WBS PROJECT PLANING

profileBYSTANDER
IFSM_438_Wedding_WBS.pdf.pdf

ID Task

Mode

Task Name Duration Start Finish

0 Wedding WBS 26 days? Mon 01/04/19 Sat 04/05/19 1 Plan for Wedding 26 days Mon 01/04/19 Fri 03/05/19

2 Sign Contract for a church

5 days? Mon 01/04/19 Fri 05/04/19

3 Find church 4 days? Mon 01/04/19 Thu 04/04/19

4 Decide on a church

3 days Mon 01/04/19 Wed 03/04/19

5 Interview with Priest

1 day Thu 04/04/19 Thu 04/04/19

6 Secure church 1 day? Fri 05/04/19 Fri 05/04/19

7 Select date of Wedding

1 day Fri 05/04/19 Fri 05/04/19

8 Reserve the church

1 day Fri 05/04/19 Fri 05/04/19

9 Sign Contract for a reception facility

4 days? Fri 05/04/19 Tue 09/04/19

10 Find suitable reception hall

3 days? Fri 05/04/19 Mon 08/04/19

11 Walk through reception halls

1 day Fri 05/04/19 Fri 05/04/19

12 Decide on location

1 day Mon 08/04/19 Mon 08/04/19

13 Secure reception hall

1 day? Tue 09/04/19 Tue 09/04/19

S S M T W T F S S M T W T

24 Mar '19 31 Mar '19 07 Apr '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

ID Task

Mode

Task Name Duration Start Finish

14 Select date of reception

1 day Tue 09/04/19 Tue 09/04/19

15 Reserve reception hall

1 day Tue 09/04/19 Tue 09/04/19

16 Invite guest 7 days? Mon 01/04/19 Mon 08/04/19

17 Make guest list 5 days? Mon 01/04/19 Fri 05/04/19

18 Decide on number of guest

4 days Mon 01/04/19 Thu 04/04/19

19 Create 100 guest list

1 day Fri 05/04/19 Fri 05/04/19

20 Send out Invites 2 days? Sat 06/04/19 Mon 08/04/19

21 Print out invites

1 day Sat 06/04/19 Sat 06/04/19

22 Mail the invites

1 day Mon 08/04/19 Mon 08/04/19

23 Provide décor/decorations

5 days? Mon 08/04/19 Fri 12/04/19

24 Select décor/decorations

4 days? Mon 08/04/19 Thu 11/04/19

25 Shop for decorations

3 days Mon 08/04/19 Wed 10/04/19

26 decide on decorations

1 day Thu 11/04/19 Thu 11/04/19

S S M T W T F S S M T W T

24 Mar '19 31 Mar '19 07 Apr '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

ID Task

Mode

Task Name Duration Start Finish

27 Purchase décor/decoratins

1 day? Fri 12/04/19 Fri 12/04/19

28 Purchase Decorations

1 day Fri 12/04/19 Fri 12/04/19

29 Setup delivery 1 day Fri 12/04/19 Fri 12/04/19

30 Provide food and beverages

3 days? Mon 15/04/19 Wed 17/04/19

31 Select food menu2 days? Mon 15/04/19 Tue 16/04/19

32 Schedule tasting

1 day Mon 15/04/19 Mon 15/04/19

33 try out menu 1 day Tue 16/04/19 Tue 16/04/19

34 Purchase food 1 day? Wed 17/04/19 Wed 17/04/19

35 Select Menu 1 day Wed 17/04/19 Wed 17/04/19

36 Purchase menu

1 day Wed 17/04/19 Wed 17/04/19

37 Provide lodging and transportation for guest

7 days? Thu 18/04/19 Fri 26/04/19

38 Find suitable lodging

3 days? Thu 18/04/19 Mon 22/04/19

39 Research nearby hotels

3 days Thu 18/04/19 Sun 21/04/19

40 Reserve hotels

1 day Mon 22/04/19 Mon 22/04/19

S S M T W T F S S M T W T

24 Mar '19 31 Mar '19 07 Apr '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

ID Task

Mode

Task Name Duration Start Finish

41 Find transportation

4 days? Tue 23/04/19 Fri 26/04/19

42 Research transportation companies

3 days Tue 23/04/19 Thu 25/04/19

43 Reserve transportation

1 day Fri 26/04/19 Fri 26/04/19

44 Wedding day 0 days Sat 04/05/19 Sat 04/05/19

S S M T W T F S S M T W T

24 Mar '19 31 Mar '19 07 Apr '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

T F S S M T W T F S S M T W T F S S M T W T F S S M

07 Apr '19 14 Apr '19 21 Apr '19 28 Apr '19 05 May '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 5

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

T F S S M T W T F S S M T W T F S S M T W T F S S M

07 Apr '19 14 Apr '19 21 Apr '19 28 Apr '19 05 May '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 6

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

T F S S M T W T F S S M T W T F S S M T W T F S S M

07 Apr '19 14 Apr '19 21 Apr '19 28 Apr '19 05 May '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 7

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

04/05

T F S S M T W T F S S M T W T F S S M T W T F S S M

07 Apr '19 14 Apr '19 21 Apr '19 28 Apr '19 05 May '19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 8

Project: Wedding WBS

Date: Wed 01/05/19

This study source was downloaded by 100000785772547 from CourseHero.com on 06-16-2022 20:32:26 GMT -05:00

https://www.coursehero.com/file/40926806/IFSM-438-Wedding-WBSpdf/

Powered by TCPDF (www.tcpdf.org)