Project Management Microsoft Project IT 625
Executive Project Status Summary Wellness Vendor Project
Key Milestones Date Status
Project Kick-Off Meeting 05/05/2015 Complete
Business Requirements Documented/Approved 07/31/2015 Complete
Module 1 Implementation 08/31/2015 Complete
Module 2 Implementation 9/30/2015 Complete
Module 3 Implementation 10/23/2015 Issues
End to end Testing 11/09/2015
Move to Production 11/27/2015 On Track
Project Closure 12/31/2015 On Track
Overall Project Status: Behind Work Effort
Complete: 19%
Project Overview:
The reporting analytics team needs to expand the data warehouse to
ingest third party data feeds from wellness vendors. This information will
be incorporated downstream to employer group analytics and reporting
processes. This expansion will also be used to develop new activity
reports to message value on these products.
Issues / Risks
Issues:
Risks:
Project Manager has left the project. Project milestones are slated to be
behind after this week’s status update.
No updates at this time. New PM to be assigned.
Spend Type
Total Approved
Spend
Total Updated
Spend
% of
Approved Hours Estimated Hours-To-Date Spend-To-Date % Spend
Remaining
Spend % Remaining
Capital Expenditures 277,988$ $50,446 18% 2,342 53 $54,458 20% 223,531$ 80%
Operating Expense 163,662$ $225 1% 1,642 48 $3,825 2% 159,837$ 98%
Total Spend 441,650$ $50,671 19% 3,984 101 $58,283 22% 383,368$ 87%
Accomplishments this Period / Next Steps
Accomplishments:
Additional Contractor Onboarding – complete
Next Steps:
Assign Project Manger ASAP
Cost Detail Analysis Update Approved Spend 19% Complete
Updated By: Nicole Cobb
Project Overview: Business Reinvestment Project Manager: TBD Project Owner: Business Owner Project Sponsor: Sr. VP Operations
Updated Expected Completion Date: N/A IS Manager: N/A Original Expected Completion Date: 12/30/2015
- Confidential - 1