help
|
Pg. 06 |
|
|
|
|
|
|
Assignment 2
Deadline: Day 17/11/2018 @ 23:59
[Total Mark for this Assignment is 5]
IT Project Management
IT270
College of Computing and Informatics
|
|
|
|
|
|
|
|
Question One
Learning Outcome(s):
LO1: Explain the job roles of an IT project manager.
LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.
4 Marks
Using the information in next Table to answer the below questions:
A) Draw the network diagram?
B) How many paths are in the network, and what are they?
C) What is the critical path and its duration?
D) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF ?
|
Task |
Duration (Days) |
Predecessor/s |
|
A |
5 |
- |
|
B |
6 |
- |
|
C |
7 |
- |
|
D |
8 |
- |
|
F |
1 |
A |
|
G |
2 |
B |
|
H |
3 |
C |
|
I |
4 |
D |
|
J |
5 |
F,G,H |
|
K |
1 |
I |
|
L |
2 |
J |
|
M |
1 |
K |
|
N |
10 |
L,M |
ANS.
a) Network diagram
b) Paths:
A – F – J – L – N = 23 days
B – G – J – L – N = 25 days
C – H – J – L – N = 27 days
D – I – K – M – N = 24 days
c) Critical path:
C – H – J – L – N = 27 days
d) Find the value of float time/slack time for each task in the network by calculating the value of ES, EF, LS, LF?
|
Activity Name
|
Activity Time |
Earliest Start |
Earliest Finish |
Latest Start |
Latest Finish |
Slack (LS-ES) |
|
A |
5 |
0 |
5 |
4 |
9 |
4 |
|
B |
6 |
0 |
6 |
2 |
8 |
2 |
|
C |
7 |
0 |
7 |
0 |
7 |
0 |
|
D |
8 |
0 |
8 |
3 |
11 |
3 |
|
F |
1 |
5 |
6 |
9 |
10 |
4 |
|
G |
2 |
6 |
8 |
8 |
10 |
2 |
|
H |
3 |
7 |
10 |
7 |
10 |
0 |
|
I |
4 |
8 |
12 |
11 |
15 |
3 |
|
J |
5 |
10 |
15 |
10 |
15 |
0 |
|
K |
1 |
12 |
13 |
15 |
16 |
3 |
|
L |
2 |
15 |
17 |
15 |
17 |
0 |
|
M |
1 |
13 |
14 |
16 |
17 |
3 |
|
N |
10 |
17 |
27 |
17 |
27 |
0 |
|
Project Completion Time = |
27 |
Days |
||||
|
The Critical Path is= |
C – H – J – L – N |
Question two
Learning Outcome(s):
LO1: Explain the job roles of an IT project manager.
LO5: Assess the tasks in the project initiation phase including identifying business requirements, stakeholders, and project team responsibilities.
1Marks
Define Project Management Plan and write its common elements?
A project management plan
is a document used to coordinate all project planning documents and help guide
a project s execution and control. Plans created in the other knowledge areas are considered subsidiary parts of the overall project management plan. Project management plans also document project planning assumptions and decisions regarding choices, facilitate communication among stakeholders, define the content, extent, and timing of key management reviews, and provide a baseline for progress measurement and project control. Project management plans should be dynamic, flexible, and subject to change when the environment or project changes. These plans should greatly assist the project manager in leading the project team and assessing project status.
|
Major section headings |
Section topics |
|
Overview |
Purpose, scope, and objectives; assumptions and constraints; project deliverables; schedule and budget summary; evolution of the plan |
|
Project Organization |
External interfaces; internal structure; roles and responsibilities |
|
Managerial Process Plan |
Start-up plans (estimation, staffing, resource acquisition, and project staff training plans); work plan (work activities, schedule, resource, and budget allocation); control plan; risk management plan; closeout plan |
|
Technical Process Plans |
Process model; methods, tools, and techniques; infrastructure plan; product acceptance plan |
|
Supporting Process Plans |
Configuration management plan; verification and validation plan; documentation plan; quality assurance plan; reviews and audits; problem resolution plan; subcontractor management plan; process improvement plan |
Key outputs included:
· A team contract
· A project scope statement
· A work breakdown structure (WBS)
· A project schedule, in the form of a Gantt chart with all dependencies and resources entered
· A list of prioritized risks (part of a risk register)