ISM650week4assignment.xlsx

Sheet2

Project Start: 01
ID Name Duration Start Finish 8/1/20 8/8/20 8/15/20 8/22/20 8/29/20 9/5/20 9/12/20 9/19/20 9/26/20 10/3/20
Emergency Call Box Project 2020 - waterfall 8/1/20 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 Resources
TASKS Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
2 Tower Site Preparation 18 8/1/20 8/18/20 Project Manager
3 Construct concrete mounting pad 12 8/1/20 8/12/20 site engineer
4 Insert galvanized rods 7 8/12/20 8/18/20 site engineer
5 Hardware Requirements 21 8/18/20 9/7/20 Telecommmunication technicians
6 Concrete diameter slab 7 8/18/20 8/24/20 Telecommmunication technicians
7 Rath Kit, Phillips, Screwdriver, and Torx bit 8 8/24/20 8/31/20 Telecommmunication technicians
8 Spanner Adapter, Adjustable wrench, Analog phone line, and phone cable 8 8/31/20 9/7/20 Telecommmunication technicians
9 Installation 14 9/7/20 9/20/20 Telecommmunication technicians
10 Tower and solar 6 9/7/20 9/12/20 Telecommmunication technicians
11 Panel installation 5 9/12/20 9/16/20 Telecommmunication technicians
12 Battery installation 5 9/16/20 9/20/20 Telecommmunication technicians
13 Wiring 8 9/20/20 9/27/20 Telecommmunication technicians
14 Communication 5 9/20/20 9/24/20 Telecommmunication technicians
15 Phone programming 4 9/24/20 9/27/20 Telecommmunication technicians
16 Testing 9 9/27/20 10/5/20 Telecommmunication technicians
17 Test emergency button 6 9/27/20 10/2/20 Telecommmunication technicians
18 Volume adjustment 3 10/2/20 10/4/20 Telecommmunication technicians
Troubleshootinng 2 10/4/20 10/5/20 Telecommmunication technicians

Sheet3