project scope statement
Sheet1
| Priority Status | Deadline | Task Progress | ||
| Planning | ||||
| Location selection | High | 28/02/2021 | Done | |
| Mapping process- US to UK | Low | 15/06/2021 | In Progress | |
| General Mapping | Medium | 30/11/2021 | On hold | |
| Legal Duties | High | 5/3/22 | In Progress | |
| Milestone | ||||
| Financing | High | 31/08/2021 | In Progress | |
| Raw Material | Medium | 30/10/2022 | In Progress | |
| Procuring of Machines | Low | 25/07/2022 | On hold | |
| Next Step | ||||
| Hiring employees | Low | 10/9/22 | On hold | |
| Quality Assurance | High | 20/11/2022 | In Progress | |
| Marketing | Medium | 15/12/2022 | On hold | |
| Logistics e.g Transport | Medium | 10/11/22 | In Progress |