project management
IST 614 (6W1) – Summer 2021
Cleveland State University
Abdullah Oguz, Ph.D., PMP®
Page 1 of 3
Individual Assignment – 2
• This assignment is due Sunday, June 6, 2021, at 11:59 pm.
• You will work on Microsoft Project for this assignment. You will submit only one MS
Project file on Blackboard.
The following represents an example of a WBS for a process improvement project. It is divided
into three phases. This assignment will include only Phase 1. This WBS was retrieved from the
https://www.projectmanagement.com/ website which is affiliated with PMI.
There are 8 items in the following page. You should complete all of them.
IST 614 (6W1) – Summer 2021
Cleveland State University
Abdullah Oguz, Ph.D., PMP®
Page 2 of 3
1. Create a new blank project on Microsoft Project. Name the file as
“LastName_FirstName_IST614_6W1”. (e.g., Oguz_Abdullah_IST614_6W1.mpp)
2. Create “Project Summary Task”, and name it as “Process Improvement Project”.
3. Insert a column for WBS.
4. Type all the activities (Indent and outdent tasks)
5. Type all the days for each activity based on the table below.
WBS Days Predecessors
1
1.1
1.1.1 3
1.1.2 3 1.1.1
1.1.3
1.1.3.1
1.1.3.1.1 3 1.1.2
1.1.3.1.2 3 1.1.3.1.1
1.1.3.1.3 3 1.1.3.1.2
1.1.3.1.4 3 1.1.3.1.2
1.1.3.2
1.1.3.2.1 3 1.1.3.1.4
1.1.3.2.2 3 1.1.3.1.4
1.1.3.2.3 3 1.1.3.2.1
1.1.3.2.2
1.1.3.2.4 0 1.1.3.2.3
1.1.4
1.1.4.1 3 1.1.3.2.4
1.1.4.2 3 1.1.4.1
1.1.4.3
1.1.4.3.1 3 1.1.4.2
1.1.4.3.2 3 1.1.4.3.1
1.1.4.3.3 0 1.1.4.3.3
1.1.5
1.1.5.1
1.1.5.1.1 3 1.1.4.3.3
1.1.5.1.2 3 1.1.5.1.1
1.1.5.2
1.1.5.2.1 3 1.1.4.3.3
1.1.5.2.2 3 1.1.5.2.1
1.1.5.3
1.1.5.3.1 3 1.1.4.3.3
1.1.5.3.2 3 1.1.5.3.1
IST 614 (6W1) – Summer 2021
Cleveland State University
Abdullah Oguz, Ph.D., PMP®
Page 3 of 3
6. Specify the predecessors for all the activities based on the table above. You should check
them in a dropdown menu in each row on Predecessors column.
7. Confirm that you can see the total project duration on the first row where your project name
is written.
8. Now you can submit your assignment on Blackboard.