the direct work contracts. As a result, it is possible to
make an early start on-site and attain early completion. However, for this type of contract to be a
success, there must be a collaboration and trust between the client, contractor and the design
consultants, hence this contract will ensure the client is fully involved over the project lifecycle to
make the project a success. According to Love et al. (2009), it is preferred that the contractor is
selected no later than the design stage. This is crucial since it will ensure that the contractor is
9
involved in providing professional advice on design programme and participate in making
decisions on the other project activities such as the delivery of project materials and the
construction programmes. The role of the management contractor is to carry out the project
activities according to project specifications, project design and drawings, and as per the
contract cost plan prepared by the quantity survey (Love et al., 2009).
2.4 Most suitable main standard form of contract
The two most common standard form of a contract in the construction industry across the globe
and especially in the UK is the Joint Contracts Tribunal (JCT) standard and the NEC standard.
Since the proposed procurement arrangement is the Management Procurement and the most
suitable option under this is the Management Contract, the most suitable main standard form of
contract is JCT, particularly the Management Contract (MC11) according to Jctltd.co.uk
(2020).The MC11 has the same benefits as the Management Contract discussed above,
including the factor that the client will be required to appoint a management contractor to
oversee the entire work in the project and in doing so, the management contractor has to
collaborate and work together with the other contractors and the client to ensure the project is a
success, hence leading to a high to the very high involvement of the client in the project as
expected by the client (The Joint Contracts Tribunal Limited, 2011).
2.5 Most suitable tendering strategy
According to Martens and Smith (2018), from the point of the contracting authority, the most
economically advantageous tender is established based on the cost, using a cost-effective
approach such as life-cycle costing plus other criteria, such social and environmental aspects,
work environment, innovation, and best price-quality ratio. For this to be achieved in a given
project, they argue that there is need to ensure the possibility of effective competition and clear
criteria providing details of how the tenderers were evaluated against the criteria that the results
from the tendering process can be verified and ensure only the most economically
10
advantageous tenderer is awarded contracts. There are three main types of tendering strategies
available in the construction industry: single-stage tendering, two-stage tendering, and
negotiated tendering strategy (Cicmil and Marshall, 2005). Among these tendering strategies
available, the most appropriate one that will ensure the most economically advantageous tender
in line with the requirement of the client and the procurement arrangement mentioned above is
the Two-stage tendering strategy. According to RICS (2017), this strategy is more appropriate in
situations in which there is a time-constrained since it enables design and tendering to overlap.
Since the "Concept design" of the proposed school project has already been completed but the
detail design of the project is yet to be started, using the Two-stage tendering strategy will
ensure that tendering and design can overlap to minimize potential delays in the const ruction
activities of the school owing to the time constraints required in the project. A key benefit of this
tendering strategy is that the design process of the project will benefit from the technical input of
a contractor in the later design stages. Instead of bidding for the entire project work, the
preferred contractor is selected in a competitive process and then joins the design team on a
consultancy basis using a pre-construction services agreement (PCSA). This ensures
collaboration between the design team and the execution contractors, which could address
technical design issues before the preferred contractor presents a bid for the execution of the
project (RICS, 2017). It is the competitive selection of the contractors in this tendering strategy
that will ensure the most economically advantageous tender is achieved as the criteria designed
by the client with help of independent professional consultant is followed in choosing the best
contractor.
2.6 Mechanism for pricing and agreeing on the price for the project
Several pricing mechanisms are commonly used in the construction industry, including cost
reimbursement, measurement contracts, and lump sum contracts among others (Love et al.,
2009). Normally, the pricing mechanism employed has to be consistent with the standard form
11
of contract that is used and to ensure the pricing the contract specifications are compatible.
Since this project uses JCT Management Contact (CM11) form of contract, the pricing used
therefore has to be aligned with the requirement of this contract form. Since the contract
involves a Management contractor responsible for overseeing the overall works in the project,
there pricing has to take into account the fee due to the management contractor for the work
being done. As such, JCT recommends that the pricing mechanism used in this case be the
Prime cost of the Project plus a Management Fee for the management contractor (The Joint
Contracts Tribunal Limited, 2017). To successfully use this mechanism to pricing, the client will
need to have appointed the Management contractor, a Quantity Surveyor and Architect/Contract
Administrator. The Management contractor will be involved in ensuring teamwork between the
Quantity Surveyor, Architect/Contract Administrator and teams involved in the project, including
agreeing constructions methods, the work packages, and contract cost plan. Once this agreed,
the client should be notified by Architect/Contract Administrator that it is practical to undertake
the project and the client can choose whether the project should continue to the next stage or
not.
3.0 Current situations
3.1 Impacts of COVID-19 on the client's procurement strategy
COVID-19 has had unprecedented impacts in many industries across the globe and the
construction industry was not spared either. The industry is expected to see fall of about 20.6%
in output due to COVID-19 impacts on the industry, particularly due to lockdown and travel
restrictions as well as social distancing measures, which were some of the stringent measures
taken by the UK government to mitigate the spread of the virus (MacFarlane, 2020). The
implication of the COVID-19 is more apparent in the supply chain, especially because many of
the construction companies in the UK are small companies and may not have the capacity to
absorb some of the shocks in the industry, including the potential of financial stress due to lack
12
of adequate financial reserves. For instance, Statista (2020) argues that about 93% of the
construction companies in the UK are small companies, with 7 or less number of employees.
With the COVID-19, these companies are more likely to face financial challenges due to
declined construction economic construction activities since they may not have adequate
financial reserves. Furthermore, the large companies, which often subcontract these small
companies are also facing financial constraints during this COVID-19 situation. A survey by
ONS BICS (as quoted by Falconer, 2020) shown that about 53% of the companies in the UK
construction industry argued that their cash reserves would only last up to six months. What this
means is that there is the possibility that the main contractors will benefit from the proposed
contract more than the subcontractors since the client does not have any capacity to dictate
how the subcontractors should be paid under the JCT Management Contract form standard
contract suggested in this report. As such, the subcontractors are at the risk of failing to paid on
time by the main contractors, hence they may delay the project due to lack of adequate
financing, affecting the client. Moreover, if a subcontractor becomes bankrupt, there would be a
need for the contractor to look for alternative subcontractors, which would further delay the
project if no immediate alternative. Things will be worse if the suppliers of the key products and
materials required in the project become insolvency, which will focus the contractor to also look
for an alternative.Furthermore, COVID-19 could also have a significant impact on the way the
project is delivered due to new stringent measures, such as social distancing measures which
may reduce the number of people required in the construction industry. This will have an effect
of increasing the number of hours required to complete a task at a given period, hence may
delay the project delivery.
13
3.2 How to manage the COVID-19 issues to enable project success, business benefits and
overall ethical operations
The biggest issues that arise from COVID-19 is the possibility of contractor, subcontractors, and
suppliers becoming bankrupt, especially small companies which do not have sufficient financial
reserves. To address this, these stakeholders must take advantage of the financial assistance
that the government of the UK is providing to small and medium-sized business, such as the
Bounce Back Loan Scheme (BBLS), which targets SMEs, giving them loans of between 2,000
to 50,000 pounds in an attempt to cushion and enable them to transition to normal in the future
(Gov.uk, 2020). However, there are concerns that the government may run out of money if the
pandemic persists in future (Price, 2020), hence the need for SMEs to innovate and find ways to
generate more money. Unfortunate, there is no possibility that the client in the current project
could dictate how independent contractors should do with their money. However, the client with
help of the management contractors may work together with the main contractor to innovate and
find a way in which the subcontractors and the suppliers can be paid on time to sustain them
over the project life cycle. For instance, a project bank account can be developed where
suppliers and the contractors can be paid directly by the client on request and as per the
directions of the main contractor. This will ensure the main contractor does not exploit the
suppliers and subcontractors as well. Lastly, yet importantly, the contractors and subcontractors
must be encouraged to embrace a culture of working remotely and ensure they comply with
social distancing and other requirements to reduce exposure of workers to the virus, which
could delay the project further.
Conclusion
In conclusion, this report has presented a procurement plan that can be used to ensure the
construction of the state-funded school in York is made possible and delivered on time, and
budget. The report established Management Contract under JCT is the most suitablestandard
14
form of contract that should be used in this project and identified the Two-stage tendering
strategy as most appropriate to achieve the most economically advantageous tender while
Prime cost plus management fee as the most applicable mechanism for pricing in this project in
line with the suggested standard for the contract. However, the report establishes that
contractors, especially subcontractors and suppliers could see financial challenges under
COVID-19 situation under this contract since the client cannot direct the contractors on what to
do with the money they pay them. It is recommended that contractors, suppliers and
subcontractors take advantage of the available funding recommendation by the government and
that the main contractor be encouraged to pay their subcontractors and suppliers on time to
keep them afloat.
15
References
Eriksson, P. E., & Westerberg, M. (2009). Effects of procurement on construction project
performance. In International Conference on Management of Technology: 05/04/2009-
09/04/2009.
Price, D. (2020) 'We will run out of money' – why the COVID-19 rescue packages aren't
working. Retrieved from: https://www.constructionnews.co.uk/agenda/we-will-run-out-of-money-
why-the-covid-19-rescue-packages-arent-working-16-04-2020/
Gov.uk (2020) Apply for a coronavirus Bounce Bank Loan. Retrieved from:
https://www.gov.uk/guidance/apply-for-a-coronavirus-bounce-back-loan
Falconer, T. (2020) Shaky foundations: COVID-19 and the UK Construction Sector. Retrieved
from: https://www.ibisworld.com/industry-insider/coronavirus-insights/shaky-foundations-covid-
19-and-the-uk-construction-sector/
Statista (2020) Total number of construction firms in England as of the third quarter of 2018, by
employment size. Retrieved from: https://www.statista.com/statistics/564797/construction-firms-
size-region-england/
MacFarlane, I. (2020) Full impact of COVID-19 spells uncertainty for the construction sector.
Retrieved from: https://www.showhouse.co.uk/news/full-impact-of-covid-19-spells-uncertainty-
for-construction-sector/
Tiwari, S. T. S., Chan, S. W., & Mubarak, M. F. (2018, April). Critical analysis of procurement
techniques in construction management sectors. In IOP Conference Series: Materials Science
and Engineering (Vol. 342, No. 1, p. 012100).
16
Cicmil, S., & Marshall, D. (2005). Insights into collaboration at the project level: complexity,
social interaction and procurement mechanisms. Building Research & Information, 33(6), 523-
535.
The Joint Contracts Tribunal Limited (2017) Deciding on the appropriate JCT contract 2016.
Retrieved from: https://www.jctltd.co.uk/docs/Deciding-on-the-appropriate-JCT-contract-
2016.pdf
RICS (2017) RICS Professional Guidance, UK. Tendering strategies 1st edition. Retrieved from:
http://www.trentglobal.edu.sg/wp-
content/uploads/2017/01/Tendering_strategies_1st_edition_PGguidance_2014.pdf
Martens, B. and Smith, R. (2018) Evaluation methodologies. Retrieved from:
http://www.ippa.org/images/JOPP/vol17/issue-1/Article_4_Stilger-et-al.pdf
The Joint Contracts Tribunal Limited (2011) Deciding on the appropriate JCT contract 2011.
Retrieved from: https://www.jctltd.co.uk/docs/Deciding-on-the-appropriate-JCT-contract-2011-
Sept-11-version-2.pdf
Jctltd.co.uk (2020) Contract families: Management Building Contract. Retrieved from:
https://www.jctltd.co.uk/category/management-building-contract
Kafile, M. (2018). Effects of procurement processes on project execution in a project
management company in Cape Town, South Africa (Doctoral dissertation, Cape Peninsula
University of Technology).
Mabveka, G. (2013) Project implementation failure: Procurement procedures a scapegoat.
Retrieved from:
https://www.researchgate.net/publication/237062917_PROJECT_IMPLEMENTATION_FAILUR
E_PROCUREMENT_PROCEDURES_A_SCAPEGOAT
17
Love, R. P., Davis, P., Baccarini, D., Wilson, G., & Lopez, R. (2009) Capital Works
Procurement: The Selection of a Building Procurement Method. Research Project No: 2006-
034-C-01.
Masterman, J. W. E., &Gameson, R. N. (1994). Client characteristics and needs in relation to
their selection of building procurement systems. East meets West, 221-228.
Mortledge, R., Smith, A., Kashiwagi, D.T. (2006). Building Procurement. Blackwell, Oxford, UK.
Ng, T., Luu, D., & Chen, S. (2002). Decision criteria and their subjectivity in construction
procurement selection. Construction Economics and Building, 2(1), 70-80.
18
Appendixes
Appendix 1: Selection of the most appropriate Management Contracting option in the
project Selection criteria Client needs and
characteristics
Management Contracting
(MC)
Construction
Management (CM)
How important it is
to the client (1 to 5)
How important it is
to the MC (1 to 5)
Total
Score
How important it is
to the CM (1 to 5)
Total
Score
A B =A*B C =A*C
Speed 5 4 20 3 15
Cost certainty 5 4 20 3 15
Time certainty 5 4 20 3 15
Flexibility 3 5 25 5 15
Responsibility 4 5 20 4 16
Complexity 4 5 20 5 20
Quality level 4 5 20 4 16
Risk allocation 4 5 20 5 20
Price competition 4 5 20 5 20
Overall score 185 152
Ranking 1 2
19
Appendix 2: Category groups planning in Procurement and supply chain process
Source : Futurepurchasing
- Executive summary
- Contents
- 1.0 Introduction 4
- 2.0 Detailed procurement plan 5
- 2.1 Client's organizational characteristics and the client needs 5
- 2.2 Project characteristics 6
- 2.3 Most suitable procurement arrangement 7
- 2.4 Most suitable main standard form of contract 9
- 2.5 Most suitable tendering strategy 9
- 2.6 Mechanism for pricing and agreeing on the price for the project 10
- 3.0 Current situations 11
- 3.1 Impacts of COVID-19 on the client's procurement strategy 11
- 3.2 How to manage the COVID-19 issues to enable project success, business
- benefits and overall ethical operations 13
- Conclusion 13
- References 15
- Appendixes 18
- Appendix 1: Selection of the most appropriate Management Contracting option in
- the Project 18
- Appendix 2: Category groups planning in Procurement and supply chain process 19
- 1.0 Introduction
- 2.0 Detailed procurement plan
- 2.1 Client's organizational characteristics and the client needs
- 2.2 Project characteristics
- 2.3 Most suitable procurement arrangement
- 2.4 Most suitable main standard form of contract
- 2.5 Most suitable tendering strategy
- 2.6 Mechanism for pricing and agreeing on the price for the project
- 3.0 Current situations
- 3.1 Impacts of COVID-19 on the client's procurement strategy
- 3.2 How to manage the COVID-19 issues to enable project success, business benefits and overall ethical operations
- Conclusion
- References
- Appendixes
- Appendix 1: Selection of the most appropriate Management Contracting option in the project
- Appendix 2: Category groups planning in Procurement and supply chain process