Assignment 2

Deadline: Day 17/11/2018 @ 23:59

[Total Mark for this Assignment is 5]

IT Project Management

IT270

https://www.seu.edu.sa/sites/ar/SitePages/images/logo.png

College of Computing and Informatics

Question One

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

4 Marks

Using the information in next Table to answer the below questions:

A) Draw the network diagram?

B) How many paths are in the network, and what are they?

C) What is the critical path and its duration?

D) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF ?

Task

Duration (Days)

Predecessor/s

A

5

-

B

6

-

C

7

-

D

8

-

F

1

A

G

2

B

H

3

C

I

4

D

J

5

F,G,H

K

1

I

L

2

J

M

1

K

N

10

L,M

ANS.

a) Network diagram

b) Paths:

A – F – J – L – N = 23 days

B – G – J – L – N = 25 days

C – H – J – L – N = 27 days

D – I – K – M – N = 24 days

c) Critical path:

C – H – J – L – N = 27 days

d) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF?

Activity Name

Activity Time

Earliest

Start

Earliest

Finish

Latest Start

Latest Finish

Slack

(LS-ES)

A

5

0

5

4

9

4

B

6

0

6

2

8

2

C

7

0

7

0

7

0

D

8

0

8

3

11

3

F

1

5

6

9

10

4

G

2

6

8

8

10

2

H

3

7

10

7

10

0

I

4

8

12

11

15

3

J

5

10

15

10

15

0

K

1

12

13

15

16

3

L

2

15

17

15

17

0

M

1

13

14

16

17

3

N

10

17

27

17

27

0

Project Completion Time =

27

Days

The Critical Path is=

C – H – J – L – N

Question two

Learning Outcome(s):

LO1: Explain the job roles of an IT project manager.

LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.

1Marks

Define Project Management Plan and write its common elements?

A project management plan

is a document used to coordinate all project planning documents and help guide

a project s execution and control. Plans created in the other knowledge areas are considered subsidiary parts of the overall project management plan. Project management plans also document project planning assumptions and decisions regarding choices, facilitate communication among stakeholders, define the content, extent, and timing of key management reviews, and provide a baseline for progress measurement and project control. Project management plans should be dynamic, flexible, and subject to change when the environment or project changes. These plans should greatly assist the project manager in leading the project team and assessing project status.

Major section headings

Section topics

Overview

Purpose, scope, and objectives; assumptions and constraints; project deliverables; schedule and budget summary; evolution of the plan

Project Organization

External interfaces; internal structure; roles and responsibilities

Managerial Process Plan

Start-up plans (estimation, staffing, resource acquisition, and project staff training plans); work plan (work activities, schedule, resource, and budget allocation); control plan; risk management plan; closeout plan

Technical Process Plans

Process model; methods, tools, and techniques; infrastructure plan; product acceptance plan

Supporting Process Plans

Configuration management plan; verification and validation plan; documentation plan; quality assurance plan; reviews and audits; problem resolution plan; subcontractor management plan; process improvement plan

Key outputs included:

· A team contract

· A project scope statement

· A work breakdown structure (WBS)

· A project schedule, in the form of a Gantt chart with all dependencies and resources entered

· A list of prioritized risks (part of a risk register)