BIA-BCP-DRP-CIRT template fill

profilepavan
ISRMJLAB7.docx

Review Test Submission: Lab #07 Assessment

Content

Course

2019_SPR_MAIN_Info. Security and Risk Mgmt._20_21_COMBINED

Test

Lab #07 Assessment

Status

Completed

Attempt Score

2.4 out of 2.4 points  

Time Elapsed

18 minutes

Results Displayed

Submitted Answers

· Question 1

0.3 out of 0.3 points

True or False: Customer Service business functions typically have a short RTO and RPO maximum allowable time objective.

Selected Answer:

True

· Question 2

0.3 out of 0.3 points

What is the proper sequence of development and implementation for the following?

Selected Answer:

1. Risk Management plan, 2. Business Impact Analysis, 3. Business Continuity plan, then 4. Disaster Recovery plan.

· Question 3

0.3 out of 0.3 points

True or False: If the RPO metric does not equal the RTO, you can potentially lose data that might not be backed up.

Selected Answer:

True

· Question 4

0.3 out of 0.3 points

True or False: The BIA helps define the scope and priorities of the Business Continuity plan and the Disaster Recovery plan.

Selected Answer:

True

· Question 5

0.3 out of 0.3 points

True or False: the BIA is similar to conducting a risk assessment except that it is focused on identifying critical, major and minor business functions and operations.

Selected Answer:

True

· Question 6

0.3 out of 0.3 points

True or False: The BIA’s goal and purpose is to identify IT Infrastructure components that are critical to the organization. 

Selected Answer:

False

· Question 7

0.3 out of 0.3 points

True or False: RTO is what the organization defines as the minimum allowable or acceptable downtime.

Selected Answer:

False

· Question 8

0.3 out of 0.3 points

True or False: the larger the RTO and RPO maximum allowable time, the potentially more expensive the solution.

Selected Answer:

False